Stormwater Plans, LLC dba SWP Contracting & Paving

CourtArmed Services Board of Contract Appeals
DecidedApril 10, 2025
Docket63900, 63901
StatusPublished

This text of Stormwater Plans, LLC dba SWP Contracting & Paving (Stormwater Plans, LLC dba SWP Contracting & Paving) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stormwater Plans, LLC dba SWP Contracting & Paving, (asbca 2025).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeals of - ) ) Stormwater Plans, LLC dba SWP ) ASBCA Nos. 63900, 63901 Contracting & Paving ) ) Under Contract No. W912QR-17-C-0048 )

APPEARANCES FOR THE APPELLANT: Traeger Machetanz, Esq. Davis Wright Tremaine LLP Seattle, WA

Jonathan A. DeMella, Esq. Davis Wright Tremaine LLP Anchorage, AK

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney James M. Inman, Esq. Zachary J. Grader, Esq. Sean P. Johnson, Esq. Engineer Trial Attorneys U.S. Army Engineer District, Louisville

OPINION BY ADMINISTRATIVE JUDGE WILSON ON THE GOVERNMENT’S MOTION FOR PARTIAL DISMISSAL

These appeals involve a contract between Stormwater Plans, LLC (SWP) and the United States Army Corps of Engineers (USACE) for the reconstruction of parts of an aircraft hangar at Davis-Monthan Air Force base in Tucson, Arizona. SWP alleges that USACE was responsible for delays to the project and seeks $6,669,603.53 in damages (ASBCA No. 63900). SWP also appeals USACE’s affirmative claim for liquidated damages in the amount of $1,237,095 (ASBCA No. 63901). USACE moves to dismiss three claims asserted in SWP’s complaint on the grounds that these claims were never properly presented to the contracting officer (CO): (1) SWP’s allegation that USACE breached the implied duty of good faith and fair dealing; (2) SWP’s claim for the return of liquidated damages for work pertaining to lightweight concrete; and (3) SWP’s contention that the dimensions of the existing “pre-engineered metal building” (PEMB) footing were defective and caused delays and cost increases to the project. SWP opposes the motion and asserts that these allegations stem from the same set of operative facts presented to the CO. For the reasons stated below, we grant USACE’s motion with respect to the lightweight concrete issue, but otherwise deny it.

STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION

1. On September 29, 2017, USACE awarded Contract No. W912QR-17-C-0048 to SWP for the repair of Aircraft Maintenance Unit, Facility 5251 at Davis-Monthan Air Force Base in Tucson, Arizona at a total price of $13,867,032.47 (R4, tab 5 at GovtR4 00178-79, 00185-88).

2. After experiencing various issues and delays during the course of the project, SWP submitted a certified claim to USACE’s CO on June 1, 2023, seeking an equitable adjustment of $6,669,603.53 and a time extension of 771 days for delays allegedly resulting from USACE’s defective designs for the project (R4, tab 3 at GovtR4 00043). SWP’s claim also sought the return of liquidated damages improperly withheld by USACE adding “[g]iven all time extensions reflected herein, SWP is entitled to the release of all amounts withheld as liquidated damages.” (id. at GovtR4 00056; compl. ¶¶ 32, 63).

3. Specifically, SWP’s claim identified actions that USACE took or failed to take that allegedly delayed SWP’s performance, such as USACE’s issuing of an ambiguous and improper notice to proceed (NTP) (R4, tab 3 at GovtR4 00045), delays pertaining to USACE’s review of SWP’s steel joist submittal (id.), changed site conditions affecting Concrete Masonry Unit (CMU) and footing tie in (id.), design issues with the project’s fire suppression system (id. at GovtR4 00049-51), and design issues relating to the project’s fire alarm system (id. at GovtR4 00051-54).

4. On February 21, 2024, the CO issued a final decision (COFD) denying SWP’s claim in its entirety (R4, tab 2). Additionally, the CO asserted an affirmative claim against SWP for $1,237,095 in liquidated damages, $678,709.86 of which had already been withheld by USACE (id. at GovtR4 00039).

5. On May 14, 2024, SWP appealed both the denial of its June 1, 2023 claim and USACE’s affirmative claim for liquidated damages to the Board (R4, tab 1).

6. On May 16, 2024, the Board docketed SWP’s appeals as ASBCA Nos. 63900 and 63901, respectively.

7. On June 17, 2024, SWP submitted its complaint to the Board.

8. SWP’s complaint sought recovery based on theories of change and differing site conditions (compl. ¶¶ 12-13), USACE’s alleged maladministration of the contract (id. at 13-14), defective specifications and USACE’s alleged breach of the implied

2 warranty of constructability (id. at 14-16), and USACE’s alleged breach of the implied warranty of good faith and fair dealing (id. at 16-17). The complaint specifically alleged that the contract completion date was delayed when the alleged maladministration impacted the lightweight concrete placement for the mezzanine area of the project due to USACE’s failure to coordinate with base security in order to allow the concrete trucks access to the base (compl. ¶¶ 15-17, 43). Additionally, the complaint listed affirmative defenses to USACE’s liquidated damages claim and prayer for relief, stating in pertinent part: “The Government’s affirmative claim should be denied in its entirety and the retained liquidated damages in the amount of $678,709.86 should be released to SWP . . .” (id. at 17- 18).

9. SWP’s complaint alleged that the dimensions USACE provided for the existing PEMB footing were defective and resulted in increased costs and delays to the project (compl. ¶¶ 13, 19, 46, 49, 50, 52). Specifically, the complaint asserted that the final drawings did not accurately reflect the existing PEMB support dimensions (id. ¶¶ 13, 19, 46), which constituted a defective specification requiring SWP to perform extra work (id. ¶ 52).

DECISION

The Parties’ Contentions

USACE moves for partial dismissal on the grounds that three of SWP’s claims were never presented to the CO: (1) SWP’s claim that USACE breached the implied duty of good faith and fair dealing (gov’t mot. at 5-6; gov’t reply at 4-5); (2) SWP’s claim for recovery of liquidated damages relating to lightweight concrete work (gov’t mot. at 6; gov’t reply at 5-6); and (3) SWP’s allegations that USACE’s drawings did not accurately reflect the existing PEMB support dimensions (gov’t mot. at 6-7). SWP contends these claims are based on the same set of operative facts as those presented to the CO in its June 1, 2023 claim and therefore are properly before the Board (app. resp. at 1).

Standard of Review

Section 7103(a)(1) of the Contract Disputes Act (CDA), 41 U.S.C. §§ 7101-7109, requires that “[e]ach claim by a contractor against the Federal Government relating to a contract shall be submitted to the contracting officer for a decision.” In other words, a COFD on a claim is a prerequisite for Board jurisdiction. The Board’s jurisdictional requirements over a contractor’s appeal cannot be forfeited or waived. BB Gov’t Servs. Srl, ASBCA No. 63255, 23-1 BCA ¶ 38,303 at 185,962. While the CDA itself does not define the term “claim,” the Federal Acquisition Regulation (FAR) defines a claim as “a written demand or written assertion by one of the contracting parties seeking, as a matter of right, the payment of money in a sum

3 certain, the adjustment or interpretation of contract terms, or other relief arising under or relating to the contract.” FAR 2.101.

As the proponent of the Board’s jurisdiction, SWP bears the burden of proving the Board’s subject matter jurisdiction over these claims by a preponderance of the evidence. Reynolds v. Army & Air Force Exch. Serv., 846 F.2d 746, 748 (Fed. Cir. 1988); Centerra Grp., LLC, f/k/a The Wackenhut Servs., Inc., ASBCA No. 61267, 18-1 BCA ¶ 37,204 at 181,118. To establish Board jurisdiction over its claims, SWP must show that: (1) it has submitted each claim relating to the contract to a CO and (2) the CO has issued a final decision or deemed denial.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Alabama v. North Carolina
560 U.S. 330 (Supreme Court, 2010)
M. Maropakis Carpentry, Inc. v. United States
609 F.3d 1323 (Federal Circuit, 2010)
Centex Corp. v. United States
395 F.3d 1283 (Federal Circuit, 2005)
Placeway Construction Corporation v. The United States
920 F.2d 903 (Federal Circuit, 1990)
Scott Timber Company v. United States
333 F.3d 1358 (Federal Circuit, 2003)
Metcalf Construction Company v. United States
742 F.3d 984 (Federal Circuit, 2014)
K-Con Building Systems, Inc. v. United States
778 F.3d 1000 (Federal Circuit, 2015)
Elgin Builders, Inc. v. United States
33 Cont. Cas. Fed. 74,381 (Court of Claims, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
Stormwater Plans, LLC dba SWP Contracting & Paving, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stormwater-plans-llc-dba-swp-contracting-paving-asbca-2025.