Ruhnau-Evans-Ruhnau Associates v. United States

31 Cont. Cas. Fed. 71,396, 3 Cl. Ct. 217, 1983 U.S. Claims LEXIS 1646
CourtUnited States Court of Claims
DecidedAugust 22, 1983
DocketNo. 511-81C
StatusPublished
Cited by10 cases

This text of 31 Cont. Cas. Fed. 71,396 (Ruhnau-Evans-Ruhnau Associates v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ruhnau-Evans-Ruhnau Associates v. United States, 31 Cont. Cas. Fed. 71,396, 3 Cl. Ct. 217, 1983 U.S. Claims LEXIS 1646 (cc 1983).

Opinion

ORDER

KOZINSKI, Chief Judge.

This case presents the interesting and apparently novel question whether section 12 of the Contract Disputes Act, 41 U.S.C. § 611 (Supp. IV 1980), authorizes payment of interest on an award to a contractor when the underlying claim was presented to the contracting officer by the government.

FACTS

Plaintiff, Ruhnau-Evans-Ruhnau (RER), an architectural engineering firm, contracted to provide drawings and specifications for the renovation of certain Air Force buildings. RER provided the plans and was paid for them. The Air Force subsequently awarded the renovation contract on the basis of RER’s plans. Completion of the renovation contract was delayed 24 days and the contractor persuaded the contracting officer that the delay was caused by errors and omissions in RER’s plans. The contracting officer awarded the contractor an equitable adjustment for losses it suffered as a result of the delay and then issued a final decision that RER was liable to the Air Force for the amount of the adjustment paid the contractor. Plaintiff paid this sum (plus interest) under protest. It then brought suit under the direct access provision of the Act, 41 U.S.C. § 609 (Supp. IV 1980), to recover the money paid.

After trial, the court held that the contracting officer had erred in attributing all 24 days of delay to deficiencies in RER’s plans. The court found that 14 days of delay were attributable to other causes and ordered that a proportionate amount of the [218]*218money RER had paid be refunded to it.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Magnus Pacific Corporation v. United States
133 Fed. Cl. 640 (Federal Claims, 2017)
K-Con Building Systems, Inc. v. United States
107 Fed. Cl. 571 (Federal Claims, 2012)
Tiger Natural Gas, Inc. v. United States
61 Fed. Cl. 287 (Federal Claims, 2004)
Youngdale & Sons Construction Co. v. United States
38 Cont. Cas. Fed. 76,467 (Federal Claims, 1993)
Sun Eagle Corp. v. United States
37 Cont. Cas. Fed. 76,119 (Court of Claims, 1991)
Elgin Builders, Inc. v. United States
33 Cont. Cas. Fed. 74,381 (Court of Claims, 1986)
Hoffman Construction Co. v. United States
32 Cont. Cas. Fed. 73,279 (Court of Claims, 1985)
Z.A.N. Co. v. United States
32 Cont. Cas. Fed. 72,875 (Court of Claims, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
31 Cont. Cas. Fed. 71,396, 3 Cl. Ct. 217, 1983 U.S. Claims LEXIS 1646, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ruhnau-evans-ruhnau-associates-v-united-states-cc-1983.