Cleveland Neighborhood Health Services, Inc. v. St. Clair Builders, Inc.

582 N.E.2d 640, 64 Ohio App. 3d 639, 1989 Ohio App. LEXIS 5233
CourtOhio Court of Appeals
DecidedOctober 2, 1989
DocketNo. 55734.
StatusPublished
Cited by21 cases

This text of 582 N.E.2d 640 (Cleveland Neighborhood Health Services, Inc. v. St. Clair Builders, Inc.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cleveland Neighborhood Health Services, Inc. v. St. Clair Builders, Inc., 582 N.E.2d 640, 64 Ohio App. 3d 639, 1989 Ohio App. LEXIS 5233 (Ohio Ct. App. 1989).

Opinion

Martin, Judge.

Appellant, Cleveland Neighborhood Health Services, Inc., appeals the judgment of the trial court wherein it was determined that appellant owed appellee, St. Clair Builders, Inc., $147,881.15 on a construction contract. This judgment amount was later reduced to $107,881.15 due to a clerical error that was brought to the court’s attention via appellant’s Civ.R. 60(A) motion.

The construction contract at issue arose in 1984 when appellant began soliciting bids to have alterations and additions made on a building located on Superior Avenue in Cleveland, Ohio (“Superior Project”). Appellee was awarded the contract and January 2,1985 was set as the start-up date for the project.

Due to difficulty in acquiring the necessary permits for the job and the inclement weather conditions, the project was not begun until the first week in March. The record indicates that all parties were aware of the delays and raised no objections to the delayed start. Also, appellant agreed to extend the completion date from June 1, 1985 to at least July 1, 1985.

In addition to the Superior Project, appellant also hired appellee to work on three separate construction jobs. The sites for these jobs were in the Collinwood area, oil Miles Avenue, and on East 82nd Street. Appellee was *642 authorized to begin work at these areas in April, May and June 1985, respectively.

Appellant argues that during the time when the Superior Project was under way, several problems arose. Many of the difficulties involved seemed to be a lack of conformity in the specifications required for the job. Appellant hired architect Neil Guda to prepare the plans for the renovations at the Superior site. However, several changes were made before final copies were given to appellee. The record also reveals that appellant required appellee to alter the building plans along the way, which created further delays and confusion over the actual construction work needed.

During the time when appellee was working on the Superior Project, it was paid according to the American Institute of Architects (“AIA”) draw forms. Appellee would list the percentage of work completed, and then request payment from appellant for that amount. Appellee’s first request was for $59,939.55, which reflected work completed from January 7, 1985 through April 26, 1985. This amount was paid. Appellee’s second request was for $73,203.30 for work performed from April 26, 1985 through June 17, 1985, which sum appellant also paid.

In August 1985, appellee submitted its third draw request to appellant for work performed from June 17, 1985 through August 2, 1985. This request was denied, and appellee was subsequently fired by appellant by September 4, 1985.

On November 19, 1985, appellant filed suit against appellee alleging breach of contract, breach of warranty, and a claim for out-of-pocket expenses and lost revenue. Appellee filed an answer and counterclaim asserting that appellant had breached the Superior Project contract and owed money on the Collinwood, Miles Avenue, and East 82nd projects as well.

On January 24, 1988, a bench trial commenced whereby the parties submitted all evidence relative to the disputes at issue. Following the trial, counsel for appellee submitted a letter to the court setting out the figures presented at trial which reflected the amounts owed to appellee for work completed on the various construction projects. This letter also pointed out to the court that a clerical error had been made in prior calculations. The corrected error was subsequently adopted by the court’s judgment entry.

In February 1988, the parties submitted proposed findings of fact and conclusions of law to the trial court. The judgment subsequently rendered by the trial court was in favor of appellee, and appellant was found to be liable for the outstanding amounts owed on the four projects.

*643 Appellant moved the trial court for findings of fact and conclusions of law pursuant to Civ.R. 52. The trial court complied with this request.

From that judgment, appellant filed a notice of appeal to this court. Appellee filed a cross-appeal. Thereafter, appellant filed a Civ.R. 60(A) motion to have the case remanded to the trial court for correction of the clerical error in the judgment amount. This motion was granted.

On remand, appellee moved for reconsideration of its earlier request for prejudgment interest. The trial court granted appellee’s motion.

On review of the decision rendered by the trial court, this court is presented with six assignments of error.

“I. The trial court erred when it accepted and adopted defense counsel’s off-the-record, ex-parte letter.
“II. The trial court clearly erred in calculating the damages awarded to St. Clair.
“III. The trial court erred in determining that St. Clair completed 100% of the Superior contract.
“IV. The trial court erred in finding that St. Clair had not breached the Superior contract.
“V. The trial court erred by disallowing the consequential damages incurred by Health Services regarding the out-of-pocket costs of doctors and lost revenues.
“VI. The trial court erred in awarding to St. Clair prejudgment interest.”

Appellant’s first assignment of error claims that prejudice resulted when the trial court accepted an ex-parte letter from appellee’s counsel. This contention has no merit.

The letter at issue contained figures which listed the amount of money owed to appellee for work done under the construction agreement with appellant. In issuing findings of fact and conclusions of law, the trial court adopted these figures as valid in terms of the total amount owed. These figures were incorporated into the findings issued by the court.

It was later discovered that the judgment figure entered by the trial court was erroneous. Appellee had mistakenly added $40,000 to the documentation of outstanding bills. This $40,000 amount had already been paid to appellee as an advance on work performed under contract.

Even though the trial court was in error for adopting the incorrect figures proposed by appellee, this error was subsequently corrected. While we accept the fact that the trial court has the duty to examine such documentation thoroughly to ensure that it is accurate in law and fact, no prejudice resulted *644 in this case. Cf. Paxton v. McGranahan (Oct. 31, 1985), Cuyahoga App. No. 49645, unreported, 1985 WL 6444.

In appellant’s Civ.R. 60(A) motion, this error was brought to the attention of the trial court and corrected. Thus, any error that may have occurred did not prejudice appellant.

Appellant’s first assignment of error is without merit.

Appellant’s second, third and fourth assignments of error will be discussed jointly as they all challenge the trial court’s decision as being against the weight of the evidence, and allege that the findings of fact and conclusions of law issued by the trial court were erroneous.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United Assn. Local 168, Apprentice Educational Fund v. Robinson
2025 Ohio 2421 (Ohio Court of Appeals, 2025)
Francis v. Signature of Solon Home Owners Assn. Bd. of Trustees
2024 Ohio 6017 (Ohio Court of Appeals, 2024)
Cuyahoga Cty. Treasurer v. Henen
2024 Ohio 2263 (Ohio Court of Appeals, 2024)
Kumar v. USA Insulation
2018 Ohio 5332 (Ohio Court of Appeals, 2018)
Huntington v. Greer
2016 Ohio 5100 (Ohio Court of Appeals, 2016)
Whitt Sturtevant, L.L.P. v. NC Plaza L.L.C.
2015 Ohio 3976 (Ohio Court of Appeals, 2015)
Watershed Mgt. v. Neff
2014 Ohio 3631 (Ohio Court of Appeals, 2014)
Marks v. Swartz
882 N.E.2d 924 (Ohio Court of Appeals, 2007)
Tucker v. Young, Unpublished Decision (3-6-2006)
2006 Ohio 1126 (Ohio Court of Appeals, 2006)
Zolg v. Yeager
701 N.E.2d 723 (Ohio Court of Appeals, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
582 N.E.2d 640, 64 Ohio App. 3d 639, 1989 Ohio App. LEXIS 5233, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cleveland-neighborhood-health-services-inc-v-st-clair-builders-inc-ohioctapp-1989.