Chaney v. Ramsey, Unpublished Decision (4-7-1999)

CourtOhio Court of Appeals
DecidedApril 7, 1999
DocketCase No. 98 CA 614
StatusUnpublished

This text of Chaney v. Ramsey, Unpublished Decision (4-7-1999) (Chaney v. Ramsey, Unpublished Decision (4-7-1999)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Chaney v. Ramsey, Unpublished Decision (4-7-1999), (Ohio Ct. App. 1999).

Opinion

This is an appeal from a judgment entered by the Pike County Common Pleas Court dismissing a complain filed by Jeffrey Chaney, plaintiff below and appellant herein, and granting the first claim for relief in a counterclaim filed by appellant's cousin Roger Ramsey and his wife, Nancy Ramsey, defendants below and appellees herein.

Appellant assigns the following errors:

FIRST ASSIGNMENT OF ERROR:

"THE LOWER COURT ERRED IN DETERMINING THAT PLAINTIFF HAD BREACHED THE CONTRACT DUE TO LACK OF COMPLETION IN A REASONABLE TIME AND FAILED TO CONSIDER THE DOCTRINE OF SUBSTANTIAL PERFORMANCE."

SECOND ASSIGNMENT OF ERROR:

"THE TRIAL COURT ERRED IN DETERMINING THAT DEFENDANTS DID NOT BREACH THE CONTRACT."

THIRD ASSIGNMENT OF ERROR:

"THE LOWER COURT ERRED IN ITS AWARD OF DAMAGES."

On February 1, 1995, the parties signed a contract stating that appellant would construct a house for appellees for $125,000. The contact described the house and specified allowances for kitchen and bath cabinetry, plumbing fixtures, lighting, carpeting, and climate control systems. The parties later agreed on various modifications to the contract.

Appellant began construction in May 1995. During the next year, appellees placed money in a construction account. Appellant drew money from the construction account and paid for the majority of supplies, labor, and materials for the house. By June 1996 appellees had paid a total of $117,000 for the house, but estimated that the house was only sixty to seventy percent complete.

On June 25, 1996, appellees sent appellant a letter ordering appellant to cease all work on the house. Appellant ceased work as ordered. Appellees hired other contractors to finish the house.

On October 21, 1996, appellant filed the instant complaint alleging as follows:

"1. Whereas on or about February 1, 1995, Plaintiff proposed to build a house on land of Defendant, located at 118 Stafford Drive, Waverly, Ohio 45690, Pike County, for one hundred twenty five thousand dollars ($125,000.00), and Defendant accepted said proposal (exhibit A).

2. During the construction the parties entered into subsequent oral agreements to modify the original contract, thereby increasing material costs and Defendant's obligation to Plaintiff in the amount of thirteen thousand three hundred eighty-seven dollars and twenty cents ($13,387.20) (exhibit B).

3. On June 25, 1996 Defendant notified Plaintiff that he was to cease all work relating to said construction. Plaintiff was instructed to remove all personally owned tools, and materials were to remain at the worksite (exhibit C).

4. The amount due Plaintiff on June 25, 1996 was fifteen thousand two hundred forty seven dollars and twenty cents ($15,247.20).

5. On July 25, 1996 Plaintiff gave notice of a claim of lien in regard to the unpaid balance on Defendant's property at 118 Stafford Drive, Waverly, Ohio 45690.

6. As a result of Defendant's breach of contract, Plaintiff has suffered damages in the amount of fifteen thousand two hundred forty seven dollars and twenty cents ($15,247.20)."

Appellant prayed for judgment in the amount of $15,247.20.

On November 22, 1996, appellees filed an answer and counterclaim. In the answer, appellees admitted that they agreed to certain modifications to the contract, but argued that those agreed modifications did not include all the modifications alleged by appellant. In the first claim for relief in their counterclaim, appellees alleged that appellant: (1) failed to construct the house in a timely manner; (2) failed to pay materialmen and subcontractors even though appellees had provided appellant with money for that purpose; (3) failed to reimburse appellees for materials purchased directly by them even though appellant had received money from appellee for those items; and (4) failed to construct in a workmanlike manner the portion of the house that he did complete before June 25, 1996. Appellees further alleged that as a result of appellant's actions, appellees incurred damages in the amount of $22,340.67 and will incur future damages because the house is not yet complete.1

When answering appellees' request for admissions, appellant admitted that as of June 25, 1996:

"8. * * * [he had] been paid a total sum of $117,000 by the Defendants.

* * *

13. * * * the siding on the Defendants' home was not properly completed or finished.

14. * * * no interior trim or stairway work was completed in the Defendants' home.

15. * * * no trim was installed in the Defendants' home.

20. * * * no outside concrete had been poured at the Defendants' residence.

22. * * * no outside concrete had been poured at the Defendant's residence.

23. * * * the garage at the Defendants' home had not been completed.

24. * * * no electric wiring had been installed in the garage at the Defendants' home.

25. * * * the front porch deck at the Defendants' home had not been completed.

26. * * * no grading had been done around the Defendants' home.

27. * * * no interior finished floors had been installed at the Defendants' home and that only sub-flooring was installed."

On February 9-10, 1998, the trial court heard the matter. Appellant testified that appellees' house was the first house he built. He further testified that he broke ground on May 12, 1995 and the house was ninety percent complete on June 25, 1996 when appellees ordered him to cease work. Appellant explained that rainy weather in May and June 1995 delayed foundation work on the house and cold weather the following winter delayed other work on the house. According to appellant, the parties agreed to modifications worth $13,387.

On cross-examination, appellant admitted that during a deposition when asked how much money he budgeted for overhead profit, he testified "I didn't allow any, just if there was any left over that would have made a profit," and during the same deposition when asked if he was hoping to build the home as a break even project appellant answered "yes." On cross-examination at trial appellant further admitted that he used the construction account to make payments on his Bobcat and he withdrew $5,000 from the construction account shortly before he purchased a BMW automobile for himself. Later during the trial, appellant admitted that of the $117,000 he received from appellees for the house construction, he used only $80,000 for labor and materials.

Appellant gave the following testimony on cross-examination concerning his deposition testimony and whether he had made any promises to appellees regarding when the house would be finished:

"Q. You were under oath at that time. Question: Do you recall giving Mr. and Mrs. Ramsey an estimate when you began construction as to when you thought you would have their home completed? Answer: I think I did. Question: And do you recall what that was? Answer: I believe I told them it would be about seven months or so. Do you now recall that you gave them that estimate?

A. If that's what I said then, yes. I just didn't recall answering at the time.

Q. Do you recall when it wasn't done in seven months that you then told them it would be ready by Thanksgiving?

A. The seven month time period would have been around Thanksgiving.
Q. Did you then tell them it would be ready by Christmas?
A. I don't recall.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jones v. Honchell
470 N.E.2d 219 (Ohio Court of Appeals, 1984)
Kersh v. Montgomery Developmental Center
519 N.E.2d 665 (Ohio Court of Appeals, 1987)
Barton v. Ellis
518 N.E.2d 18 (Ohio Court of Appeals, 1986)
Doner v. Snapp
649 N.E.2d 42 (Ohio Court of Appeals, 1994)
Sites v. Moore
607 N.E.2d 1114 (Ohio Court of Appeals, 1992)
Miller v. Bealer
608 N.E.2d 1133 (Ohio Court of Appeals, 1992)
C. E. Morris Co. v. Foley Construction Co.
376 N.E.2d 578 (Ohio Supreme Court, 1978)
Ross v. Ross
414 N.E.2d 426 (Ohio Supreme Court, 1980)
Seasons Coal Co. v. City of Cleveland
461 N.E.2d 1273 (Ohio Supreme Court, 1984)
Vogel v. Wells
566 N.E.2d 154 (Ohio Supreme Court, 1991)
Gerijo, Inc. v. City of Fairfield
70 Ohio St. 3d 223 (Ohio Supreme Court, 1994)
Central Motors Corp. v. City of Pepper Pike
73 Ohio St. 3d 581 (Ohio Supreme Court, 1995)
Davis v. Flickinger
674 N.E.2d 1159 (Ohio Supreme Court, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
Chaney v. Ramsey, Unpublished Decision (4-7-1999), Counsel Stack Legal Research, https://law.counselstack.com/opinion/chaney-v-ramsey-unpublished-decision-4-7-1999-ohioctapp-1999.