Steen Electric v. Homes of Elegance, Inc., Unpublished Decision (11-24-2004)

2004 Ohio 6275
CourtOhio Court of Appeals
DecidedNovember 24, 2004
DocketC.A. No. 21876.
StatusUnpublished
Cited by3 cases

This text of 2004 Ohio 6275 (Steen Electric v. Homes of Elegance, Inc., Unpublished Decision (11-24-2004)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Steen Electric v. Homes of Elegance, Inc., Unpublished Decision (11-24-2004), 2004 Ohio 6275 (Ohio Ct. App. 2004).

Opinion

DECISION AND JOURNAL ENTRY
{¶ 1} Appellant, Homes of Elegance, Inc. ("Homes of Elegance"), appeals from the judgment of the Akron Municipal Court, which entered judgment in favor of appellee, Steen Electric dba Valley Heating Cooling ("Steen Electric"), in the amount of $5,276.00 arising from a contract in which appellee agreed to perform heating and cooling services for appellant. This Court reverses.

I.
{¶ 2} On October 29, 2001, appellant, a general contractor, entered into a contract with appellee, a heating and cooling subcontractor, under which appellee would furnish and install all H.V.A.C. work on a residential home known as the North Shores Project. This included furnishing and installing two furnaces and two air conditioning units.1

{¶ 3} Under the terms of the contract, appellant would pay appellee one-half ($7,403.00) of the total contract price of $14,806.00 upon completion of the "rough" work and one-half ($7,403.00) upon completion of the project. There is no dispute that the "rough" work was completed and that appellant made the first payment. The dispute involves whether the project was substantially completed before appellee stopped work such that it was entitled to the second payment.

{¶ 4} Appellee ceased work when the parties' relationship deteriorated after appellant changed the project from one containing an unfinished basement to one for a finished basement and included a large room addition. Appellee informed appellant that the existing H.V.A.C. plans contained in the contract were not sufficient for the added square footage in the house. There is a dispute regarding whether appellee timely performed the work and whether appellant requested appellee to cease performing any work or appellee stopped work on its own.

{¶ 5} Appellant has not paid any part of the final $7,403.00. Appellee claims that it substantially performed its obligations under the contract and billed appellant $5,958.00 on January 17, 2002. Appellee filed suit against appellant alleging breach of contract. Later, appellee filed an amended complaint and appellant counterclaimed.

{¶ 6} The trial court held a hearing and found that appellee had substantially performed the work it had contracted to perform. The court found that ninety percent of the work was completed by the time appellee stopped working. Consequently, the trial court awarded appellee ninety percent of the second billing in the amount of $5,276.70. The court also found that appellee may not have been reasonable in stopping work due to a letter from appellant's counsel inquiring as to its intentions regarding completing the work. Appellee timely appealed from the trial court's judgment, setting forth three assignments of error for review.

II.
ASSIGNMENT OF ERROR I
"The trial court erred by allowing plaintiff [appellee] to recover despite the fact that plaintiff breached the agreement with defendant [appellant]."

{¶ 7} This Court's determination on Assignments of Error II and III render this Assignment of Error moot.

ASSIGNMENT OF ERROR II
"The trial court erred in finding that plaintiff's [appellee] work under the agreement constituted `substantial performance.'"

ASSIGNMENT OF ERROR III
"The trial court erred by ignoring defendant's actual cost of completing the unfinished work."

{¶ 8} This Court will consider these Assignments of Error together.

{¶ 9} Whether a party has substantially performed under the terms of a contract is a question of fact. Marinich v. Bush (Dec. 30, 1999), 12th Dist. Nos. CA99-01-011 and CA99-01-018, citing Volak v. Henderson (July 19, 1995), 9th Dist. No. 94CA005815, citing Jacob Youngs v. Kent (1921), 230 N.Y. 239,129 N.E. 889. As noted above, this Court reviews the court's findings of fact under a sufficiency of the evidence standard.Ehrich, 9th Dist No. 17089.

{¶ 10} In this case, the trial court found that appellee performed ninety percent of the work required and therefore had substantially performed the contract

{¶ 11} Appellant argued that this finding is incorrect. It argued that appellee did not substantially perform its obligations under the contract. Appellant cited the case ofCleveland Neighborhood Health Serv., Inc. v. St. Clair Builders,Inc. (1989), 64 Ohio App.3d 639 in support. In that case, the trial court awarded the builder the amount due under a construction contract. The Eighth District affirmed the trial court's finding that the contractor substantially performed the contract and was due the remainder of the contract amount. The facts showed that the entire contract was for the amount of $218,000.00. The evidence produced at trial showed that $2,000.00 worth of work remained to be done under the contract. The court also found that $7,000.00 worth of work was needed to correct portions of the work not properly performed. The court found that ninety five percent of the work had been completed. It used the $7,000.00 cost to complete, rather than the $2,000.00 contract price, to determine the percentage of the contract performed.

{¶ 12} At the hearing, appellant produced evidence from Echols Heating and Air Conditioning ("Echols"), another H.V.A.C. subcontractor hired to complete the unfinished work. Echols testified that it would cost approximately $5,000.00 to finish the work. Echols also testified that completing the work of another contractor was often more expensive than under the original contract.

{¶ 13} Appellant's calculations established that appellee had completed only two thirds of the job as measured by the method used in St. Clair Builders. Appellant reached this two thirds figure by taking the amount needed to complete the work ($5,000.00) and dividing it by the total amount of the contract ($14,806.00) [$14,806 (contract amount) divided by $5,000.00 (amount to complete job by Echols) = one third unfinished.] Appellant claimed that two thirds completion of a contract cannot be considered substantial performance. As a result, appellant argued that appellee should not have been awarded anything.

{¶ 14} Appellee argued that the trial court properly applied the St. Clair Builders' standard in determining that it had substantially performed the contract. Appellee based its computations on the amounts provided in the contract, and not what it would actually cost appellant to complete the project, to determine what percentage of the contract remained unperformed. Appellee claimed that only approximately $1,500.00 was needed to complete the contract. Under appellee's computation, it had substantially performed by contact by performing ninety percent of its obligations. ($14,806.00 [total contract price] divided by $1,500.00 [cost under contract to complete work] = ninety percent.)

{¶ 15} The issue in this case is whether the contract amount or the actual amount to complete the contract should to be used to determine whether a party has substantially performed its obligations under a contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bakhshi v. Baarlaer
2021 Ohio 13 (Ohio Court of Appeals, 2021)
Oberlin v. Lorain Cty. Joint Vocational School Dist. Bd. of Edn.
2019 Ohio 3977 (Ohio Court of Appeals, 2019)
Scolieri v. Danko Fine Land., Unpublished Decision (5-31-2005)
2005 Ohio 2787 (Ohio Court of Appeals, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
2004 Ohio 6275, Counsel Stack Legal Research, https://law.counselstack.com/opinion/steen-electric-v-homes-of-elegance-inc-unpublished-decision-ohioctapp-2004.