Class v. City of Seattle

955 F.2d 1268, 1992 WL 16087
CourtCourt of Appeals for the Ninth Circuit
DecidedFebruary 4, 1992
DocketNos. 90-15380, 90-15451, 90-15453, 90-16383 and 90-16446
StatusPublished
Cited by323 cases

This text of 955 F.2d 1268 (Class v. City of Seattle) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Class v. City of Seattle, 955 F.2d 1268, 1992 WL 16087 (9th Cir. 1992).

Opinion

LEAVY, Circuit Judge:

These consolidated appeals involve challenges to the district court’s approval of settlement agreements and a plan of allocation in securities litigation. The case arose out of the nation’s largest bond default, the 1983 default on $2.25 billion in revenue bonds issued in order to finance the construction of two nuclear power plants in the State of Washington that were never completed. For the following reasons, we affirm the district court’s approval of the settlement agreements and Allocation Plan in all respects.

FACTS AND PROCEEDINGS

The facts are set forth by the district court in In re Washington Public Power Supply Sys. Sec. Litig., 720 F.Supp. 1379 (D.Ariz.1989). We summarize.

A

In 1976, the Washington Public Power Supply System (“WPPSS”)1 entered into agreements (“Participants’ Agreements”) with eighty-eight public utilities in the Pacific Northwest under which each participating utility (“Participant”) purchased a percentage of the project capability of two nuclear power plants being built by WPPSS. The two plants, Project 4 and Project 5 (“Projects 4/5”), were among five nuclear power plants which WPPSS had undertaken to construct in the 1970s. Under the Participants’ Agreements, each Participant agreed to pay its percentage share of costs incurred by WPPSS to finance, construct, and operate Projects 4/5, whether or not the Projects were completed, operable, or operating. During the [1274]*1274next five years, WPPSS issued $2.25 billion in bonds to finance Projects 4/5.

On January 22, 1982, construction of Projects 4/5 was terminated. At that time, Project 4 was approximately 24 percent completed and Project 5 approximately 16 percent completed. Costs had almost reached the original estimated total cost for complete construction of both plants. WPPSS alleged that termination was necessary due to its inability to obtain adequate financing.

The Participants would have been obligated to commence payments to WPPSS one year later. Before the payments became due, however, several actions were filed by ratepayers, certain Participant utilities, and Chemical Bank in its capacity as Trustee for all Projects 4/5 Bondholders. These actions sought to contest or enforce the Participants’ obligations to make payments to WPPSS under the terms of the Participants’ Agreements. On June 15, 1983, the Washington Supreme Court held that certain of the Participant municipal utilities lacked authority to enter into the Participants’ Agreements. Chemical Bank v. Washington Public Power Supply Sys., 99 Wash.2d 772, 666 P.2d 329 (1983), aff'd on reh’g, 102 Wash.2d 874, 691 P.2d 524 (1984), cert. denied, 471 U.S. 1065, 105 S.Ct. 2140, 85 L.Ed.2d 497 (1985). On remand to the State Superior Court, the remaining Participants’ Agreements were held to be unenforceable. On appeal, the Washington Supreme Court affirmed, thereby releasing the remaining Participants from their payment obligations. Chemical Bank v. Washington Public Power Supply Sys., 102 Wash.2d 874, 691 P.2d 524 (1984), cert. denied, 471 U.S. 1065, 105 S.Ct. 2140, 85 L.Ed.2d 497 (1985).

B

Early in 1983, numerous class actions alleging securities law violations in connection with the sale of the Bonds were filed in the United States District Courts for the Western District of Washington and the Southern District of New York. Initially the class actions were brought on behalf of purchasers of WPPSS Projects 4/5 bonds from March 1, 1977 through January 22, 1982. The complaints were amended to include Bondholders who had purchased bonds from January 23, 1982 through June 15, 1983. These two groups of purchasers (“MDL 551 Class Members”) were certified under Fed.R.Civ.P. 23 as the Pre-Termi-nation and Post-Termination Classes, respectively. In August 1983, Chemical Bank undertook similar litigation on behalf of all Projects 4/5 Bondholders (“Bondholders”).2 The actions were consolidated by the Judicial Panel on Multidistrict Litigation and transferred to the United States District Court for the Western District of Washington in Seattle under the caption “MDL 551.”

The Complaint filed on behalf of all MDL 551 Class Members alleged violations of both federal and Washington state securities laws as well as violation of the common law. The Chemical Bank Complaint alleged securities fraud, negligence, and other claims under state and federal law as well as breach of contract claims. Both actions primarily revolved around allegations of material misrepresentations or omissions in the prospectuses, or “Official Statements,” issued in connection with the offer and sale of the Bonds. The Complaints asserted claims against WPPSS; its directors; the nineteen public utilities and four cities that were members of WPPSS; the sixty-eight Projects 4/5 Participants that were not members of WPPSS; the individual and alternate members of the Projects 4/5 Participants Committee; and the Bonneville Power Administration (“BPA”). The Class Complaint also asserted claims against Blyth Eastman Paine [1275]*1275Webber, the financial consultant to WPPSS; R.W. Beck and Associates, the consulting engineers to WPPSS; United Engineers and Constructors, and Ebasco Services Incorporated, the architect/engineers for Projects 4/5; Wood Dawson Smith Heilman, bond counsel to WPPSS; Houghton Cluck Coughlin & Riley, special counsel to WPPSS; Merrill, Lynch, Pierce, Fenner & Smith Incorporated, Solomon Brothers Inc., Smith Barney Harris Uphan & Co., Incorporated, and Prudential-Bache Securities, Inc., bond underwriters; and Moody’s Investors Service and Standard & Poor’s Corporation, securities rating agencies.

The MDL 551 litigation proceeded for more than five years. Multiple motions to dismiss or for summary judgment were argued and considered by the district court.3 Special Masters and protocols were used extensively. Discovery was comprehensive. An estimated 200 million document pages were produced. Depositions of more than 300 persons were taken over a period of three and one-half years. Approximately 285 fact witnesses were deposed over a two-year period. In addition, 34 expert witnesses were deposed beginning in November 1987.

On February 10, 1987, the district court filed an order changing venue from the Western District of Washington to the District of Arizona pursuant to 28 U.S.C. § 1404(a). On petition for mandamus, we upheld the district court’s order. Washington Public Utilities Group v. United States Dist. Court, 843 F.2d 319 (9th Cir.1987).

Trial commenced on September 7, 1988. Seventeen jurors heard opening arguments and the testimony of a single witness until December 1988. At that time, final settlement agreements were reached. The majority of the settlements occurred prior to the start of trial. The remainder were reached during the two and one-half months of trial.

The settlements called for payment into a Settlement Fund of more than $580 million before interest. Four previously approved settlement agreements involved payments of an additional $107 million.

Notice of these settlements and of Settlement Hearings was provided to MDL 551 Class Members through an extensive mail and publication program in accordance with Rule 23.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Coburn v. City of Sacramento
E.D. California, 2020
Conti v. L'Oreal USA S/D, Inc.
E.D. California, 2020
Shirley Nichols v. Citibank
Ninth Circuit, 2018
Ontiveros v. Zamora
303 F.R.D. 356 (E.D. California, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
955 F.2d 1268, 1992 WL 16087, Counsel Stack Legal Research, https://law.counselstack.com/opinion/class-v-city-of-seattle-ca9-1992.