Christenson v. Crowned Ridge Wind, LLC

2022 S.D. 46
CourtSouth Dakota Supreme Court
DecidedAugust 3, 2022
Docket29615
StatusPublished
Cited by2 cases

This text of 2022 S.D. 46 (Christenson v. Crowned Ridge Wind, LLC) is published on Counsel Stack Legal Research, covering South Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Christenson v. Crowned Ridge Wind, LLC, 2022 S.D. 46 (S.D. 2022).

Opinion

#29615-a-MES 2022 S.D. 46

IN THE SUPREME COURT OF THE STATE OF SOUTH DAKOTA

****

IN THE MATTER OF ADMINISTRATIVE APPEAL GARRY EHLEBRACHT, STEVEN GREBER, MARY GREBER, RICHARD RALL, AMY RALL, AND LARETTA KRANZ, Appellees,

and

AMBER KAY CHRISTENSON and ALLEN ROBISH, Appellants,

v.

CROWNED RIDGE WIND, LLC, and SOUTH DAKOTA PUBLIC UTILITIES COMMISSION, Appellees.

APPEAL FROM THE CIRCUIT COURT OF THE THIRD JUDICIAL CIRCUIT DEUEL COUNTY, SOUTH DAKOTA

THE HONORABLE DAWN M. ELSHERE Judge

R. SHAWN TORNOW Sioux Falls, South Dakota Attorney for appellants.

MILES F. SCHUMACHER of Lynn Jackson Shultz & Lebrun P.C. Sioux Falls, South Dakota ****

CONSIDERED ON BRIEFS NOVEMBER 8, 2021 OPINION FILED 08/03/22 BRIAN J. MURPHY of NextEra Energy Resources, LLC Juno Beach, Florida Attorneys for appellee Crowned Ridge Wind, LLC.

AMANDA M. REISS KRISTEN N. EDWARDS of South Dakota Public Utilities Commission Attorneys for appellee South Dakota Public Utilities Commission. #29615

SALTER, Justice

[¶1.] Crowned Ridge Wind II, LLC (Crowned Ridge) applied to the South

Dakota Public Utilities Commission (the PUC) seeking permission to construct a

large wind energy farm in northeast South Dakota. Several individuals from Grant

and Codington Counties who were affected by the potential wind farm intervened to

oppose Crowned Ridge’s application. The PUC conducted a contested case hearing

and later issued a written decision approving the permit. The intervenors sought

review in the circuit court. The court affirmed the PUC’s decision and two of the

intervenors now appeal to this Court. We affirm.

Facts and Procedural History

[¶2.] Crowned Ridge requested permission from the PUC to construct a

wind farm comprised of 132 wind turbines capable of producing 300.6 megawatts of

electricity in Codington, Grant, and Deuel Counties (the Project). 1 In addition to

Crowned Ridge, other parties to the permit application process included PUC staff

as well as “[a]ny person residing in the area where the facility is proposed to be

sited, or any directly interested person” who applies for and obtains “party status.”

SDCL 49-41B-17(4). Amber Christenson and Allen Robish (the Intervenors), both of

1. Under the provisions of SDCL 49-41B-2(13), the Project was defined as a “[w]ind energy facility” because its size and design contemplated generating “one hundred megawatts or more of electricity.” The Project also satisfied the broader statutory definition of a “[f]acility,” which includes a wide variety of energy facilities. SDCL 49-41B-2(7). Accordingly, Crowned Ridge could not begin construction of the Project without obtaining a permit from the PUC. See SDCL 49-41B-4.

-1- #29615

whom live in rural areas near the Project, timely sought and obtained party status

to oppose the issuance of the permit. 2

[¶3.] The PUC conducted a contested case hearing using the procedures set

out in South Dakota’s Administrative Procedure Act contained in SDCL chapter 1-

26. See SDCL 49-41B-17.2. As part of the hearing, the PUC received evidence

concerning the potential impacts of the Project on the environment and surrounding

communities.

[¶4.] The hearing produced extensive testimony from seventeen witnesses,

many of whom submitted “pre-filed” testimony and exhibits detailing the evidence

they developed and reviewed concerning the potential impacts of the Project. 3 The

Intervenors raised several points of contention with the permit application. As they

relate to this appeal, the Intervenors questioned Crowned Ridge’s compliance with a

Conditional Use Permit (CUP) issued by Grant County, the future impact the

Project would have on solid waste management facilities, and the potential adverse

health effects the Project would have on local inhabitants.

2. The PUC also granted party status to seven additional area residents who opposed the issuance of the permit. Six of those individuals were represented by different counsel during all stages of their challenge to the permit application process and were parties to the appeal decided in Ehlebracht v. Crowned Ridge Wind II, LLC, 2022 S.D. 19, 972 N.W.2d 477.

3. See ARSD 20:10:22:39 (stating in part, “[u]pon the filing of an application pursuant to SDCL 49-41B-11, an applicant shall also file all data, exhibits, and related testimony which the applicant intends to submit in support of its application”).

-2- #29615

The Grant County CUP

[¶5.] Prior to the hearing, Crowned Ridge submitted pre-filed testimony of

senior project manager Tyler Wilhelm who stated that Crowned Ridge was

“responsible for obtaining all applicable federal, state, and local permits” required

for construction of the Project. On behalf of Crowned Ridge, Wilhelm applied for a

Wind Energy System CUP from the Grant County Board of Adjustment, which the

Board approved. The CUP application stated that “[the Project] adheres to the . . .

Wind Energy System requirements, as outlined in § 1211[,] Energy System (WES)

Requirements of the Grant County Zoning Ordinance.”

[¶6.] During Wilhelm’s testimony at the contested case hearing, the

Intervenors questioned him regarding a subsequent amendment to the Grant

County zoning ordinances governing wind energy facilities. The zoning ordinance

in effect at the time the Grant County Board of Adjustment issued the CUP to

Crowned Ridge contained a provision limiting the maximum level of ambient noise

produced by wind turbines to 50 dBA 4 “at the perimeter of the principal and

accessory structures . . . .” However, eleven days after the issuance of the Crowned

Ridge CUP, Grant County amended the ordinance, limiting the sound generated by

4. The unit abbreviation “dBA” refers to “A-weighted decibels.” It is “a unit for measuring sound levels, approximately equal to the smallest difference in loudness detectable by the human ear.” Atkinson v. City of Pierre, 2005 S.D. 114, ¶ 42 n.13, 706 N.W.2d 791, 802 n.13 (Sabers, J., dissenting).

-3- #29615

wind turbines to “45 dBA . . . measured twenty-five (25) feet from the perimeter of

the existing non-participating residences[5] . . . .”

[¶7.] According to Wilhelm, Crowned Ridge had, in fact, been instrumental

in the amendment to the noise ordinance, explaining that “[w]e were part of that . . .

process with the counties to get a new wind ordinance in place . . . .” Although

Wilhelm acknowledged that the CUP was issued to Crowned Ridge prior to the

adoption of the amended ordinance, he maintained that “[Crowned Ridge’s]

application that we filed is 100 percent consistent with what was adopted after our

filing and our approval date.”

[¶8.] Crowned Ridge also submitted pre-filed testimony from Jay Haley, a

wind energy consultant, who was engaged by Crowned Ridge to conduct studies

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McCook Lake Recreation Area v. Dakota Bay, LLC
2025 S.D. 53 (South Dakota Supreme Court, 2025)
Kirwan v. City of Deadwood
990 N.W.2d 108 (South Dakota Supreme Court, 2023)

Cite This Page — Counsel Stack

Bluebook (online)
2022 S.D. 46, Counsel Stack Legal Research, https://law.counselstack.com/opinion/christenson-v-crowned-ridge-wind-llc-sd-2022.