Christenson v. Crowned Ridge Wind, LLC

2022 S.D. 46
South Dakota Supreme Court·Decided August 3, 2022·No. 29615·Published·Cited by 2 cases

Opinion

#29615-a-MES 2022 S.D. 46

IN THE SUPREME COURT

OF THE

STATE OF SOUTH DAKOTA

****

IN THE MATTER OF ADMINISTRATIVE APPEAL GARRY EHLEBRACHT, STEVEN GREBER, MARY GREBER, RICHARD RALL, AMY RALL, AND LARETTA KRANZ, Appellees,

and

AMBER KAY CHRISTENSON and ALLEN ROBISH, Appellants,

v.

CROWNED RIDGE WIND, LLC, and SOUTH DAKOTA PUBLIC UTILITIES COMMISSION, Appellees.

****

APPEAL FROM THE CIRCUIT COURT OF THE THIRD JUDICIAL CIRCUIT DEUEL COUNTY, SOUTH DAKOTA

****

THE HONORABLE DAWN M. ELSHERE Judge

****

R. SHAWN TORNOW Sioux Falls, South Dakota Attorney for appellants.

MILES F. SCHUMACHER of Lynn Jackson Shultz & Lebrun P.C. Sioux Falls, South Dakota

****

CONSIDERED ON BRIEFS

NOVEMBER 8, 2021

OPINION FILED 08/03/22

BRIAN J. MURPHY of NextEra Energy Resources, LLC Juno Beach, Florida Attorneys for appellee Crowned Ridge Wind, LLC.

AMANDA M. REISS KRISTEN N. EDWARDS of South Dakota Public Utilities Commission Attorneys for appellee South Dakota Public Utilities

Commission.

SALTER, Justice [¶1.] Crowned Ridge Wind II, LLC (Crowned Ridge) applied to the South Dakota Public Utilities Commission (the PUC) seeking permission to construct a large wind energy farm in northeast South Dakota. Several individuals from Grant and Codington Counties who were affected by the potential wind farm intervened to oppose Crowned Ridge’s application. The PUC conducted a contested case hearing and later issued a written decision approving the permit. The intervenors sought review in the circuit court. The court affirmed the PUC’s decision and two of the intervenors now appeal to this Court. We affirm.

Facts and Procedural History [¶2.] Crowned Ridge requested permission from the PUC to construct a wind farm comprised of 132 wind turbines capable of producing 300.6 megawatts of electricity in Codington, Grant, and Deuel Counties (the Project). 1 In addition to Crowned Ridge, other parties to the permit application process included PUC staff as well as “[a]ny person residing in the area where the facility is proposed to be sited, or any directly interested person” who applies for and obtains “party status.” SDCL 49-41B-17(4). Amber Christenson and Allen Robish (the Intervenors), both of

1. Under the provisions of SDCL 49-41B-2(13), the Project was defined as a “[w]ind energy facility” because its size and design contemplated generating “one hundred megawatts or more of electricity.” The Project also satisfied the broader statutory definition of a “[f]acility,” which includes a wide variety of energy facilities. SDCL 49-41B-2(7). Accordingly, Crowned Ridge could not begin construction of the Project without obtaining a permit from the PUC.

See SDCL 49-41B-4.

whom live in rural areas near the Project, timely sought and obtained party status to oppose the issuance of the permit. 2 [¶3.] The PUC conducted a contested case hearing using the procedures set out in South Dakota’s Administrative Procedure Act contained in SDCL chapter 1- 26. See SDCL 49-41B-17.2. As part of the hearing, the PUC received evidence concerning the potential impacts of the Project on the environment and surrounding communities. [¶4.] The hearing produced extensive testimony from seventeen witnesses, many of whom submitted “pre-filed” testimony and exhibits detailing the evidence they developed and reviewed concerning the potential impacts of the Project. 3 The Intervenors raised several points of contention with the permit application. As they relate to this appeal, the Intervenors questioned Crowned Ridge’s compliance with a Conditional Use Permit (CUP) issued by Grant County, the future impact the Project would have on solid waste management facilities, and the potential adverse health effects the Project would have on local inhabitants.

2. The PUC also granted party status to seven additional area residents who opposed the issuance of the permit. Six of those individuals were represented by different counsel during all stages of their challenge to the permit application process and were parties to the appeal decided in Ehlebracht v.

Crowned Ridge Wind II, LLC, 2022 S.D. 19, 972 N.W.2d 477.

3. See ARSD 20:10:22:39 (stating in part, “[u]pon the filing of an application pursuant to SDCL 49-41B-11, an applicant shall also file all data, exhibits, and related testimony which the applicant intends to submit in support of its application”).

The Grant County CUP [¶5.] Prior to the hearing, Crowned Ridge submitted pre-filed testimony of senior project manager Tyler Wilhelm who stated that Crowned Ridge was “responsible for obtaining all applicable federal, state, and local permits” required for construction of the Project. On behalf of Crowned Ridge, Wilhelm applied for a Wind Energy System CUP from the Grant County Board of Adjustment, which the Board approved. The CUP application stated that “[the Project] adheres to the . . . Wind Energy System requirements, as outlined in § 1211[,] Energy System (WES) Requirements of the Grant County Zoning Ordinance.” [¶6.] During Wilhelm’s testimony at the contested case hearing, the Intervenors questioned him regarding a subsequent amendment to the Grant County zoning ordinances governing wind energy facilities. The zoning ordinance in effect at the time the Grant County Board of Adjustment issued the CUP to Crowned Ridge contained a provision limiting the maximum level of ambient noise produced by wind turbines to 50 dBA 4 “at the perimeter of the principal and accessory structures . . . .” However, eleven days after the issuance of the Crowned Ridge CUP, Grant County amended the ordinance, limiting the sound generated by

4. The unit abbreviation “dBA” refers to “A-weighted decibels.” It is “a unit for measuring sound levels, approximately equal to the smallest difference in loudness detectable by the human ear.” Atkinson v. City of Pierre, 2005 S.D.

114, ¶ 42 n.13, 706 N.W.2d 791, 802 n.13 (Sabers, J., dissenting).

wind turbines to “45 dBA . . . measured twenty-five (25) feet from the perimeter of the existing non-participating residences[5] . . . .” [¶7.] According to Wilhelm, Crowned Ridge had, in fact, been instrumental in the amendment to the noise ordinance, explaining that “[w]e were part of that . . . process with the counties to get a new wind ordinance in place . . . .” Although Wilhelm acknowledged that the CUP was issued to Crowned Ridge prior to the adoption of the amended ordinance, he maintained that “[Crowned Ridge’s] application that we filed is 100 percent consistent with what was adopted after our filing and our approval date.” [¶8.] Crowned Ridge also submitted pre-filed testimony from Jay Haley, a wind energy consultant, who was engaged by Crowned Ridge to conduct studies using computer-based modeling to estimate the level of noise the wind turbines would produce during operation. During Haley’s testimony at the hearing, the Intervenors also questioned him about the amendment to the Grant County zoning ordinance. Haley testified that, in order to test compliance with the Grant County zoning ordinance in effect at the time the CUP was issued, he conducted sound studies on all principal and accessory structures located within the Project’s footprint, which included over 170 receptor locations. According to his study, each of the principal and accessory structures fell within the fifty-decibel limit contained in the original Grant County ordinance.

5. The term “non-participating residences” describes individuals living near a wind farm project who have not entered into lease or easement agreements to participate in the project with the wind farm developer.

Free access — add to your briefcase to read the full text and ask questions with AI

Christenson v. Crowned Ridge Wind, LLC, 2022 S.D. 46 (S.D. 2022).

2022 S.D. 46 (Christenson v. Crowned Ridge Wind, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

McCook Lake Recreation Area v. Dakota Bay, LLC
2025 S.D. 53 (South Dakota Supreme Court, 2025)
Kirwan v. City of Deadwood
990 N.W.2d 108 (South Dakota Supreme Court, 2023)