§ 49-41B-11 — Applications for permit--Filing deadline--Form--Contents.

South Dakota § 49-41B-11
JurisdictionSouth Dakota
Title 49PUBLIC UTILITIES AND CARRIERS
Ch. 49-41AENERGY CONVERSION AND TRANSMISSION FACILITIES

This text of South Dakota § 49-41B-11 (Applications for permit--Filing deadline--Form--Contents.) is published on Counsel Stack Legal Research, covering South Dakota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
S.D. Codified Laws § 49-41B-11 (2026).

Text

All applications for a permit shall be filed with the Public Utilities Commission not less than six months prior to the planned date of commencement of construction of a facility in such form as prescribed by rules, and shall contain, but not be limited to, the following information:

(1)The name and address of the applicant;
(2)Description of the nature and location of the facility;
(3)Estimated date of commencement of construction and duration of construction;
(4)Estimated number of employees employed at the site of the facility during the construction phase and during the operating life of the facility. Estimates shall include the number of employees who are to be utilized but who do not currently reside within the area to be affected by the facility;
(5)Future additi

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Christenson v. Crowned Ridge Wind, LLC
2022 S.D. 46 (South Dakota Supreme Court, 2022)
2 case citations
In Re Otter Tail Power Co. Ex Rel. Big Stone II
2008 SD 5 (South Dakota Supreme Court, 2008)
2 case citations

Legislative History

SL 1977, ch 390, § 7.

Nearby Sections

15
View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
South Dakota § 49-41B-11, Counsel Stack Legal Research, https://law.counselstack.com/statute/sd/49-41B-11.