Ehlebracht v. Crowned Ridge Wind II, LLC and S.D. Pub. Util. Comm'n

2022 S.D. 19
CourtSouth Dakota Supreme Court
DecidedMarch 23, 2022
Docket29610
StatusPublished
Cited by4 cases

This text of 2022 S.D. 19 (Ehlebracht v. Crowned Ridge Wind II, LLC and S.D. Pub. Util. Comm'n) is published on Counsel Stack Legal Research, covering South Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ehlebracht v. Crowned Ridge Wind II, LLC and S.D. Pub. Util. Comm'n, 2022 S.D. 19 (S.D. 2022).

Opinion

#29610-a-MES 2022 S.D. 19

IN THE SUPREME COURT OF THE STATE OF SOUTH DAKOTA

****

IN THE MATTER OF THE ADMINISTRATIVE APPEAL OF GARRY EHLEBRACHT, STEVEN GREBER, MARY GREBER, RICHARD RALL, AMY RALL, AND LARETTA KRANZ, Appellants,

v.

CROWNED RIDGE WIND II, LLC, and SOUTH DAKOTA PUBLIC UTILITIES COMMISSION, Appellees.

APPEAL FROM THE CIRCUIT COURT OF THE THIRD JUDICIAL CIRCUIT DEUEL COUNTY, SOUTH DAKOTA

THE HONORABLE DAWN M. ELSHERE Judge

A.J. SWANSON Canton, South Dakota Attorney for appellants.

DANA VAN BEEK PALMER MILES F. SCHUMACHER of Lynn, Jackson, Shultz & Lebrun P.C. Sioux Falls, South Dakota

ARGUED OCTOBER 5, 2021 OPINION FILED 03/23/22 ****

BRIAN J. MURPHY of NextEra Energy Resources, LLC Juno Beach, Florida Attorneys for appellees Crowned Ridge Wind II, LLC.

AMANDA R. REISS KRISTEN N. EDWARDS Special Assistant Attorneys General Pierre, South Dakota Attorneys for appellees South Dakota Public Utilities Commission. #29610

SALTER, Justice

[¶1.] Crowned Ridge Wind II, LLC (Crowned Ridge) applied to the South

Dakota Public Utilities Commission (the PUC) for a permit to construct a large-

scale wind energy farm in northeast South Dakota. Several individuals intervened

and objected to Crowned Ridge’s application. After conducting an evidentiary

hearing, the PUC issued a written decision approving the application. The

intervenors appealed to the circuit court, which affirmed the PUC’s decision. Six of

the intervenors now appeal to this Court. We affirm.

Facts and Procedural History

[¶2.] Crowned Ridge is a wind energy company that sought to construct a

wind farm comprised of 132 wind turbines capable of producing 300.6 megawatts of

electricity in Codington, Grant, and Deuel Counties (the Project). Under the

provisions of SDCL 49-41B-2(13), Crowned Ridge’s Project was statutorily defined

as a “wind energy facility” because its size and design contemplated generating “one

hundred megawatts or more of electricity.” The Project also satisfied the broader

statutory definition of a “facility,” which includes a wide variety of energy facilities.

SDCL 49-41B-2(7). Consequently, Crowned Ridge could not begin construction of

the Project without obtaining a permit from the PUC. SDCL 49-41B-4. 1

[¶3.] Crowned Ridge submitted its application for a permit on July 9, 2019.

The six individuals who are the appellants in this appeal (the Intervenors) timely

1. Crowned Ridge was also required to secure the approval of the respective county zoning authorities before beginning construction on the Project. See Ehlebracht v. Deuel Cnty. Bd. of Adjustment, 2022 S.D. 18, 972 N.W.2d 464.

-1- #29610

sought and obtained party status to oppose the issuance of a permit. 2 Each of the

Intervenors are residents of Deuel County living near the Project. Their opposition

to the permit was primarily based on the wind turbines’ production of ambient noise

and a phenomenon known as shadow flicker, which refers to momentary disruptions

of natural sunlight caused by the rotation of a wind turbine’s blades.

[¶4.] Crowned Ridge did not propose to construct turbines on land owned by

the Intervenors and did not enter into lease or easement agreements with them, as

it had done with the other area landowners on whose property the Project was

directly sited. Members of this latter group are known as participating landowners,

while those in the former category, including the Intervenors, are described as non-

participating landowners.

[¶5.] Where, as here, an application meets with opposition, the PUC

conducts a contested case hearing using the procedures set out in South Dakota’s

Administrative Procedure Act contained in SDCL chapter 1-26. See SDCL 49-41B-

17.2. For Crowned Ridge’s application, the PUC conducted a hearing on February

4–6, 2020, to consider evidence and argument concerning the potential impact of the

Project on the environment and surrounding communities.

[¶6.] The evidentiary hearing produced extensive testimony from seventeen

witnesses. Many of the witnesses had previously submitted “pre-filed” direct

2. In addition to the applicant, parties to the permit application process also include PUC staff and “[a]ny person residing in the area where the facility is proposed to be sited, or any directly interested person” who asks to intervene and obtains “party status.” SDCL 49-41B-17. The PUC ultimately granted party status as intervenors to nine individuals. Three of those individuals are not parties to this appeal.

-2- #29610

testimony and exhibits to the PUC, detailing their views about the Project. See

ARSD 20:10:22:39 (stating in part, “[u]pon the filing of an application pursuant to

SDCL 49-41B-11, an applicant shall also file all data, exhibits, and related

testimony which the applicant intends to submit in support of its application.”).

[¶7.] For instance, Crowned Ridge submitted pre-filed direct testimony from

Jay Haley, a wind energy consultant who was engaged by Crowned Ridge to conduct

studies on the levels of noise and shadow flicker the Project would produce. At the

evidentiary hearing itself, Haley testified that, based on the “conservative

assumptions” of the sound study, the noise levels produced by the Project would fall

within the applicable county guidelines of forty-five decibels measured at non-

participating residences. Haley further testified that, based on the light study he

conducted, the shadow flicker produced by the Project would fall within the county-

imposed limits of no more than thirty hours of affected light per calendar year. 3

[¶8.] Crowned Ridge also submitted pre-filed direct testimony from

Christopher Ollson, PhD. Dr. Ollson was engaged by Crowned Ridge to study the

potential health implications associated with sound and shadow flicker. At the

evidentiary hearing, Dr. Ollson testified that the proposed limits of forty-five

decibels of sound at non-participating residences and no more than thirty hours of

shadow flicker would pose “no potential health or welfare risk to the county

residents.”

3. Zoning ordinances in both Grant and Deuel Counties included limitations on sound generation of forty-five decibels at non-participating residences and a shadow flicker limit of no more than thirty hours per year. The zoning ordinance for Codington County included a sound limit of fifty decibels at all residences but did not regulate shadow flicker.

-3- #29610

[¶9.] Darren Kearney, a utility analyst employed by the PUC staff, testified

about the process by which the PUC has historically regulated shadow flicker

limits. During cross-examination, counsel for the Intervenors questioned Kearney

about a lower shadow flicker level (fifteen hours per year) previously imposed as a

condition for a different wind energy project, known as Prevailing Wind Park. 4

Free access — add to your briefcase to read the full text and ask questions with AI

Related

STROM TRUST v. SCS CARBON TRANSPORT, LLC
2024 S.D. 48 (South Dakota Supreme Court, 2024)
Bracken v. Dlr Reemployment Assistance Division
2023 S.D. 22 (South Dakota Supreme Court, 2023)
Christenson v. Crowned Ridge Wind, LLC
2022 S.D. 46 (South Dakota Supreme Court, 2022)

Cite This Page — Counsel Stack

Bluebook (online)
2022 S.D. 19, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ehlebracht-v-crowned-ridge-wind-ii-llc-and-sd-pub-util-commn-sd-2022.