Christenson v. Crowned Ridge Wind, LLC

2022 S.D. 45
South Dakota Supreme Court·Decided August 3, 2022·No. 29334·Published·Cited by 2 cases

Opinion

#29334-a-MES 2022 S.D. 45

IN THE SUPREME COURT OF THE STATE OF SOUTH DAKOTA

****

AMBER KAYE CHRISTENSON, ALLEN ROBISH, KRISTI MOGEN, and PATRICK LYNCH, Appellants,

v.

CROWNED RIDGE WIND, LLC, and SOUTH DAKOTA PUBLIC UTILITIES COMMISSION, Appellees.

APPEAL FROM THE CIRCUIT COURT OF THE THIRD JUDICIAL CIRCUIT CODINGTON COUNTY, SOUTH DAKOTA

THE HONORABLE CARMEN MEANS Judge

R. SHAWN TORNOW Sioux Falls, South Dakota Attorney for appellants.

MILES F. SCHUMACHER of Lynn Jackson Shultz & Lebrun P.C. Sioux Falls, South Dakota

BRIAN J. MURPHY of NextEra Energy Resources, LLC Juno Beach, Florida Attorneys for appellee Crowned Ridge Wind, LLC.

CONSIDERED ON BRIEFS MARCH 23, 2021 OPINION FILED 08/03/22 AMANDA M. REISS KRISTEN N. EDWARDS of South Dakota Public Utilities Commission Attorneys for appellee South Dakota Public Utilities Commission. #29334

SALTER, Justice

[¶1.] Crowned Ridge Wind, LLC (Crowned Ridge) applied to the South

Dakota Public Utilities Commission (the PUC) for a permit to construct a wind

energy farm in northeast South Dakota. Several individuals impacted by the

potential wind farm intervened and objected to Crowned Ridge’s application. After

conducting an evidentiary hearing, the PUC issued a written decision approving the

application. The intervenors appealed to the circuit court, which affirmed the

PUC’s decision. Two of the intervenors now appeal to this Court. We affirm.

Facts and Procedural History

[¶2.] Crowned Ridge is a wind energy company that sought to construct a

wind farm comprised of up to 130 wind turbines capable of producing 300

megawatts of electricity in Codington and Grant Counties (the Project). Given its

size, the Project is classified as a “wind energy facility” and was required to obtain a

permit from the PUC before beginning construction. See SDCL 49-41B-2(13)

(defining “[w]ind energy facility” as a facility, which, among other things, is

“capable of generation of one hundred megawatts or more of electricity”); SDCL 49-

41B-4 (stating siting permit requirement).

[¶3.] Amber Christenson and Allen Robish, among other area residents,

sought and obtained party status as intervenors (the Intervenors) in order to oppose

Crowned Ridge’s application. 1 Their opposition triggered the PUC’s contested

1. In addition to the applicant, parties to the PUC application process include PUC Staff and “[a]ny person residing in the area where the facility is proposed to be sited, or any directly interested person” who applies for and (continued . . .) -1- #29334

hearing procedures, including the requirement that Crowned Ridge file written

testimony in support of its application in advance of the hearing. See ARSD

20:10:22:39 (stating in part, “Upon the filing of an application pursuant to SDCL

49-41B-11, an applicant shall also file all data, exhibits, and related testimony

which the applicant intends to submit in support of its application.”).

[¶4.] Crowned Ridge filed, or “pre-filed” as it is commonly known, the

testimony of a number of witnesses, including Jay Haley who conducted sound and

shadow flicker 2 studies in connection with the Project. Haley’s testimony and

attached studies were supplemented during the pendency of the administrative

case.

[¶5.] Using this pre-filed testimony procedure, Crowned Ridge also filed the

written testimony of Kimberly Wells, Ph.D., who provided her findings and expert

opinions regarding the Project’s impact on the environment, to include its effect on

natural resources as well as cultural implications. However, as the dates for the

evidentiary hearing drew closer, Crowned Ridge learned that Dr. Wells would be

unable to attend and testify in person. As a result, Crowned Ridge indicated it

would call Sarah Sappington, who is a colleague of Dr. Wells, to testify about the

environmental impact of the Project.

________________________ (. . . continued) obtains “party status.” SDCL 49-41B-17. Christenson is a resident of Codington County; Robish resides in Grant County.

2. Shadow flicker is the effect of the sun shining through the rotating blades of a wind turbine, casting a moving shadow. See Ehlebracht v. Crowned Ridge Wind II, LLC, 2022 S.D. 19, ¶ 3, 972 N.W.2d 477, 481.

-2- #29334

[¶6.] Sappington had previously received a bachelor’s degree in

anthropology with an emphasis in archaeology and a master’s degree in the same

disciplines. At the time of the hearing, she had been employed by an environmental

consulting firm for sixteen years, working on a variety of energy development

projects throughout the Midwest.

[¶7.] Sappington worked with Dr. Wells on the environmental planning for

the Project and had personal knowledge of the findings and opinions expressed in

Dr. Wells’s initial pre-filed testimony. In fact, Sappington assisted in drafting the

testimony. To provide notice of the transition from Dr. Wells to Sappington,

Crowned Ridge pre-filed Sappington’s testimony adopting Dr. Wells’s earlier

testimony.

[¶8.] At the PUC’s July 2019 evidentiary hearing, Crowned Ridge called

Haley as a witness, but before he began his direct examination, the Intervenors

objected to his testimony. They argued that Haley had misrepresented himself as a

professional engineer and used the corresponding “P.E.” designation after his name

on correspondence and documents filed in connection with his sound and shadow

flicker studies.

[¶9.] Haley explained that he holds a bachelor’s degree in mechanical

engineering and was a licensed professional engineer in North Dakota and

Minnesota for nearly 30 years. However, he had in recent years voluntarily allowed

his licensure to lapse because of changes to continuing education requirements and

his plan to retire in the near future. Although he understood that he was no longer

able to stamp engineering drawings, he believed he could still use the professional

-3- #29334

engineer designation. He learned that his latter belief was incorrect shortly before

the evidentiary hearing.

[¶10.] Nevertheless, Haley explained that it was not necessary to be a

professional engineer to conduct sound and shadow flicker studies. He stated that

he was a partner in a wind energy consulting firm and had performed many such

studies over the years and trained hundreds of others from various disciplines to

use a particular software program to plan the construction of wind farms. Haley

also testified that he was a member of a committee working to develop international

standards for evaluating and locating proposed wind energy farms.

[¶11.] Crowned Ridge responded to the Intervenors’ argument by claiming

Haley’s inaccurate use of the “P.E.” designation was an innocent mistake that did

not impact his ability to provide expert testimony. Staff for the PUC offered a

similar view, indicating that the Intervenors’ objection may implicate issues of

weight or credibility, but not admissibility.

[¶12.] The PUC’s hearing examiner agreed and overruled the Intervenors’

objection.

Free access — add to your briefcase to read the full text and ask questions with AI

Christenson v. Crowned Ridge Wind, LLC, 2022 S.D. 45 (S.D. 2022).

2022 S.D. 45 (Christenson v. Crowned Ridge Wind, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Bracken v. Dlr Reemployment Assistance Division
2023 S.D. 22 (South Dakota Supreme Court, 2023)
Christenson v. Crowned Ridge Wind, LLC
2022 S.D. 46 (South Dakota Supreme Court, 2022)