Chesapeake & Potomac Telephone Co. v. Sisson & Ryan, Inc.

362 S.E.2d 723, 234 Va. 492, 4 Va. Law Rep. 1345, 1987 Va. LEXIS 280
CourtSupreme Court of Virginia
DecidedNovember 25, 1987
DocketRecord 840962
StatusPublished
Cited by35 cases

This text of 362 S.E.2d 723 (Chesapeake & Potomac Telephone Co. v. Sisson & Ryan, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Chesapeake & Potomac Telephone Co. v. Sisson & Ryan, Inc., 362 S.E.2d 723, 234 Va. 492, 4 Va. Law Rep. 1345, 1987 Va. LEXIS 280 (Va. 1987).

Opinion

THOMAS, J.,

delivered the opinion of the Court.

In September 1979, a building under construction on behalf of the Chesapeake and Potomac Telephone Company of Virginia (C & P) collapsed after a heavy rain. C & P sued its excavation-grading contractor, Sisson and Ryan, Inc. (S & R or the “grading contractor”), and S & R’s surety, Federal Insurance Company (Federal). S & R filed third party claims against the project’s architects, Smithey & Boyton (the “architects”), and against the project’s general contractor, C. L. Lewis (the “general contractor”). The third-party actions were dismissed on demurrer. The case proceeded to a jury trial on C & P’s motion for judgment. C & P claimed damages of $350,000 with interest, plus costs and attorneys’ fees. The jury returned a verdict of $45,000, on which judgment was entered. In a post-trial proceeding, the trial court denied C & P’s claim for attorneys’ fees. C & P appeals.

C & P does not make a direct attack upon the adequacy of the damages. Instead, it argues that the trial was plagued by errors which resulted in jury confusion and which influenced the size of the verdict. Chief among these errors, according to C & P, was the admission of hearsay evidence. C & P also complains that it was entitled to recover attorneys’ fees pursuant to its contract with S & R.

On September 14, 1978, C & P entered into a contract with S & R for the preliminary site work for C & P’s Radford Work Center (the “site work contract”). The work center was to consist of a one-story building for the storage of tools and materials, and a two-story office building which contained a three-bay garage, a loading dock, and a pole and cable storage area. The site work contract consisted of several writings that were incorporated by reference; they included the September 14 agreement between C & P and S & R, the general conditions of the contract for construction, the supplementary general conditions, the EEOC re *495 quirements, the specifications, and the drawings. The September 14 agreement between C & P and S & R governed in the case of inconsistencies with the general conditions of the contract.

S & R commenced work pursuant to the site work contract on September 15, 1978, the day after the agreement was signed. The work was substantially complete by mid-November 1978. Final inspection and acceptance of the work occurred in February 1979.

Louis Baltz, a C & P employee, testified that while S & R’s work was in progress he visited the site and saw oversized material 1 piled up near the entrance gate but he thought that material was going to be “wasted” off site. He said that he never saw S & R use oversized material on the job. He testified further that C & P received reports from S & R showing that oversized material was being removed from the site.

According to Baltz, in February 1979, at the time of the final inspection, the site looked “beautiful.” Oversized rock was nowhere in sight. He noted, however, that the site was frozen. Baltz stated that, to his knowledge, no one at C & P knew of any boulders in the landfill until the collapse of the building which led to the suit.

On cross examination, Baltz admitted that if C & P’s soils engineer, Froehling & Robertson (Froehling), had been doing its job of inspecting S & R’s work, it would have discovered the boulders. This is so, Baltz said, because the boulders, once uncovered, were obvious.

The contract for the construction of the tools building was executed in January 1979. Construction commenced in June 1979. The first indication of a problem with the site came in September *496 1979. At that time, the mechanical contractor was using a backhoe to dig a drain line when the backhoe struck a “tremendous boulder.” The backhoe could not move the boulder. After the incident with the boulder, a weekend intervened. There were heavy rains over that weekend. When work resumed, the contractor noticed cracks in the building.

Baltz visited the site on the Tuesday following the weekend rains. He observed the cracks in the walls of the building and also noticed that “the rear wall had a tremendous bow in it.” Baltz asked Danny Sisson from S & R whether he knew of boulders being in the field. Sisson replied, “[s]ure, they are all across the site.”

After the collapse of the building, Froehling made four or five test bores. At a meeting held October 30, 1979, the contractor questioned whether Froehling should investigate the collapse. As a result, C & P hired another soils engineer, Geotechnics, to determine the cause of the collapse.

John R. Cutright of Geotechnics testified concerning the tests run by his company and the conclusions that were reached. Five test pits were dug. Nineteen compaction tests were run in those pits. Seventeen of the nineteen tests were valid. Ten tests showed compliance with the 90% compaction requirement contained in the specifications; seven did not.

Geotechnics ran one hundred nine penetrometer tests. These tests show the strength of supporting soil, in place. The heaviest load from the tools building was 1,007 pounds per square foot (p.s.f.). Of the 109 tests, ninety-four were taken outside or away from the area where the rocks were nested. 2 Each of these tests showed sufficient strength to support the heaviest load of the building. The same was not true with regard to the fifteen tests taken in the area of the nested rocks, on the site of the building collapse. All of these tests “showed no strength. The soils were so weak they would not register on the device for strength.”

Cutright testified that when the site was excavated, he observed large rocks so close together that soil could not be compacted around them. Some of the rocks were touching. Geotechnics discovered ground water seeping into pits and voids around the rocks. Cutright said that the way the rocks were placed, openings were *497 left around the rocks. The witness explained further that where water seeps into voids it causes readjustments in the soil and lets the rocks move; this movement undermines support to the materials over the rocks and can cause a structure, such as a building, to come down. He also pointed out, based on the results from an “unconfined compression test” conducted in the laboratory, that the load bearing strength of the soil around the nested rock was only 160 to 175 p.s.f. — clearly insufficient to support the building’s load of approximately 1,000 p.s.f. He said the basic cause for the building’s failure was the nested oversized rock.

Another Geotechnics representative made clear that the soil deficiencies were found almost exclusively in the area of the nested rock. The witness said further that it is physically impossible to compact around nested rock. According to him, the building would not have failed without the nested rock.

S & R’s own witness agreed with C & P’s experts on the reason for the collapse of the building. He testified as follows:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Key Government Finance, Inc. v. E3 Enterprises Inc.
2 F. Supp. 3d 741 (D. Maryland, 2014)
Bynum v. Commonwealth
704 S.E.2d 131 (Court of Appeals of Virginia, 2011)
Shen Valley Masonry, Inc. v. Thor, Inc.
81 Va. Cir. 89 (Roanoke County Circuit Court, 2010)
Virginia Electric & Power Co. v. Utiliquest, L.L.C.
72 Va. Cir. 119 (Alexandria County Circuit Court, 2006)
Barber v. VistaRMS, Inc.
634 S.E.2d 706 (Supreme Court of Virginia, 2006)
Ulloa v. Qsp, Inc.
624 S.E.2d 43 (Supreme Court of Virginia, 2006)
Sykes v. Brady-Bushey Ford, Inc.
69 Va. Cir. 219 (Charlottesville County Circuit Court, 2005)
Lee v. Mulford
611 S.E.2d 349 (Supreme Court of Virginia, 2005)
Bizmark, Inc. v. Industrial Gas & Supply Co., Inc.
358 F. Supp. 2d 518 (W.D. Virginia, 2005)
Trex Co., Inc. v. ExxonMobil Oil Corp.
234 F. Supp. 2d 572 (E.D. Virginia, 2002)
Omni Alarm Systems, Inc. v. MCI Electric Co.
58 Va. Cir. 264 (Virginia Circuit Court, 2002)
Gibson v. Gibson
70 Va. Cir. 433 (Greene County Circuit Court, 2001)
Harris v. Allstate Insurance
540 S.E.2d 576 (West Virginia Supreme Court, 2000)
Blue Stone Land Co., Inc. v. Neff
526 S.E.2d 517 (Supreme Court of Virginia, 2000)
Coady v. Strategic Resources, Inc.
515 S.E.2d 273 (Supreme Court of Virginia, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
362 S.E.2d 723, 234 Va. 492, 4 Va. Law Rep. 1345, 1987 Va. LEXIS 280, Counsel Stack Legal Research, https://law.counselstack.com/opinion/chesapeake-potomac-telephone-co-v-sisson-ryan-inc-va-1987.