Idaho State University v. Mitchell

552 P.2d 776, 97 Idaho 724, 1976 Ida. LEXIS 347
CourtIdaho Supreme Court
DecidedFebruary 26, 1976
Docket11735 and 11736
StatusPublished
Cited by31 cases

This text of 552 P.2d 776 (Idaho State University v. Mitchell) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Idaho State University v. Mitchell, 552 P.2d 776, 97 Idaho 724, 1976 Ida. LEXIS 347 (Idaho 1976).

Opinions

BAKES, Justice.

On July 1, 1970, the interior of the recently completed but never before used sports arena of Idaho State University at Pocatello (hereinafter “ISU”), the “Mini-dome,” was flooded with over a foot of water and tons of silt and debris which damaged the arena’s artificial turf. The incident occurred because one of the two water pipes which supplied the structure had failed. In' an attempt to recover its costs of repair and cleanup, ISU sued the contractor, Mitchell Construction Co., and the architect, Cedric M. Allen, on theories of negligence and breach of contractual warranties. Subsequently, Mitchell filed a third party complaint against Bingham Mechanical & Metal Products, Inc., the subcontractor which installed the water pipe that had failed.

The water pipe that broke ran laterally from a water main which paralleled the west side of the sports arena and entered the building at its southwest corner. There was a similar lateral pipe running from the same water main which entered the building at the northwest corner. These pipes were laid by Bingham Mechanical on backfill soil which was compacted by Mitchell Construction according to specifications made by the architect Cedric Allen.

[726]*726In late 1973, prior to Mitchell’s third party complaint against Bingham Mechanical, depositions were taken of Brent Ballif, a consulting engineer who was employed by both ISU and the architect; John Korbis, the director of the physical plant at ISU; the architect Allen; and the contractor Mitchell. These depositions focused on the sufficiency of the architect’s plans and specifications for laying of the water pipes and the requirements for compaction of the backfill on which the pipe was laid, the manner in which the pipe was laid and the soil compacted, and theories as to the cause of the pipe failure. On November 14, 1973, Mitchell filed its third party complaint against Bingham Mechanical. On November 23, 1973, ISU moved for summary judgment against Mitchell Construction Co. and thereafter the architect Allen moved for summary judgment in his favor.

In a memorandum decision and order dated February 26, 1974, the trial court ruled that there was no genuine issue of fact concerning the alleged negligence of the architect and granted summary judgment in his favor against ISU. It then concluded that ISU’s motion for summary judgment on the issue of liability should be granted against Mitchell, based on the warranty given by the contractor. In this same opinion the trial court determined that Mitchell Construction Co. had a right to look to Bingham Mechanical for indemnification based on the subcontractor’s warranty given to the contractor. There had been no motion for summary judgment on the third party complaint made by either Mitchell or Bingham Mechanical, but the court reasoned that the issues were so interrelated that the entire matter should be disposed of together. Formal orders were entered granting partial summary judgment on the issue of liability in favor of ISU against Mitchell Construction Co., and in favor of Mitchell Construction Co. against the subcontractor, Bingham Mechanical, and also granting the architect’s motion for summary judgment. Bingham Mechanical filed a motion for relief from judgment on the ground that the trial court was without jurisdiction to grant summary judgment against the subcontractor when no motion for such summary judgment was before it, which motion was denied.

Following a hearing on the issue of ISU’s damages, judgment was entered in the main action on June 3, 1974. On July 25, 1974, judgment was entered in the indemnification action against Bingham Mechanical. Mitchell and Bingham Mechanical appeal from these judgments, while ISU has acquiesced in the judgment entered in favor of the architect. Since these two appeals raise different questions of law, we will consider them separately.

NO. 11795: ISU v. MITCHELL CONSTRUCTION CO.

A. The Contract:

The construction of the Minidome was divided into three distinct contracts. The Phase I contract encompassed construction solely of the superstructure itself; the Phase II contract included the construction of the substructure and the general construction of the stadium, up to and including the asphalt subfloor upon which the artificial turf was placed. The third contract was for the procurement and installation of the artificial turf. Mitchell Construction Co. was the successful bidder for Phase II of the contract, entering into the contract with the Idaho Department of Public Works in 1968.

The “General Conditions of the Contract for Construction,” plaintiff’s exhibit “C”, governs the duties and relationships among the owner (ISU), the contractor (Mitchell Construction Co.) and the architect (Allen). This document is divided into fourteen articles. Article 4 of the contract governs the activities of the contractor. Section 4.18.1 of this article is entitled “Indemnification” and reads as follows:

“4.18 INDEMNIFICATION
“4.18.1 The Contractor shall indemnify and hold harmless the Owner and the Architect and their agents and employees [727]*727from and against all claims, damages, losses and expenses including attorneys’ fees arising out of or resulting from the performance of the Work, provided that any such claim, damage, loss or expense (a) is attributable to bodily injury, sickness, disease or death, or to injury to or destruction of tangible property (other than the Work itself) including the loss of use resulting therefrom, and (b) is caused in whole or in part by any negligent act or omission of the Contractor, any Subcontractor, anyone directly or indirectly employed by any of them or anyone for whose acts any of them may be liable, regardless of whether or not it is caused in part by a party indemnified hereunder.”

Article 13 of the contract relates to the unconvering and correction of work. Section 13.2.2 provides:

“13.2.2 If, within one year after the Date of Substantial Completion or within such longer period of time as may be prescribed by law or by the terms of any applicable special guarantee required by the Contract Documents, any of the Work is found to be defective or not in accordance with the Contract Documents, the Contractor shall correct it promptly after receipt of a written notice from the Owner to do so unless the Owner has previously given the Contractor a written acceptance of such condition. The Owner shall give such notice promptly after discovery of the condition.”

Article 1 of the General Conditions of the Contract defines certain terms which are used as words of art throughout the document. “The Work” is defined as:

“1.1.3 THE WORK
The term Work includes all labor necessary to produce the construction required by the Contract Documents, and all materials and equipment incorporated or to be incorporated in such construction.”

Article 8, relating to time, defines the Date of Substantial Completion of the Work as:

“8.1.3 The Date of Substantial Completion of the Work or designated portion thereof is the Date certified by the Architect when construction is sufficiently complete, in accordance with the Contract Documents, so the Owner may occupy the Work or designated portion thereof for the use for which it is intended.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Nield v. Pocatello Health Services, Inc.
332 P.3d 714 (Idaho Supreme Court, 2014)
Oregon Mutual Insurance v. Farm Bureau Mutual Insurance
218 P.3d 391 (Idaho Supreme Court, 2009)
Safeco Ins. Co. of America v. Yon
796 P.2d 1040 (Idaho Court of Appeals, 1990)
Chesapeake & Potomac Telephone Co. v. Sisson & Ryan, Inc.
362 S.E.2d 723 (Supreme Court of Virginia, 1987)
Andre v. Morrow
680 P.2d 1355 (Idaho Supreme Court, 1984)
McEnroe v. Morgan
678 P.2d 595 (Idaho Court of Appeals, 1984)
American Land Title Co. v. Isaak
671 P.2d 1063 (Idaho Supreme Court, 1983)
Olson v. Idaho Department of Water Resources
666 P.2d 188 (Idaho Supreme Court, 1983)
Rajspic v. Nationwide Mutual Insurance
662 P.2d 534 (Idaho Supreme Court, 1983)
W.L. Scott, Inc. v. Madras Aerotech, Inc.
653 P.2d 791 (Idaho Supreme Court, 1982)
Sines v. Appel
644 P.2d 331 (Idaho Supreme Court, 1982)
Shea v. Bader
638 P.2d 894 (Idaho Supreme Court, 1981)
Juker v. American Livestock Insurance
637 P.2d 792 (Idaho Supreme Court, 1981)
Rasmuson v. Walker Bank & Trust Co.
625 P.2d 1098 (Idaho Supreme Court, 1981)
Pocatello Industrial Park Co. v. Steel West, Inc.
621 P.2d 399 (Idaho Supreme Court, 1980)
Alegria v. Payonk
619 P.2d 135 (Idaho Supreme Court, 1980)
Mitchell v. Bingham Mechanical & Metal Products, Inc.
584 P.2d 1241 (Idaho Supreme Court, 1978)
Just's, Inc. v. Arrington Construction Co.
583 P.2d 997 (Idaho Supreme Court, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
552 P.2d 776, 97 Idaho 724, 1976 Ida. LEXIS 347, Counsel Stack Legal Research, https://law.counselstack.com/opinion/idaho-state-university-v-mitchell-idaho-1976.