Omni Alarm Systems, Inc. v. MCI Electric Co.

58 Va. Cir. 264, 2002 Va. Cir. LEXIS 146
CourtVirginia Circuit Court
DecidedFebruary 26, 2002
DocketCase No. (Law) 01-36
StatusPublished
Cited by2 cases

This text of 58 Va. Cir. 264 (Omni Alarm Systems, Inc. v. MCI Electric Co.) is published on Counsel Stack Legal Research, covering Virginia Circuit Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Omni Alarm Systems, Inc. v. MCI Electric Co., 58 Va. Cir. 264, 2002 Va. Cir. LEXIS 146 (Va. Super. Ct. 2002).

Opinion

By Judge John E. Wetsel, Jr.

This case came before the Court for trial on February 20,2002, the parties appeared with their counsel, and evidence was heard and argued. Upon consideration, the Court has decided to find for the Defendant, because the Plaintiffs negotiation of the check tendered by the Defendant, which was conspicuously marked for payment “in full” of their disputed contract claim, operated as an accord and satisfaction pursuant to Virginia Code § 8.3 A-311.

I. Findings of Fact

The following facts are found by the greater weight of the evidence.

The Plaintiff, Omni Alarm Systems, is in the business of installing and maintaining security and other related electronic systems.

The Defendant, MCI Electric Company (“MCI”), is an electrical contractor, and on April 23, 1999, MCI entered into a contract with Construction Control Corporation (“CCC”) for work on the addition to the Warren County Courthouse.

The contract between MCI and CCC stated that the work was to begin on or before April 21,1999, and was to be substantially completed by January 21, 2000, with final completion on or before February 21, 2000. Article 8 of the MCI-CCC contract provided that:

[265]*265All Contractors specifically recognize that a delay in achieving either the Substantial Completion Date or the Final Completion Date will necessarily cause damages, losses, and expenses to the Owner.... All parties recognize and acknowledge that said damages, losses, and expenses might not be readily identifiable or ascertainable at the time they occur or at any future time. Therefore, and in recognition of these factors and the likelihood that actual damages from such a delay will not be readily ascertainable, the delaying contractor(s) shall pay to the Owner, as liquidated damages and not as a penalty, the sum of $500.00 per calendar day fdr each day by which failure to meet the Final Completion Date shown in the Construction Schedule, adjusted in accordance with Article 8.2, delays the Final Completion of the project.

On August 24,1999, MCI entered hito a Purchase Order with OMNI for the installation of the cameras and security devices for the contract price of $40,561.75. Unfortunately, the Purchase Order omitted many material provisions which would be commonly found in á subcontract on a municipal project. There was no start date, no completion date, and no specification of the specific equipment to be installed; instead, the Purchase Order simply provided that OMNI’s work would be “per plans and specifications.” The Purchase Order made no reference to any liquidated damage provision.

The only documents which MCI gave to OMNI at the time the Purchase Order was entered into were the plans, on which the security devices were simply located by symbols. The plans contained no specifications. The project specifications were a part of a large bound “Project Manual,” which contained all the significant contract documents, and both CCC and MCI had copies of the Project Manual, but OMNI did not.

The Project Manual contained all the significant contract documents including those containing the liquidated damage provision, and both MCI and CCC referred to the Project Manual as the “Specifications.” See, e.g. Defendant’s Ex. 1, July 11,2000, letter. In its notation in the OMNI Purchase Order, “per plans and specifications,” MCI was referring to the “Project Manual,” so it used the wrortg nomenclature in its Purchase Order, and OMNI was not given a copy of the Project Manual. Insofar as the actual work to be performed, there was no reason to give OMNI a copy of the Project Manual, becahse the project specifications had no provisions governing the work that OMNI was to perform.

OMNI’s security work had to be done after MCI had installed the wiring conduits, and OMNI did not start its work until February 11,2000, which was [266]*266after the date for substantial completion set forth in the Project Manual had passed. OMNI claimed that had it been provided proper access to the work by MCI, OMNI could have completed its work under the Purchase Order in six weeks.

The first written notice received by OMNI Alarm Systems concerning liquidated damages was a July 12,2000, letter from MCI, which enclosed the July 11, 2000, letter from CCC, stating that, as of July 17, 2000, liquidated damages would be assessed against MCI. Defendant’s Exhibit 1.

After July 17, 2000, OMNI and MCI became involved in a dispute over the completion of the work. See, e.g. Defendant’s Exs. 2 and 4, and Plaintiff s Ex. 4 and 5. Warren County, through its agent CCC, withheld $23,000.00 as liquidated damages from MCI’s contract retainage.

On September 22,2000, OMNI invoiced MCI for $40,561.75 pursuantto the Purchase Order dated August 24, 1999.

On October 27, 2000, MCI sent OMNI a check for $17,561.75, which was the difference between the OMNI Purchase Order amount of $40,561.75, and the $23,000 in liquidated damages which had been assessed against MCI by CCC. MCI’s check contained the notation “In full” on the face of the check, an agent for OMNI marked through the “In full” notation and wrote beside it “Amount in dispute,” and OMNI negotiated the check.

On February 16,2001, OMNI filed this action to collect the balance of its Purchase Order.

II. Conclusions of Law

A contract will be construed against the party who prepared it. Mahoney v. NationsBank, 249 Va. 216, 222,455 S.E.2d 5 (1995). “[T]he words used by the parties [in their contract] must be given their plain and ordinary meanings.” Hutter v. Heilmann, 252 Va. 227, 231, 475 S.E.2d 267, 270 (1996). “The court will not write a new contract for the parties even when, in light of the facts known to them, the court might think they should have adopted different language.” Lerner v. Gudelsky Co., 230 Va. 124, 132, 334 S.E.2d 579 (1985). The parties’ contract becomes the law of the case unless it is repugnant to some rule of law or public policy. Mercer v. South Atlantic Ins. Co., 111 Va. 699, 704, 69 S.E. 961,962 (1911).

In this case, MCI made a mistake in fact when it prepared the Purchase Order, and it did not refer to the “Project Manual;” therefore, the liquidated damage provision in the contract between MCI and CCC was not part of the contract between MCI and OMNI.

[267]*267Among other defenses, MCI defends this action on the grounds that OMNFs negotiation of its check, which it tendered marked “In Full,” operated as an accord and satisfaction pursuant to Virginia Code § 8.3A-311, which provides in pertinent part that:

(a) If a person against whom a claim is asserted proves that (i) that person in good faith tendered an instrument to the claimant as full satisfaction of the claim, (ii) the amount of the claim was unliquidated or subject to a bona fide dispute, and (iii) the claimant obtained payment of the instrument, the following subsections apply.
(b) . . .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Coleman-Adams Construction, Inc. v. Mills Heating & Air Conditioning, Inc.
93 Va. Cir. 442 (Amherst County Circuit Court, 2016)
Baughman v. Automated Horizons, Inc.
61 Va. Cir. 67 (Virginia Circuit Court, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
58 Va. Cir. 264, 2002 Va. Cir. LEXIS 146, Counsel Stack Legal Research, https://law.counselstack.com/opinion/omni-alarm-systems-inc-v-mci-electric-co-vacc-2002.