Rodriguez v. McDonnell Douglas Corp.

87 Cal. App. 3d 626, 151 Cal. Rptr. 399, 1978 Cal. App. LEXIS 2224
CourtCalifornia Court of Appeal
DecidedDecember 21, 1978
DocketCiv. 51350
StatusPublished
Cited by95 cases

This text of 87 Cal. App. 3d 626 (Rodriguez v. McDonnell Douglas Corp.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rodriguez v. McDonnell Douglas Corp., 87 Cal. App. 3d 626, 151 Cal. Rptr. 399, 1978 Cal. App. LEXIS 2224 (Cal. Ct. App. 1978).

Opinion

Opinion

JEFFERSON (Bernard), J.

By an amended complaint, plaintiff Richard Rodriguez sought recovery for personal injuries sustained while he was working on the premises of McDonnell Douglas Corporation (hereinafter, McDonnell). Named as defendants were McDonnell, its general contractor—Norman Engineering Company (hereinafter Norman), a subcontractor—Bethlehem Steel Corporation (hereinafter Bethlehem), Cox Brothers Crane Service (hereinafter Cox) and H. H. Robertson Company (hereinafter Robertson).

Joined with Richard Rodriguez as a plaintiff was his wife, Mary Anne, suing for her damages for loss of consortium. 1

Defendants answered the complaint, denying the material allegations of negligence 2 and raising the defense of contributory negligence on the part of both plaintiff Richard Rodriguez and his employer, Orvin Engineering Company (hereinafter Orvin).

McDonnell cross-complained for indemnity against Norman, Orvin, Bethlehem, Cox, Twining Laboratories of Southern California, Inc. (hereinafter Twining) and Robertson.

*635 Norman cross-complained for express indemnity against Bethlehem and Orvin.

The State Compensation Insurance Fund (hereinafter State Fund) intervened in the ¿ction to secure reimbursement for workers’ compensation benefits provided to plaintiff Richard Rodriguez.

Trial was by jury, commencing in November 1975. During trial, plaintiffs and intervener State Fund dismissed their complaints against Robertson. McDonnell dismissed its cross-complaint against Robertson and Twining.

After approximately three months of trial, the jury returned a special verdict or special findings. 3

*636 Thus, liability was imposed by the jury on Norman and Bethlehem; Orvin, not named a defendant by plaintiffs due to its status as plaintiff Richard’s employer, was found by the jury to have contributed 10 percent to plaintiff’s injuries.

Pursuant to a prior stipulation of the parties, the trial court, sitting without a jury, heard the issues relating to the various cross-complaints. On its cross-complaint against Norman, McDonnell was awarded $52,142.50 with interest.

Norman was awarded judgment on its cross-complaints for express contractual indemnity against both Bethlehem and Orvin in the sum of $4,723,708.62, 4 plus attorney fees of $69,341.94 on the ground that Norman’s negligence was “passive,” while Bethlehem’s and Orvin’s negligence was “active.”

Judgment was entered for the plaintiffs in the amount of $4,113,122.25 for plaintiff Richard Rodriguez, the trial court deducting from the jury award the total amount of workers’ compensation benefits, $122,873.75, which had been provided by State Fund, and in the amount of $500,000 for plaintiff Mary Ann Rodriguez. In entering judgment for State Fund against Norman and Bethlehem, the trial court deducted 10 percent from the total of $122,873.75 because of the jury finding that Orvin was 10 percent negligent, making the net judgment amount $110,586.37.

*637 Norman, Bethlehem, Orvin and the plaintiffs made motions for new trial. 5 Bethlehem also made a motion to set aside the judgment and sought judgment notwithstanding the verdict. All the motions were denied.

Bethlehem has appealed from the judgment rendered against it in favor of the plaintiffs, and from the judgment on the cross-complaint rendered against it in favor of Norman. In addition, Bethlehem has appealed from the denial of its motion to vacate judgment; from the denial of its motion for judgment notwithstanding the verdict; and from the denial of its motion for new trial. 6 Norman has appealed from plaintiffs’judgment against it.

Plaintiffs have filed a protective appeal from the judgment rendered in favor of McDonnell and Cox.

I

The Factual Background

A. Introduction

In 1969, McDonnell decided to modify Building 85, a 50-foot high steel hangar located at its facility in Long Beach, in order to accommodate its new larger DC-10 aircraft.

*638 McDonnell hired Norman as architect and engineer to draw the requisite plans and specifications. McDonnell then hired Norman as general contractor for the project. The contract between McDonnell and Norman imposed broad responsibility on Norman to supervise the entire remodeling effort, whether performed by Norman personnel or by subcontractors. Included in Norman’s responsibility was the maintenance of safe conditions on the job.

The modification plans contemplated demolition of portions of the south wall of Building 85, so that there would be an opening 17 feet high and 45 feet wide. Norman employees commenced demolition activities in April 1970, using acetylene torches and other tools to accomplish their task.

Norman subcontracted certain structural steel work to Bethlehem and, pursuant to its contract with McDonnell, hired a licensed fire protection engineer, Orvin, to modify the existing fire sprinkler system of Building 85.

McDonnell engineers visited the project often, to see that work was progressing according to plan and on schedule. McDonnell employee Bowers, a project engineer, was at the site of modification daily, checking on personnel and enforcing safety regulations. To meet certain requirements of the City of Long Beach, McDonnell retained the responsibility of inspecting the structural steel work, and hired Twining for this purpose; a Twining employee, Barnes, was on the job daily to inspect steel as it was installed—to monitor its strength, and to see that the welding was done properly. Barnes reported to Bowers.

During the modification, Norman had no specifically designated safety engineer on duty. However, its job superintendent, Podratz, was on the scene providing overall supervision. Podratz testified that he did not inspect the structural steel work, relying on the Twining inspector to perform that assignment. Podratz did not inspect the work performed by the fire protection engineer, Orvin, either, because Norman was not licensed in this area; both the McDonnell-Norman contract and applicable law required that the fire protection work be done by a licensed fire protection engineer.

Bethlehem commenced the structural steel work on June 8, 1970. Its plans showed that Bethlehem workers were to remove from the south wall a horizontal steel member some 30 feet in length, known as a girt or *639 channel iron. The girt was located slightly more than 17 feet above the ground, within inches of the opening in the wall. The girt’s flat unchanneled side was up and its “legs,” i.e., the channeled portion, was down.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Johnson v. Monsanto Company
California Court of Appeal, 2020
Johnson v. Monsanto Co.
California Court of Appeal, 2020
Jimenez v. Superior Court
California Court of Appeal, 2019
Williams v. The Pep Boys etc.
California Court of Appeal, 2018
Licudine v. Cedars-Sinai Medical Center
3 Cal. App. 5th 881 (California Court of Appeal, 2016)
Rico v. Mitsubishi Motors Corp.
171 P.3d 1092 (California Supreme Court, 2007)
McCrary Construction Co. v. Metal Deck Specialists, Inc.
35 Cal. Rptr. 3d 624 (California Court of Appeal, 2005)
Elsner v. Uveges
130 Cal. Rptr. 2d 483 (California Court of Appeal, 2003)
People v. Superior Court
23 P.3d 563 (California Supreme Court, 2001)
Rooz v. Kimmel
55 Cal. App. 4th 573 (California Court of Appeal, 1997)
Jones v. City of Los Angeles
20 Cal. App. 4th 436 (California Court of Appeal, 1993)
Washburn v. Beatt Equipment Co.
840 P.2d 860 (Washington Supreme Court, 1992)
Demkowski v. Soon Keun Lee
233 Cal. App. 3d 1251 (California Court of Appeal, 1991)
Weller v. American Broadcasting Companies, Inc.
232 Cal. App. 3d 991 (California Court of Appeal, 1991)
DePalma v. Westland Software House
225 Cal. App. 3d 1534 (California Court of Appeal, 1990)
Bonner v. Workers' Compensation Appeals Board
225 Cal. App. 3d 1023 (California Court of Appeal, 1990)
CMSH Co., Inc. v. Antelope Development, Inc.
223 Cal. App. 3d 174 (California Court of Appeal, 1990)
Vaerst v. Tanzman
222 Cal. App. 3d 1535 (California Court of Appeal, 1990)
Fortman v. Hemco, Inc.
211 Cal. App. 3d 241 (California Court of Appeal, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
87 Cal. App. 3d 626, 151 Cal. Rptr. 399, 1978 Cal. App. LEXIS 2224, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rodriguez-v-mcdonnell-douglas-corp-calctapp-1978.