C & G Excavating, Inc. v. United States

39 Cont. Cas. Fed. 76,715, 32 Fed. Cl. 231, 1994 U.S. Claims LEXIS 202, 1994 WL 580960
United States Court of Federal Claims·Decided October 24, 1994·No. No. 94-466C·Published·Cited by 15 cases

Opinion

OPINION

MILLER, Judge*

This bid-protest case comes before the court after argument on cross-motions for summary judgment. The overriding issue is whether the Small Business Administration (the “SBA”) may deny a certificate of competency (“COC”) for reasons other than those forming the basis of the contracting officer’s nonresponsibility determination. Assuming that SBA review is not limited to the matters referred by the contracting officer, the issue becomes whether 48 C.F.R § 19.602-2(a)(2) (1993), requires the SBA to conduct a site visit to investigate a contractor’s financial condition when that condition forms the basis of the SBA’s COC denial, but was not identified by the contracting officer as a basis for [233] the nonresponsibility determination. Plaintiff charges that the SBA acted arbitrarily and capriciously by failing to seek clarification or additional information concerning plaintiffs financial condition.

FACTS

C & G Excavating, Inc. (“plaintiff”), a Delaware corporation with a principal place of business in Peach Bottom, Pennsylvania, engages in the business of land excavation and dredging. Plaintiff submitted a bid in response to solicitation DACW65-94-B-0009, a small business set aside issued by the United States Army Corps of Engineers (the “Corps”) on January 24,1994, for the dredging of the Rudee Inlet in Virginia Beach, Virginia.

On March 22, 1994, the Corps opened the sealed bids and identified plaintiff as the low bidder, with a price of $530,000.00. The only other bidder, Cottrell Engineering Corp., submitted a bid in the amount of $594,000.00, thereby exceeding plaintiffs bid by $64,-000. 00. On March 25, 1994, Cottrell filed an agency protest, arguing that plaintiff did not meet the technical requirements specified in section 02881 of the solicitation. Specifically, Cottrell, citing the solicitation, alleged that plaintiff did not possess “ ‘a hydraulic pipeline dredgeE ] having a minimum 1,000 horsepower continuous to the pump,’ ” as required by section 02881 of the contract.

Corps employees John B. Roberts, Contract Specialist, Contracts Branch, and Joel F. Scussel, Operations Section, conducted a pre-award survey to ascertain whether plaintiff qualified as responsible within the meaning of 48 C.F.R. § 9.104-1 (1993), to receive and perform the contract at issue. Mr. Roberts sought information concerning plaintiffs financial capacity from various sources, including plaintiffs bank, Farmer’s First Bank. The information received, as set forth in the April 26, 1994 pre-award survey, revealed that plaintiff had a checking balance “in the Moderate Four [4] figures,” a certificate of deposit average “in the Mid Five [5] figures,” and a loan average balance “in the Low Six [6] figures.”

Messrs. Roberts and Scussel also contacted various individuals to obtain information on plaintiffs technical capability and overall competency as reflected by performance ratings on prior projects. According to the references contacted, plaintiff had received performance ratings ranging from “satisfactory” to “unsatisfactory.” Mr. Roberts further requested that Carol C. Todd, plaintiffs President, explain in writing how plaintiffs dredge the “Amber II” satisfied the terms of section 02881. Finally, Mr. Roberts assigned individuals to visit plaintiffs facility and inspect the Amber II for capability and safety. Based on the information accumulated during the pre-award survey, Mr. Roberts concluded that the Corps should not award the contract to plaintiff because the Amber II failed to satisfy the requirements of section 02881.

On April 26, 1994, Contracting Officer Evelyn W. Rowland sent a letter to the SBA indicating that plaintiff was not responsible from a capacity standpoint to perform the contract because its dredge did not satisfy section 02881.1 The letter informed the SBA that plaintiff had previously requested review under the certificate of competency (“COC”) program. The letter also indicated that in accordance with FAR § 19.602-4(c), the contracting officer would award the contract to another responsible bidder unless the SBA issued a COC within 15 business days of receiving the referral letter. On April 28, 1994, Thomas W. McGrath, Chief of Procurement Assistance, SBA, sent a letter to the contracting officer notifying her that the SBA had received the referral and that it was proceeding to act on it. This acknowl-edgement activated the 15-day time clock that required the SBA to issue the COC decision by May 19, 1994. This deadline, however, was later extended to May 26,1994.

Mr. McGrath also sent plaintiff a letter on April 28,1994, informing it that the contracting officer had found plaintiff not responsible and that plaintiff could apply under the COC program for a review of this decision.2 Mr. [234] McGrath explained the general procedures for processing COC applications and outlined the specific information necessary for SBA review. The letter stated that the “SBA will perform a comprehensive, independent review of your capabilities both from a production and financial viewpoint, if necessary. A facility visit, additional information, and clarifications may be required to substantiate your case____”

In addition, not only did the letter stress that plaintiff bore the burden of establishing competence to fulfill the terms of the contract, but it also stated: “Assisting you in securing this contract is one of our primary goals, but we cannot do so if you fail to provide the necessary data____” The information required in the COC application included monthly cash flow reports, financial statements for the last three fiscal years, a profit and loss statement, cost analysis data, and other evidence indicating sufficient financing.

On May 5, 1994, plaintiff filed the COC application. Plaintiff submitted unaudited financial statements for the years 1990-1992, but provided no statement for 1993 because, according to the accompanying letter dated May 5, 1994, from plaintiffs attorney, one “was not prepared.” Plaintiff also notified the SBA that it had secured both performance and payment bonds for the contract at issue, as required by the Miller Act.

As a supplement to the required COC application, Ms. Todd included a letter dated May 5, 1994, explaining that plaintiff was • delinquent in the payment of federal taxes for the taxable years 1991 and 1992. Ms. Todd attributed this delinquency to the Government’s failure to pay plaintiff, in full, the amount due on certain dredging contracts. Ms. Todd further informed the SBA that she had hired Equity Search, Inc., to assist her in resolving the tax delinquency with the Internal Revenue Service (the “IRS”). In explaining the status of the delinquency, Ms. Todd noted that “C & G and the IRS are in negotiations and ... [that the] matter will be resolved.” Ms. Todd also requested that the SBA “not consider the tax deficiencies as a negative factor.”

Free access — add to your briefcase to read the full text and ask questions with AI

C & G Excavating, Inc. v. United States, 39 Cont. Cas. Fed. 76,715, 32 Fed. Cl. 231, 1994 U.S. Claims LEXIS 202, 1994 WL 580960 (uscfc 1994).

39 Cont. Cas. Fed. 76,715 (C & G Excavating, Inc. v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Aeolus Systems, LLC v. United States
79 Fed. Cl. 1 (Federal Claims, 2007)
Textron, Inc. v. United States
74 Fed. Cl. 277 (Federal Claims, 2006)
United Enterprise & Associates v. United States
70 Fed. Cl. 1 (Federal Claims, 2006)
Aeroplate Corp. v. United States
67 Fed. Cl. 4 (Federal Claims, 2005)
Red River Service Corp. v. United States
60 Fed. Cl. 532 (Federal Claims, 2004)
CSE Construction Co. v. United States
58 Fed. Cl. 230 (Federal Claims, 2003)
Hawpe Construction, Inc. v. United States
46 Fed. Cl. 571 (Federal Claims, 2000)
Ellsworth Associates, Inc. v. United States
45 Fed. Cl. 388 (Federal Claims, 1999)
Beta Analytics International, Inc. v. United States
44 Fed. Cl. 131 (Federal Claims, 1999)
CRC Marine Services, Inc. v. United States
42 Cont. Cas. Fed. 77,310 (Federal Claims, 1998)
Pleasant Country, Ltd. v. United States
37 Fed. Cl. 321 (Federal Claims, 1997)
Stapp Towing Inc. v. United States
40 Cont. Cas. Fed. 76,839 (Federal Claims, 1995)