Bean Dredging Corp. v. United States

36 Cont. Cas. Fed. 76,017, 22 Cl. Ct. 519, 1991 U.S. Claims LEXIS 45, 1991 WL 15601
CourtUnited States Court of Claims
DecidedFebruary 11, 1991
DocketNo. 91-35C
StatusPublished
Cited by59 cases

This text of 36 Cont. Cas. Fed. 76,017 (Bean Dredging Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bean Dredging Corp. v. United States, 36 Cont. Cas. Fed. 76,017, 22 Cl. Ct. 519, 1991 U.S. Claims LEXIS 45, 1991 WL 15601 (cc 1991).

Opinion

OPINION

MARGOLIS, Judge.

This government contracts case is before the court after a full hearing on the plaintiffs’ complaint for preliminary and permanent injunctive and declaratory relief. The plaintiffs, government contractors, bid on a contract that was awarded to another contractor. The plaintiffs contend that the other contractor’s bid should be rejected as non-responsive because it failed to include a schedule listing equipment to be used on the contract project. The plaintiffs seek injunctive and declaratory relief preventing award of the contract to the other contractor and declaring the plaintiffs as the lowest responsive bidder. After careful review of the record, and after hearing the testimony of witnesses and oral argument, this court denies the defendant’s motion for summary judgment as moot, denies the plaintiffs’ request for RUSCC 11 sanctions, denies the plaintiffs’ request for injunctive and declaratory relief, and dismisses the plaintiffs' complaint with prejudice.

FACTS

The plaintiffs, Bean Dredging Corporation and Weeks Marine, Inc. (“Bean/Weeks”), bid on a contract pursuant to a solicitation issued by the United [521]*521States Army Corps of Engineers (“Corps”), Savannah, Georgia District, to perform maintenance dredging of the entrance channel to the Brunswick, Georgia harbor. Bean/Weeks maintains that the solicitation required bidders to complete and submit with their bids a Plant and Equipment Schedule. The Schedule required the bidders to list the equipment they proposed to utilize on the project, including the number, type and capacity of dredges.

At the top of Page B-2, the Schedule was annotated in bold:

* * * IMPORTANT * * *
INFORMATION REQUESTED BELOW MUST BE SPECIFIC. GENERALITIES WILL NOT BE ACCEPTED. FAILURE TO PROVIDE THIS INFORMATION MAY RESULT IN REJECTION OF THE BID.

The Schedule was referenced in Paragraph H.19 of the solicitation which contained Engineering Federal Acquisition Regulation (“EFAR”) Section 52.003-4502. This provision specified that:

(a) The Contractor agrees to keep on the job sufficient plant to meet the requirements of the work. The plant shall be in satisfactory operating condition and capable of safely and efficiently performing the work as set forth in the specifications and the plant shall be subject to inspection by the Contracting Officer at all times. The plant listed on the Plant and Equipment Schedule, ENG Form, 1619-R (SECTION B), is the minimum which the Contractor agrees to place on the job unless otherwise determined by the Contracting Officer, and its listing thereon is not to be construed as an agreement on the part of the Government that it is adequate for the performance of the work.

Bean/Weeks maintains that the provision specifies the minimum equipment which the contractor was obligated to place on the project and that satisfaction of the provision constituted a material requirement of the solicitation.

Bean/Weeks claims that they submitted their bid in compliance with the terms and requirements of the solicitation. Accordingly, Bean/Weeks committed a dredge, the Eagle, and other equipment to the project. Bean/Weeks claims that it adjusted its bid price upward to reflect the obligation of equipment to the project.

The bid opening took place on December 20, 1990. The Corps determined that the North American Trailing Company (“NAT-CO”), submitted the low bid of $1,549,250 and that Bean/Weeks was second at $1,979,800. Bean/Weeks claims that at the bid opening NATCO did not return the Schedule with its bid or obligate any equipment to the performance of the contract. A representative of Bean/Weeks, Ancil Taylor, called this to the attention of the Corps representative at the bid opening. Subsequently, the Corps determined that NATCO’s bid was responsive.

Bean/Weeks filed a protest with the Corps on December 31, 1990 contending (1) NATCO’s bid was non-responsive, (2) NAT-CO’s bid should have been rejected, and (3) the Corps should award the contract to Bean/Weeks. The Corps denied the protest on January 24, 1991 by written decision. On the basis of a series of decisions by the Comptroller General, the agency held that NATCO’s failure to specify the plant and equipment to be used is a matter of responsibility, not responsiveness.

In this court, Bean/Weeks requests that NATCO’s bid be declared non-responsive and that Bean/Weeks be declared the lowest responsive bidder under the solicitation. Bean/Weeks contends that NATCO’s bid was non-responsive. Plaintiffs assert that because the requirement of listing equipment on the Schedule defines the minimum equipment that the contractor must obligate to the contract, this requirement goes to responsiveness, not responsibility. Therefore, the Corps’ failure to reject NATCO’s non-responsive bid violated FAR § 14.404-2 which requires rejection of a non-responsive bid. Bean/Weeks further argues that NATCO should not now be able to submit a Schedule because doing so would amount to correcting a bid after bid opening. According to Bean/Weeks, the Corps’ failure to award the contract to Bean/Weeks also violated FAR § 14.407-1, [522]*522which requires an award to the lowest responsive bidder, and constituted a breach of the government’s implied duty to consider all bids received in a fair and equitable manner.1

DISCUSSION

The scope of review of the Corps’ pre-award procurement actions is extremely limited. Baird Corporation v. United States, 1 Cl.Ct. 662, 664 (1983). As the court stated in Baird, “[t]he court should not substitute its judgment on such matters for that of the agency, but should intervene only when it is clearly determined that the agency’s determinations were irrational or unreasonable. It is the burden of the aggrieved bidder to demonstrate that there was no rational basis for the agency’s determinations.” Id.

The court weighs the following factors in examining whether injunctive relief is warranted: (1) whether there is a likelihood that the plaintiffs will succeed on the merits; (2) whether the plaintiffs will suffer irreparable injury if the injunctive relief is not granted; (3) whether the threatened injury to the plaintiffs outweighs the harm to the defendant and other third parties; and (4) whether granting the relief is in the public interest. Southwest Marine, Inc. v. United States, 3 Cl.Ct. 611, 613 (1983); Yachts America, Inc. v. United States, 3 Cl.Ct. 447, 449 (1983). Because injunctive relief is so drastic in nature, the plaintiffs must demonstrate their right to injunctive relief by clear and convincing evidence. Southwest Marine, 3 Cl.Ct. at 613; Baird, 1 Cl.Ct. at 664.

Likelihood of Success on the Merits

The central issue in this case is whether listing the plant and equipment on the Schedule is a matter of responsiveness or responsibility. Bean/Weeks argues that the plant and equipment listing requirement is a question of responsiveness, that NATCO’s bid should have been rejected, and that the Corps’ failure to reject NAT-CO’s bid violated FAR provisions and demonstrates that the bid of Bean/Weeks was not fully and fairly considered. The government argues that the plant and equipment listing requirement relates to responsibility, that the Corps was not required to reject NATCO’s bid, and that the bid of Bean/Weeks was fully and fairly considered by the Corps.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Supreme Foodservice Gmbh v. United States
112 Fed. Cl. 402 (Federal Claims, 2013)
Caddell Construction Co., Inc. v. United States
111 Fed. Cl. 49 (Federal Claims, 2013)
Laboratory Corp. of America v. United States
108 Fed. Cl. 549 (Federal Claims, 2013)
Afghan American Army Services Corp. v. United States
106 Fed. Cl. 714 (Federal Claims, 2012)
Guzar Mirbachakot Transportation v. United States
104 Fed. Cl. 53 (Federal Claims, 2012)
Netstar-1 Government Consulting, Inc. v. United States
101 Fed. Cl. 511 (Federal Claims, 2011)
Bona Fide Conglomerate, Inc. v. United States
96 Fed. Cl. 233 (Federal Claims, 2010)
Crassociates, Inc. v. United States
95 Fed. Cl. 357 (Federal Claims, 2010)
Urban Development Solutions, LLC v. District of Columbia
992 A.2d 1255 (District of Columbia Court of Appeals, 2010)
Global Computer Enterprises, Inc. v. United States
88 Fed. Cl. 350 (Federal Claims, 2009)
Akal Security, Inc. v. United States
87 Fed. Cl. 311 (Federal Claims, 2009)
Serco Inc. v. United States
81 Fed. Cl. 463 (Federal Claims, 2008)
Monument Realty LLC v. Washington Metropolitan Area Transit Authority
540 F. Supp. 2d 66 (District of Columbia, 2008)
Ironclad/EEI v. United States
78 Fed. Cl. 351 (Federal Claims, 2007)
Rotech Healthcare Inc. v. United States
71 Fed. Cl. 393 (Federal Claims, 2006)
KSD, Inc. v. United States
72 Fed. Cl. 236 (Federal Claims, 2006)
Avtel Services, Inc. v. Unites States
70 Fed. Cl. 173 (Federal Claims, 2005)
KSEND v. United States
69 Fed. Cl. 103 (Federal Claims, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
36 Cont. Cas. Fed. 76,017, 22 Cl. Ct. 519, 1991 U.S. Claims LEXIS 45, 1991 WL 15601, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bean-dredging-corp-v-united-states-cc-1991.