Bean Dredging Corp. v. United States

36 Cont. Cas. Fed. 75,811, 19 Cl. Ct. 561, 1990 U.S. Claims LEXIS 41, 1990 WL 12226
CourtUnited States Court of Claims
DecidedFebruary 14, 1990
DocketNo. 604-89C
StatusPublished
Cited by9 cases

This text of 36 Cont. Cas. Fed. 75,811 (Bean Dredging Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bean Dredging Corp. v. United States, 36 Cont. Cas. Fed. 75,811, 19 Cl. Ct. 561, 1990 U.S. Claims LEXIS 41, 1990 WL 12226 (cc 1990).

Opinion

OPINION

REGINALD W. GIBSON, Judge:

This is a pre-award bid protest case seeking injunctive relief under 28 U.S.C. § 1491(a)(3) (West Supp.1989).1 2Plaintiffs Bean Dredging Corporation and Weeks Marine, Inc. (hereinafter Bean, Weeks, or plaintiffs) are joint venturers who seek to enjoin the United States Army Corps of Engineers (Corps or defendant) from cancelling an invitation for bids, which contemplates the performance of maintenance [562]*562dredging2 on the Mobile River in Mobile, Alabama. The Corps has proposed to cancel the invitation pursuant to the authority of 33 U.S.C. § 624 (West Supp.1989), which prohibits the award of river and harbor improvement contracts when every bid received by the Corps is more than 25% higher than the government’s estimate for performance of that same work. Plaintiffs, the lowest responsive and responsible bidders on subject project, challenge the defendant’s authority to cancel the invitation. Specifically, they contend that the Corps did not prepare a fair and reasonable cost estimate of a well-equipped contractor doing the work, as required by 33 U.S.C. § 624 and applicable regulations. Moreover, plaintiffs aver that this failure constitutes a violation of the implied-in-fact contractual obligation requiring the defendant to consider and treat all bids fairly.

Plaintiffs’ motion for a temporary restraining order was denied as moot. Their motions for preliminary and permanent injunctive relief were thereafter consolidated, and a hearing was held on the merits for a permanent injunction from November 29, 1989 to December 5,1989. For the reasons stated hereinafter, we grant plaintiffs’ consolidated motion for injunctive relief. Facts

The Corps’ Mobile District Office issued Invitation for Bids (IFB) No. DACW01-89B-0076 on July 27, 1989. The IFB solicited bids for maintenance dredging on the Mobile River ship channel in Mobile, Alabama. The work was to be performed on that portion of the river between Station 0 + 00 — tangent 1 and Station 31 + 60 — tangent 5; a dredging channel of approximately 24,000 to 25,000 feet in length and 500 to 1,000 feet in width. The IFB required “the removal ... of the material lying above the channel bottom elevations (below mean low water) and over the channel bottom widths and lengths as specified on the contract drawings,” PX 3, p. 2A-1. This requirement contemplated the removal of all shoal3 material within a box-cut prism. Thus, offerors were required to bid the project according to the materials within the prism, described as a depth of —42.0 feet below mean low water and the channel width prescribed by contract drawings referenced in the IFB. The quantity of materials to be removed was not advertised by the Corps. Bidders were, therefore, required to make this determination for themselves on the basis of IFB drawings coupled with three channel surveys included with the IFB. These three surveys, taken in November 1988, May 1989, and August 1989, provided all bidders with various channel cross-sections which indicated the distribution of the shoal material to be removed from the box-cut template.

The materials dredged were to be deposited in two disposal areas. The quantity of the materials to be placed in the first disposal area, known as Mud Lakes 6/7, was restricted to 1,000,000 gross cubic yards. The remainder of the dredged materials was to be deposited in the second disposal area, known as Gaillard Island, which was approximately 14 miles beyond the midpoint of the Mobile River work site. The fact of the foregoing distance to Gaillard Island as a disposal site necessarily contemplated the use of dredging pipeline with an average length of 72,000 feet. This requirement unquestionably made the project unconventional in that it required substantial amounts of submersible pipeline. This is so for the additional fact that the pipeline length was more than the Corps had used on any of five previous contracts in the Mobile River, PX 8.

Under the terms of the IFB, bidders were required to submit fixed, lump-sum prices for four line bid items. The four required components of each bid included:

[563]*563 Bid Item
# 1 — Mobilization and Demobilization;
#2 — Mobile River Dredging;
#3 — Dike Construction and General Rehabilitation for both the Mud Lakes 6/7 and Gaillard Island Disposal Areas; and
# 4 — Operation and Maintenance Costs Associated with the Mud Lakes 6/7 and Gaillard Island Disposal Areas.

The Corps, as required, prepared a project contract estimate by which it sought to judge all bids received pursuant to the solicitation. That estimate was prepared by Mr. Paul Warren, Area Engineer for the Mobile District. As Area Engineer, Mr. Warren is responsible for monitoring the condition of federal navigational channels in the Mobile District, drafting contract specifications for dredging projects, estimating the cost of dredging projects in the District, and execution of those projects. Mr. Warren, a civil engineer registered in the State of Alabama and employed with the Corps since 1974, estimated the cost of the project in issue on four separate occasions. See Appendix E. Each such estimate was prepared on a cost basis, without reference to profit. Additionally, the first two estimates, prepared prior to this litigation, were noted approved by Mr. James R. Couey, Engineering Division Chief. Said estimates were as follows: 4

The Corps’ Estimates

Item Original Estimate Revised Before Trial Revised at Trial Best & Final

1 Mob & Demob $ 437,698 $3,222,625 $3,426,031 $3,424,945

2 Dredging Mobile River 5,392,002 4,256,841 4,256,841 4,267,006

3 D/A Activities Dike 84,036 84,036 84,036 84,036

4 D/A Activities Operations 146,760 146,760 146,760 146,760

$6,060,496 $7,710,262 $7,913,668 $7,922,747.

The Best and Final Estimate (B & FE), DX 7, was increased by the Corps over the Original Estimate by the amount of $1,862,-252 ($7,922,747 - $6,060,495) or by 30.72%. The circumstances regarding the preparation of each are discussed seriatim, along with its impact on the award process.

Plaintiffs, a joint venture in which Weeks was to provide the financial assistance and Bean was to furnish the labor and equipment, submitted an $11,246,000 fixed lump-sum bid on the Mobile River dredging project. It estimated that the following costs would be incurred for each of the four bid items:

Item Amount

(1) Mobilization/Demobiliza- $3,700,000 tion

(2) Dredging Mobile River 7,416,000

(3) D/A Dike Construction 100,000

(4) D/A Operation and 30,000

Maintenance _

Total Bid $11,246,000.

Their bid was prepared by Mr. Ancil Taylor, the holder of a bachelor of science degree in construction engineering and plaintiff Bean’s Manager of Engineering and Estimating. Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Manson Constraction Co. v. United States
64 Fed. Cl. 746 (Federal Claims, 2005)
CW Government Travel, Inc. v. United States
61 Fed. Cl. 559 (Federal Claims, 2004)
Great Lakes Dredge & Dock Co. v. United States
60 Fed. Cl. 350 (Federal Claims, 2004)
Cavalier Clothes, Inc. v. United States
51 Fed. Cl. 399 (Federal Claims, 2001)
Overstreet Electric Co. v. United States
47 Fed. Cl. 728 (Federal Claims, 2000)
Mike Hooks, Inc. v. United States
42 Cont. Cas. Fed. 77,191 (Federal Claims, 1997)
Aerolease Long Beach v. United States
31 Fed. Cl. 342 (Federal Claims, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
36 Cont. Cas. Fed. 75,811, 19 Cl. Ct. 561, 1990 U.S. Claims LEXIS 41, 1990 WL 12226, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bean-dredging-corp-v-united-states-cc-1990.