Barlovento, LLC v. AUI, Inc.

District Court, D. New Mexico·Decided November 18, 2020·No. 1:18-cv-01112·Unknown

Opinion

UNITED STATES DISTRICT COURT DISTRICT OF NEW MEXICO

BARLOVENTO, LLC,

Plaintiff/Counter-Defendant,

v. Civ. No. 18-1112 GJF/JHR

AUI, INC.,

Defendant/Counterclaimant, and

WESTERN SURETY COMPANY,

Defendant.

MEMORANDUM OPINION AND ORDER ON DEFENDANT WESTERN SURETY’S MOTION FOR SUMMARY JUDGMENT

THIS MATTER is before the Court upon Defendant Western Surety Company’s “Motion for Summary Judgment on Count II of Barlovento’s Complaint” [ECFs 84-85] (“Motion”). The Motion is fully briefed.1 On February 12, 2020, the Court heard oral argument and DENIED this Motion from the bench. See ECF 140 at 305 (Court: “Western Surety’s Motion is denied on all grounds.”). To further explain and memorialize this ruling, the Court now issues the following decision. I. BACKGROUND On March 24, 2017, one week after Barlovento hired Defendant AUI, Inc. under a $3.7 million Subcontract to replace a 2,225-foot taxiway at Kirtland Air Force Base, AUI entered into a “Performance Bond” contract with Western Surety. The purpose of this Performance Bond was to guarantee that AUI would perform the Subcontract. Consequently, the Performance Bond required Western Surety, upon AUI’s “failure to promptly and faithfully perform the

1 See ECFs 98, 110 (response and reply). [Subcontract],” to “promptly remedy the default,” “[c]omplete the [Subcontract],” or provide Barlovento with a new contractor to complete the work. See ECF 85-1 at 2. After the construction project began, the Air Force answered Barlovento’s formal “Request for Information” by stating that the concrete pavement thickness was increased from 12 to 16 inches. Although the formal contract modification between the Air Force and Barlovento (“Mod

2”) was not executed until after AUI was terminated, AUI nevertheless placed three test lanes at this new thickness. Unfortunately, none of these test lanes met the required specifications, and when Barlovento issued its “Letter of Cure” to AUI on October 31, 2017, Barlovento specifically listed this failure as one of three “deficiencies” that could result in AUI’s termination. On December 5, 2017, Barlovento terminated the Subcontract with AUI. A few hours before doing so, Barlovento’s counsel notified Western Surety of the impending termination, in response to which Western Surety apparently offered to “tender a completion contractor” once Barlovento “obtain[ed] a few competitive bids for completion of AUI’s contract.” ECF 85-22 (memorandum of Western Surety’s Claims Consultant, Lisa C. Desantis). Western Surety claims,

however, that Barlovento’s counsel stated that Barlovento “already ha[d] a completion contractor,” “[did not] have time to wait for [Western] Surety’s process,” and “intend[ed] on moving forward with [Barlovento’s] completion contractor.” Id.; ECF 98-10 at 2. A week later, Barlovento indeed hired this replacement subcontractor, Southwest Concrete Paving Company (SWCPC), which eventually completed the project in late June 2018. See ECF 88-1 at 18-19. The summary judgment record is devoid of any evidence that Western Surety undertook to locate a replacement contractor, solicit bids for the completion of the project, or so much as visit the project site. The record is similarly devoid of any evidence of how much Western Surety would have paid for the completion of the remaining portion of AUI’s Subcontract and how that amount compared to what Barlovento paid SWCPC to finish the job. II. PARTIES’ PRIMARY ARGUMENTS Western Surety asserts that its Performance Bond obligations were discharged for either of two reasons. First, Western Surety contends that the four-inch (or 33 1/3 percent) increase in

concrete thickness “materially changed” the Subcontract without Western Surety’s consent. ECF 85 at 2, 7-11. Second, Western Surety argues that Barlovento “abridged” or “precluded” Western Surety from performing its bond obligation to tender a completion contractor. ECF 85 at 2, 6-7, 11-13. Barlovento, on the other hand, responds that the Court on summary judgment review should not conclude that Western Surety’s performance bond obligations were discharged on either ground. See ECF 98 at 16-20 (arguing, inter alia, that Western Surety (1) effectively consented in advance to (i.e., waived) such a change and (2) was not abridged or precluded from tendering a completion contractor).

III. LAW A. Summary Judgment Standard “The court shall grant summary judgment if the movant shows that there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.” Fed. R. Civ. P. 56(a). A fact is material when it “might affect the outcome of the suit under the governing [substantive] law,” and a dispute is genuine when “the evidence is such that a reasonable jury could return a verdict for the nonmoving party.” Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248 (1986). “A ‘judge’s function’ in evaluating a motion for summary judgment is not ‘to weigh the evidence and determine the truth of the matter but to determine whether there is a genuine issue for trial.’” Salazar-Limon v. City of Houston, 137 S. Ct. 1277, 1280 (2017) (quoting Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 249 (1986)); see also First Nat. Bank of Ariz. v. Cities Service Co., 391 U. S. 253, 289 (1968) (the question at summary judgment is whether a jury should

“resolve the parties’ differing versions of the truth at trial”). In evaluating such a motion, the Court must “view the facts and draw reasonable inferences ‘in the light most favorable to the party opposing the . . . motion.’” Scott v. Harris, 550 U.S. 372, 378 (2007) (quoting United States v. Diebold, Inc., 369 U.S. 654, 655 (1962)). B. Discharge of a Surety Under the federal law of government contracts,2 “[w]here, without the surety’s consent, the principal and the [obligee] modify their contract” the surety’s obligations may be discharged. Nat’l Sur. Corp. v. United States, 118 F.3d 1542, 1544 (Fed. Cir. 1997) (emphasis added) (quotation marks omitted).

“If the [surety] tenders complete or partial performance of the [surety’s] obligation and … the obligee unreasonably refuses such tender; the [surety’s] obligation is discharged to the extent that refusal of such tender causes the [surety] a loss.” Restatement (Third) of Suretyship and Guaranty § 46(2) (1996) (emphasis added); see also id. at cmt. a (defining a “tender” as “a valid and sufficient offer of performance,” i.e., one that is “to the proper person at the proper time and

2 The Performance Bond is “governed in accordance with the federal law of government contracts” and, “[t]o the extent that the federal law of government contracts is not dispositive, the laws of the State of New Mexico,” Subcontract at ¶ 10.8. ECF 202 at 5-9 (holding that the Performance Bond incorporates the Subcontract, including its choice-of-law provision); see also MACTEC, Inc. v. Bechtel Jacobs Co., LLC, 346 F. App’x. 59, 83 (6th Cir. 2009) (unpublished) (citing cases from the United States Court of Appeals for the Federal Circuit and the United States Court of Federal Claims as sources for “the federal law of government contracts”); Solitron Devices, Inc. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Barlovento, LLC v. AUI, Inc., (D.N.M. 2020).

Barlovento, LLC v. AUI, Inc. (Barlovento, LLC v. AUI, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

United States v. Diebold, Inc.
369 U.S. 654 (Supreme Court, 1962)
First Nat. Bank of Ariz. v. Cities Service Co.
391 U.S. 253 (Supreme Court, 1968)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
St. Paul Fire & Marine Insurance v. VDE Corp.
603 F.3d 119 (First Circuit, 2010)
Scott v. Harris
550 U.S. 372 (Supreme Court, 2007)
Lumbermens Mutual Casualty Co. v. United States
654 F.3d 1305 (Federal Circuit, 2011)
National Surety Corporation v. United States
118 F.3d 1542 (Federal Circuit, 1997)
St. Paul Fire & Marine Insurance v. City of Green River
93 F. Supp. 2d 1170 (D. Wyoming, 2000)
Sanders v. FedEx Ground Package System, Inc.
2008 NMSC 040 (New Mexico Supreme Court, 2008)
Hartford Fire Insurance Co. v. United States
254 F. Supp. 3d 1333 (Court of International Trade, 2017)
Fireman's Fund Insurance v. United States
92 Fed. Cl. 598 (Federal Claims, 2010)
Salazar-Limon v. City of Hous.
137 S. Ct. 1277 (Supreme Court, 2017)