Ames Construction, Inc. v. Clark County

District Court, D. Nevada·Decided June 26, 2020·No. 2:18-cv-00299·Unknown

Opinion

1 2 3 4 UNITED STATES DISTRICT COURT 5 DISTRICT OF NEVADA 6 * * *

7 AMES CONSTRUCTION, INC., Case No. 2:18-CV-299 JCM (GWF)

8 Plaintiff(s), ORDER

9 v.

10 CLARK COUNTY, et al.,

11 Defendant(s).

12 13 Presently before the court is Clark County and Clark County Department of Works’s 14 (collectively, “the county”) motion for summary judgment. (ECF No. 52). Ames Construction, 15 Inc. (“Ames”) filed a response (ECF No. 62), to which the county replied (ECF No. 64). 16 Also before the court is Ames’s request for oral argument. (ECF No. 66). 17 I. Background 18 The instant action arises from a variety of contractual claims resulting from a private 19 contractor’s performance of a government construction contract. 20 In April 2013, the county issued a request for a construction manager at risk (“CMAR”) 21 to assist in designing and building a flood wash to mitigate flooding issues in the city of Las 22 Vegas. (ECF No. 62 at 4). Ames submitted a proposal in response to this request, in which it 23 identified a flooding risk at the job site. Id. at 5. The county ultimately awarded the CMAR 24 contract to Las Vegas Paving (“LVP”). Id. LVP began constructing the flood wash, but it left 25 the project due to a dispute over cost. Id. at 11. 26 On July 9, 2015, the county issued an invitation to bid for the remainder of the project, 27 which entailed lining the Las Vegas Wash (the “Wash”) from Nellis Boulevard to Stewart 28 Avenue with concrete. (ECF No. 3 at 3). Subsequent amendments to the project included the 1 construction of a pedestrian bridge and trail work. Id. On September 15, 2015, the county 2 awarded Ames the contract for $20,440,260.05. Id. Separate Ames offices prepared the 2013 3 CMAR proposal and the 2015 bid. (ECF No. 62 at 5–6). Neither of the Ames offices knew of 4 the other’s work. Id. 5 The contract contained language indicating the average flow of water through the project 6 site was 9 cubic feet per second (“cfs”). (ECF No. 3 at 4). Pursuant to this clause and others 7 requiring submission of a “dewatering” plan to control potential flooding at the site, Ames 8 submitted a plan allowing the dewatering of flows up to 13 cfs, in excess of the 9 cfs the county 9 indicated as typical. Id at 5. 10 After beginning construction, Ames experienced significant delays due to flooding. Id. 11 at 8. The flow of water was much greater than the 9 cfs indicated in the contract. Id. Ames 12 measured over 10,000 cfs at the worksite, and requested additional time to complete the project 13 after altering plans regarding sequencing, necessary equipment, and repairs. Id.; (ECF No. 62 at 14 16). Ames alleges its damages caused by the delays and necessary repairs are over $14,000,000. 15 (ECF No. 3 at 8). 16 Ames subsequently brought the instant suit alleging a variety of contract claims centered 17 on the contention that the county affirmatively misrepresented the potential for flooding by 18 specifying 9 cfs as the typical flow rate. (See generally ECF No. 3). The county now moves for 19 summary judgment on all claims. (ECF No. 52). 20 II. Legal Standard 21 The Federal Rules of Civil Procedure allow summary judgment when the pleadings, 22 depositions, answers to interrogatories, and admissions on file, together with the affidavits, if 23 any, show that “there is no genuine dispute as to any material fact and the movant is entitled to a 24 judgment as a matter of law.” Fed. R. Civ. P. 56(a). A principal purpose of summary judgment 25 is “to isolate and dispose of factually unsupported claims.” Celotex Corp. v. Catrett, 477 U.S. 26 317, 323–24 (1986). 27 For purposes of summary judgment, disputed factual issues should be construed in favor 28 of the nonmoving party. Lujan v. Nat’l Wildlife Fed., 497 U.S. 871, 888 (1990). However, to 1 withstand summary judgment, the nonmoving party must “set forth specific facts showing that 2 there is a genuine issue for trial.” Id. 3 In determining summary judgment, a court applies a burden-shifting analysis. “When the 4 party moving for summary judgment would bear the burden of proof at trial, it must come 5 forward with evidence which would entitle it to a directed verdict if the evidence went 6 uncontroverted at trial. In such a case, the moving party has the initial burden of establishing the 7 absence of a genuine issue of fact on each issue material to its case.” C.A.R. Transp. Brokerage 8 Co. v. Darden Rests., Inc., 213 F.3d 474, 480 (9th Cir. 2000) (citations omitted). 9 By contrast, when the nonmoving party bears the burden of proving the claim or defense, 10 the moving party can meet its burden in two ways: (1) by presenting evidence to negate an 11 essential element of the nonmoving party’s case; or (2) by demonstrating that the nonmoving 12 party failed to make a showing sufficient to establish an element essential to that party’s case on 13 which that party will bear the burden of proof at trial. See Celotex Corp., 477 U.S. at 323–24. If 14 the moving party fails to meet its initial burden, summary judgment must be denied and the court 15 need not consider the nonmoving party’s evidence. See Adickes v. S.H. Kress & Co., 398 U.S. 16 144, 159–60 (1970). 17 If the moving party satisfies its initial burden, the burden then shifts to the opposing party 18 to establish that a genuine issue of material fact exists. See Matsushita Elec. Indus. Co. v. Zenith 19 Radio Corp., 475 U.S. 574, 586 (1986). The opposing party need not establish a dispute of 20 material fact conclusively in its favor. See T.W. Elec. Serv., Inc. v. Pac. Elec. Contractors Ass’n, 21 809 F.2d 626, 631 (9th Cir. 1987). It is sufficient that “the claimed factual dispute be shown to 22 require a jury or judge to resolve the parties’ differing versions of the truth at trial.” Id. 23 In other words, the nonmoving party cannot avoid summary judgment by relying solely 24 on conclusory allegations that are unsupported by factual data. See Taylor v. List, 880 F.2d 25 1040, 1045 (9th Cir. 1989). Instead, the opposition must go beyond the assertions and 26 allegations of the pleadings and set forth specific facts by producing competent evidence that 27 shows a genuine issue for trial. See Celotex, 477 U.S. at 324. 28 1 At summary judgment, a court’s function is not to weigh the evidence and determine the 2 truth, but to determine whether a genuine dispute exists for trial. See Anderson v. Liberty Lobby, 3 Inc., 477 U.S. 242, 249 (1986). The evidence of the nonmovant is “to be believed, and all 4 justifiable inferences are to be drawn in his favor.” Id. at 255. But if the evidence of the 5 nonmoving party is merely colorable or is not significantly probative, summary judgment may be 6 granted. See id. at 249–50. 7 The Ninth Circuit has held that information contained in an inadmissible form may still 8 be considered for summary judgment if the information itself would be admissible at trial. 9 Fraser v. Goodale, 342 F.3d 1032, 1036 (9th Cir. 2003) (citing Block v. City of Los Angeles, 253 10 F.3d 410, 418–19 (9th Cir. 2001) (“To survive summary judgment, a party does not necessarily 11 have to produce evidence in a form that would be admissible at trial, as long as the party satisfies 12 the requirements of Federal Rules of Civil Procedure 56.”)). 13 III.

Free access — add to your briefcase to read the full text and ask questions with AI

Ames Construction, Inc. v. Clark County, (D. Nev. 2020).

Ames Construction, Inc. v. Clark County (Ames Construction, Inc. v. Clark County) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

United States v. Spearin
248 U.S. 132 (Supreme Court, 1918)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Lujan v. National Wildlife Federation
497 U.S. 871 (Supreme Court, 1990)
J. L. Simmons Company, Inc. v. The United States
412 F.2d 1360 (Court of Claims, 1969)
Elte, Inc. v. S. S. Mullen, Inc.
469 F.2d 1127 (Ninth Circuit, 1972)
United States v. Clemmons J. Allen
10 F.3d 405 (Seventh Circuit, 1993)
Lipshie v. Tracy Investment Co.
566 P.2d 819 (Nevada Supreme Court, 1977)
Hilton Hotels Corp. v. Butch Lewis Productions, Inc.
808 P.2d 919 (Nevada Supreme Court, 1991)
Caravel/Woodwind Charters, Inc. v. Tahoe Keys Marina, LLC
438 F. Supp. 2d 1174 (E.D. California, 2006)
Holmes v. Howard
8 F. Supp. 2d 1269 (D. Kansas, 1998)
J.A. Jones Construction Co. v. Lehrer McGovern Bovis, Inc.
89 P.3d 1009 (Nevada Supreme Court, 2004)
Becho, Inc. v. United States
47 Fed. Cl. 595 (Federal Claims, 2000)