American Druggists Insurance v. Thompson Lumber Co.

349 N.W.2d 569, 1984 Minn. App. LEXIS 3145
CourtCourt of Appeals of Minnesota
DecidedMay 15, 1984
DocketC1-83-1737
StatusPublished
Cited by24 cases

This text of 349 N.W.2d 569 (American Druggists Insurance v. Thompson Lumber Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
American Druggists Insurance v. Thompson Lumber Co., 349 N.W.2d 569, 1984 Minn. App. LEXIS 3145 (Mich. Ct. App. 1984).

Opinion

OPINION

PARKER, Judge.

This is an appeal by a surety on a contractor’s bond from the entry of summary judgment in favor of a subcontractor. The trial court applied the doctrine of collateral estoppel by judgment entered in favor of a fellow subcontractor. The dispute focuses upon whether the subcontractor’s claim was timely filed and whether the amount of the claim was properly determined by the trial court. The surety contends that (1) the doctrine of collateral estoppel was improperly applied by the trial court; and (2) there were genuine issues of material fact which precluded summary judgment. In a cross appeal, the contractor alleges error for not being awarded its attorney's fees. The contractor also seeks attorney’s fees for this appeal. We affirm in part, modify in part and remand to the trial court for consideration of attorney’s fees.

FACTS

The City of Shorewood entered into a contract with Zagar Construction Company for the construction of a city hall. Zagar obtained a contractor’s bond from American Druggists’ Insurance Company (ADI) in the amount of $66,089, the original contract price. ADI agreed as surety to “pay all persons who have contracts directly with” Zagar for labor or materials in the performance of the contract.

Zagar subcontracted part of the job to Berg Drywall, Inc., and Thompson Lumber Company. By mid-December 1979, Zagar owed Thompson Lumber almost $25,000 and Berg Drywall $5,600.

On March 10, 1980, the City of Shore-wood approved payment of 90 percent of the amount then owing to Zagar. The remaining ten percent was withheld for “unknown contingencies.” The City approved payment of the withheld ten percent on June 23, 1980, thereby accepting completion of the contract. With money still due, Thompson Lumber filed a written notice of claim on July 25, 1980; Berg Drywall filed its notice on July 31, 1980.

Both Berg Drywall and Thompson Lumber sued Zagar and ADI. Zagar eventually filed for bankruptcy. The Berg Drywall case was decided first; the trial court found that Berg Drywall’s notice of claim was timely and entered judgment in its favor.

*572 Thompson Lumber then moved for summary judgment. The trial court granted the motion. The court invoked collateral estoppel in ruling that ADI could not reliti-gate the issue of whether a timely claim was made, based on the earlier Berg Drywall decision. The court also found that no genuine issue of material fact existed and entered judgment in the amount of $38,-530.21, plus costs, disbursements and interest.

ISSUES

1. Did the trial court properly invoke collateral estoppel to bar ADI from reliti-gating whether Thompson Lumber’s notice of claim was timely filed?

2. Were there any genuine issues of material fact which precluded the trial court from granting summary judgment for Thompson Lumber?

3. Did the trial court err in not granting Thompson Lumber attorney’s fees for successfully maintaining its action?

4. Is Thompson Lumber entitled to its attorney’s fees incurred as a result of this appeal?

DISCUSSION

I

The contractor’s bond is required for substantial public projects. Minn.Stat. § 574.26 (1982). It is designed “to protect laborers and material men who perform labor or furnish material for the execution of a public work to which the mechanic’s lien statute does not apply.” Ceco Steel Products Corp. v. Tapager, 208 Minn. 367, 370, 294 N.W. 210, 212 (1940), quoting A.J. Chromy Construction Co. v. Commercial Mechanical Services, Inc., 260 N.W.2d 579, 581 (Minn.1977). As a prerequisite to a suit on a contractor’s bond, a claim must be filed “within 90 days after the completion of the contract and acceptance thereof by the proper public authorities.” Minn.Stat. § 574.31 (1982) (emphasis added).

In the Berg Drywall case, the trial court established that the City accepted Zagar’s performance on June 23, 1980. ADI urged in that suit that the City accepted on March 10, 1980, thus barring any claims filed after June 10, 1980.

Here, ADI urges it was not collaterally estopped from relitigating the date of acceptance because the Berg Drywall case was subsequently appealed to the Minnesota Supreme Court and hence was not a final judgment.

Collateral estoppel precludes the relitigation of issues already litigated in a prior action. Hauser v. Mealey, 263 N.W.2d 803 (Minn.1978). In Ellis v. Minneapolis Comm’n on Civil Rights, 319 N.W.2d 702 (Minn.1982), the Supreme Court articulated four factors necessary to invoke this doctrine:

1. Identical issue in prior suit;

2. Final judgment on merits;

3. Estopped party a party or in privity with party in prior suit; and

4. Estopped party given a full and fair opportunity to be heard on the adjudicated issue.

The only dispute is whether the Berg Drywall judgment is deemed final. This issue was essentially determined in State ex rel. Spratt v. Spratt, 150 Minn. 5, 184 N.W. 31 (1921), where the Minnesota Supreme Court stated that “an appeal with a supersedeas bond does not vacate or annul the judgment appealed from, and the matters determined by it remain res judica-ta until it is reversed.” See Wegge v. Wegge, 252 Minn. 236, 89 N.W.2d 891 (1958); Manemann v. West, 218 Minn. 602, 17 N.W.2d 74 (1944); Bolsta v. Bremer, 212 Minn. 269, 3 N.W.2d 430 (1942). See also Wilcox Trux, Inc. v. Rosenberger, 169 Minn. 39, 209 N.W. 308 (1926) (perfection of appeal after final judgment does not affect the judgment as a bar).

ADI’s contention that the Berg Drywall judgment is unclear and inconsistent about its grounds is without merit. The Berg Drywall decision clearly states that the City accepted on June 23, 1980.

*573 II

ADI also contends there were genuine issues of material fact which precluded the trial court from granting summary judgment under Rule 56 of the Minnesota Rules of Civil Procedure.

In considering summary judgment, the nonmoving party must be given the benefit of that view of the evidence which is most favorable to him and is entitled to have all doubts and inferences resolved against the moving party. Nord v. Herreid, 305 N.W.2d 337, 339 (Minn.1981). Upon review, this court must determine (1) whether there are any genuine issues of material fact and (2) whether the trial court erred in its application of the law. Betlach v. Wayzata Condominium,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Homestar Prop. Solutions, LLC v. Safeguard Props., LLC
370 F. Supp. 3d 1020 (D. Maine, 2019)
Stratasys, Inc. v. Krampitz
D. Minnesota, 2018
Mohrman & Kaardal, P.A. v. Gene Rechtzigel
Court of Appeals of Minnesota, 2015
FIA Card Services, N. A. v. Charles T. Gholl
Court of Appeals of Minnesota, 2014
Campbell v. Lake Hallowell Homeowners Ass'n
852 A.2d 1029 (Court of Special Appeals of Maryland, 2004)
Egge v. Healthspan Services Co.
208 F.R.D. 265 (D. Minnesota, 2002)
Cherne Contracting Corp. v. Wausau Insurance Companies
572 N.W.2d 339 (Court of Appeals of Minnesota, 1997)
In Re DEF Investments, Inc.
186 B.R. 671 (D. Minnesota, 1995)
Gibson v. Gibson
149 B.R. 562 (D. Minnesota, 1993)
Reese Design, Inc. v. I-94 Highway 61 Eastview Center Partnership
428 N.W.2d 441 (Court of Appeals of Minnesota, 1988)
Lampert Lumber Co. v. Ram Construction
413 N.W.2d 878 (Court of Appeals of Minnesota, 1987)
Butler Manufacturing Co. v. Miranowski
390 N.W.2d 380 (Court of Appeals of Minnesota, 1986)
Cook v. Connolly
353 N.W.2d 184 (Court of Appeals of Minnesota, 1984)
Barry v. Johnson
350 N.W.2d 498 (Court of Appeals of Minnesota, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
349 N.W.2d 569, 1984 Minn. App. LEXIS 3145, Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-druggists-insurance-v-thompson-lumber-co-minnctapp-1984.