National Surety Co. v. Erler

220 N.W. 543, 175 Minn. 14, 1928 Minn. LEXIS 820
CourtSupreme Court of Minnesota
DecidedJune 22, 1928
DocketNo. 26,647.
StatusPublished
Cited by2 cases

This text of 220 N.W. 543 (National Surety Co. v. Erler) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
National Surety Co. v. Erler, 220 N.W. 543, 175 Minn. 14, 1928 Minn. LEXIS 820 (Mich. 1928).

Opinion

Stone, J.

In 1928 plaintiff became surety for defendant as the contractor on three state highway jobs on state “projects” Nos. 5-28, 3-34 and 3-39, and in this action seeks to recover additional premiums for alleged “overrun” on a special covenant in the applications for the bonds, under all three contracts. The overrun, so-called, consists of extra work which plaintiff claims was done by defendant under the contracts whereby the total cost was so increased that additional premiums for the contract bonds accrued. Defendant admitted some overrun and that a sum much less than that claimed was due, and tendered judgment accordingly. The trial without a jury resulted in a decision for defendant. Plaintiff appeals from the order denying its alternative motion for amended findings or a new trial.

PROJECT No. 5-28. The contract embodied the “proposal,” the “general specifications” for highway work and the special ones for “bridges and monolithic culverts.” The proposal was for the removal of an old bridge and the construction of two new ones, numbered 4054 and 4128. The specifications required the contractor to perform “such work, in additional quantities other than those designated in the estimate, as may be deemed necessary to fully complete the highway [bridges] as planned and contemplated” ' and also to perform “unclassified work,” for which there is no quantity and price included in the contract, “whenever, to complete fully the work as contemplated, it is deemed necessary or desirable,” at prices to be fixed in a stated manner.

There is nothing about the contract, including the specifications, to indicate that the work would include anything more than the removal of the old bridge and the construction of the two designated new ones, including of course anything then unforeseen but which might subsequently be added to complete that work. The issue arises, because, without any new proposal or contract in any formal *16 sense, the contractor erected within the limits of project No. 5-28 two additional bridges, Nos. 4269 and 4270. They were made necessary by the abandonment of a channel change contemplated when the original contract was let to defendant and were built by defendant under an “order for unclassified work.” According to the final estimates of the state highway department, bridges 4054 and 4128 (covered by the original contract) cost when completed respectively $3,742.59 and $9,073.81, a total of $12,816.40, while bridges 4269 and 4270, built under the work order, cost respectively $4,863.60 and $7,260.15, or a total of $12,123.75.

Without going into detail, we state as a fair assumption from the record that all the work under unclassified orders was by defendant and the highway department considered as having been done “under the terms,” as the orders state, of the original contract. The bonds sued upon were furnished with the three original formal contracts and are conditioned for the completion of the contracts “in accordance” with their terms and the payment of all claims chargeable against the work.

The principal argument for appellant is predicated upon the statutory law pursuant to which public contractors’ bonds are given. It is provided by G-. S. 1923, § 9700, that no contract with the state for public work “shall be valid for any purpose” unless the required bond is furnished; and in § 9702, that no “modification, or change of the contract, or change in the work covered thereby” shall release the sureties on the bond. We assume that all defendant’s work done on each project under unclassified work orders was considered by the highway department as done under and pursuant to the original contract. That doubtless is convenient for purposes of administration and explains the omission to require bonds when the additional work was let to defendant.

The postulate for plaintiff is correct that “parties are presumed to contract with reference to the existing law affecting or annexing incidents to their contracts.” O’Neil v. St. Olaf’s School, 26 Minn. 329, 332, 4 N. W. 47. The first present effect is that under § 9702 of our statute above referred to plaintiff as surety was not released by any mere modification of the bonded contracts. In § 9700, upon *17 which appellant relies principally, we find nothing extending, beyond the limits fixed by its express terms and purpose, the scope of any bond or contract. There is only the denouncement of invalidity on any contract for public work within the field of the statute which is not underivritten by the required bond. Nothing about the statute can lead to the result contended for by appellant. There is no ambiguity about the work contemplated by the original contract for the bridges. Neither is there uncertainty about the conclusion that the overrun for which plaintiff claims the additional premium on that job was work, or the cost of work, wholly outside of and beyond the scope of the original contracts. It was not required to change, perfect, or enlarge the work contemplated by them, but was rather something independent of and in addition thereto.

Counsel for appellant are correct also in saying that the test of defendant’s liability for additional premium in connection with the work designated as overrun is whether plaintiff would have been liable under its bond for any claim arising in favor of a laborer, subcontractor or materialman. It is from that viewpoint that we consider the problem, and for the reason indicated we conclude that the bridge work done under the unclassified orders, being beyond the scope of the original contracts, could not have been made the basis of a valid claim against plaintiff as surety for defendant.

It will be a source of regret to us if this view of the matter entails difficulty or even uncertainty upon those in charge of or in any way concerned with public contracts. But if the practice is to continue of accomplishing, under unclassified work orders or the like, projects which as to the original contract are wholly new, unrelated and additional, it must be appreciated that they are in fact the subject matter of new and independent contracts with respect to which there must be observed the statutory requirement of a bond. Perhaps, so far as the highway department is concerned, a form of bond can be used which Avill avoid the difficulty by being sufficiently elastic in its terms to cover not only the original contract but also any work done by the contractor under work orders, within *18 such limitations of time and territory as may be agreeable to the parties involved.

The contractor and highway department considered defendant’s work under unclassified orders as done under the original contracts. Such an assumption by the contracting parties may have its intended effect as between them, but its result upon a stranger to the new and substituted agreement must find its limitations in something binding upon such stranger. The terminology used by the contracting parties in characterizing what they have done cannot foreclose his rights. Plaintiff as surety was no party to the unclassified work orders. There was nothing in the contract, the bond or the application for the latter which, unaided by some new commitment on the part of plaintiff as surety, could extend its obligation to anything beyond the reach of the original contract. The latter of course would include anything in the way of a mere variation or change in the original calculated to achieve the same object.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

American Druggists Insurance v. Thompson Lumber Co.
349 N.W.2d 569 (Court of Appeals of Minnesota, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
220 N.W. 543, 175 Minn. 14, 1928 Minn. LEXIS 820, Counsel Stack Legal Research, https://law.counselstack.com/opinion/national-surety-co-v-erler-minn-1928.