Reese Design, Inc. v. I-94 Highway 61 Eastview Center Partnership

428 N.W.2d 441, 1988 Minn. App. LEXIS 810, 1988 WL 86022
CourtCourt of Appeals of Minnesota
DecidedAugust 23, 1988
DocketC8-87-2392
StatusPublished
Cited by8 cases

This text of 428 N.W.2d 441 (Reese Design, Inc. v. I-94 Highway 61 Eastview Center Partnership) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Reese Design, Inc. v. I-94 Highway 61 Eastview Center Partnership, 428 N.W.2d 441, 1988 Minn. App. LEXIS 810, 1988 WL 86022 (Mich. Ct. App. 1988).

Opinion

OPINION

FOLEY, Judge.

This is an appeal from an order for judgment denying the claim of appellant Reese Design, Inc. for fees due pursuant to a contract with a developer. Reese asserts that it was authorized to prepare final plans and specifications and should be paid for services rendered, and further that it is entitled to relief on the basis of the doctrine of account stated due to the failure of respondent CHK Partnership to object to the billings.

The trial court found that Reese was not authorized to prepare final plans and specifications, that the doctrine of account stated was not pleaded and that it did not apply to the facts of this case and that CHK objected to the billings. We affirm in part, reverse in part and remand for amended judgment.

FACTS

This appeal involves a dispute between an architectural firm, Reese, and a general partnership, CHK, as to whether architectural and engineering fees are due pursuant to a June 17, 1983 contract entered into with a developer. The entire contract consisted of a three-paragraph letter drafted by Reese. The terms of the contract were ambiguous and are now subject to interpretation. It is long understood a writing that is vague or ambiguous must be construed against the drafter.

The central issue at trial was whether Reese was authorized to begin work on the final phase of the project. The trial court held that there was no such authorization. Reese argues on appeal that the findings of the trial court are clearly erroneous.

Reese’s own expert witness, David Anderson, President of the Minneapolis Chapter of the American Institute of Architects, testified that the AIA discourages the use of letter agreements; that the terms “preliminary” and “final” are subject to individual interpretation; that the agreement drafted by Reese does not meet the AIA minimum statement of services to be included in letter agreements; and that unless services and compensation are fully defined in a letter agreement, the agreement can become burdensome to both parties as the project progresses.

The preliminary phase of the project had an estimated cost of $12,000 and the final design phase $116,000. A second letter from Reese clarified that the estimated fees of $12,000 and $116,000 contained in the contract are máximums. A third letter from Reese stated that the payment for services in the preliminary phase was expected around October 1, 1983 and that it was willing to wait until November 1, 1983 before charging interest on that amount. Reese was paid $12,000 on or about November 1, 1983.

Reese mailed bills to CHK on a monthly basis. CHK admits receiving these monthly bills but contends that the agreement called for a “lump sum” payment, and that it considered the monthly bills simply a means for Reese to accomplish its accounting. CHK did not protest many of these billings because of this anticipated lump sum payment, but it did protest the billings after it realized Reese had exceeded its authorized fees.

CHK was in the process of obtaining FHA financing. The FHA application process outlines how design and construction are allowed to proceed, and which steps *443 must be taken in order to proceed into the next phase. Reese had been involved with many other FHA projects and knew of the requirements necessary to complete before moving on to another stage.

In August 1983 the developers began discussions with Lynn Burton of Northland Mortgage to see if they could obtain FHA insurance for their project. The FHA application process involves three stages: (1) site and market analysis stage; (2) conditional commitment stage; and (3) firm commitment stage. At each stage, architectural drawings are required. At the site and market analysis stage, the requirement is minimal. At the conditional commitment stage, more extensive “schematic” drawings are required. At the firm commitment stage, detailed final plans and specifications are required.

CHK did not make application for a conditional commitment. Had it done so, an FHA staff architect would have been appointed to review the architectural documents. This review is one of the major purposes of the conditional commitment stage. An architect typically needs anywhere from 30 to 60 days to address the comments made by the FHA staff architect. The FHA will not accept a project unless the changes the FHA staff architect requests are either made or successfully negotiated between the architect, the borrower, the FHA architect and the FHA underwriter.

Reese testified that work began on final plans and specifications on September 15, 1983 and that it was aware that the FHA architect’s comments must be incorporated into the final plans. Reese testified that it was not sure whether or not an FHA architect was appointed for this project, even though it was Reese’s job to work with the FHA architect. The fact is that no FHA architect was appointed, and there was no review of Reese’s plans.

An “intake” meeting took place between the FHA and the developer on September 20, 1983. Reese attended. Burton testified that she was “extremely discouraged” about the project after this meeting, and that given questions about the project’s feasibility, she could not recommend making a conditional commitment application.

At the end of September or the beginning of October 1983, CHK received a telephone call from Reese. One of the partners of CHK, respondent Karl Keller, testified that he had been bugging another partner, respondent Donald Christenson, to get a cost estimate for the project. Reese told Keller that it needed $20,000 to supply Christenson with the plans needed to get a cost estimate. Keller discussed the matter with Christenson and agreed to spend the additional $20,000.

Reese denies that this agreement was reached. However, Reese testified that Keller authorized it to prepare “design development” plans. Design development plans are very detailed and involve the mechanical, electrical, structural and landscaping aspects of the development, according to Anderson.

CHK paid Reese $12,000 on or about November 1, 1983 and $10,000 on or about April 24,1984. The April 24,1984 payment was accompanied by a note which promised “further payments on account whenever possible.” Keller testified that the reference to “further payments” is a reference to part of the additional $20,000 that CHK promised to pay Reese.

Keller testified that he called Reese in December 1983 and told him to cease all work. Reese testified that Keller asked him to cease all work in January 1984.

Prior to this, Reese maintains that it was fully authorized to prepare final plans and specifications. However, Reese admitted that there was no formal authorization to prepare final plans and specifications. Reese contends that it was given authorization by the receipt of an FHA checklist from one of the partners of CHK, respondent Harry Hadd. Hadd testified that he had never authorized Reese to prepare final plans and specifications.

The second event which Reese considered authorization was a conversation with Christenson during September 1983. At that time, Christenson said he wanted some plans to take to the city for initial review *444 for a building permit, according to Reese.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Teng Moua v. Jani-King of Minnesota, Inc.
810 F. Supp. 2d 882 (D. Minnesota, 2011)
Sound of Music Co. v. Minnesota Mining & Manufacturing Co.
389 F. Supp. 2d 988 (N.D. Illinois, 2005)
Ventura v. Titan Sports, Inc.
65 F.3d 725 (Eighth Circuit, 1995)
Krogness v. Best Buy Co., Inc.
524 N.W.2d 282 (Court of Appeals of Minnesota, 1994)
In Re Marriage of Weinstein
470 N.E.2d 551 (Appellate Court of Illinois, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
428 N.W.2d 441, 1988 Minn. App. LEXIS 810, 1988 WL 86022, Counsel Stack Legal Research, https://law.counselstack.com/opinion/reese-design-inc-v-i-94-highway-61-eastview-center-partnership-minnctapp-1988.