Lampert Lumber Co. v. Ram Construction

413 N.W.2d 878, 1987 Minn. App. LEXIS 4919
CourtCourt of Appeals of Minnesota
DecidedOctober 20, 1987
DocketC7-87-634
StatusPublished
Cited by4 cases

This text of 413 N.W.2d 878 (Lampert Lumber Co. v. Ram Construction) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lampert Lumber Co. v. Ram Construction, 413 N.W.2d 878, 1987 Minn. App. LEXIS 4919 (Mich. Ct. App. 1987).

Opinion

OPINION

NORTON, Judge.

This appeal is from a trial court judgment and an order denying a new trial regarding appellants’ fraudulent misrepresentation. Appellants claim the trial court erred because (1) the elements of fraudulent misrepresentation are not supported by the evidence and (2) the court improperly calculated interest owing on the unpaid *880 balance of the parties’ contract. We affirm.

FACTS

In about 1977, appellant Howard Boever, on behalf of appellant general contractor Ram Construction, Inc. (Ram), first began purchasing building materials from respondent Lampert Lumber Company (Lampert). It was respondent's practice to require customers to sign a credit agreement when opening a charge account. That agreement provided the customer would pay a 1.33% per month finance charge on overdue payments. Ram arranged more than 100 project purchases with Lampert over the next seven years and each billing statement indicated the finance charge agreement.

In early 1983, Ram prepared a bid concerning construction work in the Amhoist Tower in St. Paul. The project required completion of corridors on floors 19 to 25 and a model condominium on floor 21. Ram received an estimate of $60,255.66 from Lampert for the necessary construction materials. The Amhoist Tower owners awarded Ram the contract and in April 1983, after receiving materials from Lam-pert, Ram started construction.

During the course of construction, additional materials had to be supplied by Lam-pert to Ram. An additional billing of $4750.73 resulted. Replacement materials for those of inferior quality were also sent to Ram, which charged back the $3886.75 cost of the materials to Lampert.

In early 1984, confusion existed regarding the proper amount owed Lampert by Ram. Appellant Boever and Lampert manager Robert Hoffman and Lampert salesman Dale Swails met to discuss the problems. Several adjustments were made to the Ram account concerning double billings, billing extension errors, incorrect prices, returned materials, and reversal of certain finance charges. Swails testified all of Boever’s complaints were addressed. Apparently the total amount owing was not expressly discussed. Lampert believed Ram owed $43,271.37, while Boever thought only $20,033.71 was owing.

Lampert complained to Boever regarding untimely payments and considered filing a mechanics’ lien by the February 20, 1984 deadline. Ram had paid $41,085.93 on its account. Boever urged Lampert not to file its lien because that action would only further delay payment and assured Hoffman the account would be paid in one or two weeks. Boever represented to Lampert, as found by the trial court:

a. Payments due to Ram on the Am-hoist Tower project had been delayed and that’s why Lampert had not yet been paid;
b. Lampert would be paid in full when Ram received payment from the owners of the Amhoist Tower; and
c. Ram had enough money coming on the Amhoist Tower project to pay off all of its subcontractors and material-men on the project.

By February 20, 1984, Ram, unknown to Lampert, had received from the Amhoist Tower owners $61,350.96 more than it had paid out to subcontractors and material-men. The owners still owed Ram $28,-971.94, which they subsequently paid. Boever stated at that point he anticipated receipt of an additional $15,000 from the building owners for extra work performed by Ram. No formal request was made for that money, however, and that $15,000 was never received. Boever never guaranteed payment of a specific amount. Based on Boever’s representations, Lampert decided not to file a mechanics’ lien.

Subsequent to February 1984, Ram paid Lampert $14,926.52 on its account. Additional meetings were held between Ram and Lampert to determine the proper amount owed and the structure of payment. As a result of negotiations, the total amount owed as of May 1985 was agreed to be $32,753.99. Lampert offered Boever a written agreement regarding payment, including a personal guarantee from Boe-ver, but Boever declined to sign.

Lampert sued Ram and Boever in October 1985 and served an amended summons and complaint in May 1986. Lampert sought compensatory damages in excess of *881 $45,000 plus interest for appellants’ fraudulent misrepresentation and conversion.

By order filed November 25, 1986, the trial court awarded respondent $39,789.22, holding both appellants liable. Ram is presently inactive and Boever has at all times been the sole officer and shareholder of Ram. The ordered judgment included $23,174.36 for building materials plus finance charges based on 1.33% monthly interest on overdue charges which the court found to equal $16,614.86. Judgment was entered accordingly January 8, 1987. Appellants’ motion for amended findings, or alternatively a new trial, was denied by order filed March 16, 1987. This appeal is made from both the judgment and the post-trial motion.

ISSUES

1. Does the evidence support the elements of appellant Boever’s fraudulent misrepresentation?

2. Did the trial court properly find the amount of finance charges owed respondent?

ANALYSIS

1. Appellants request the judgment against Howard Boever be vacated in its entirety because the evidence presented by respondent does not satisfy the elements of fraudulent misrepresentation. Those elements are:

1. There must be a representation;
2. That representation must be false;
3. It must have to do with a past or present fact;
4. That fact must be material;
5. It must be susceptible of knowledge;
6. The representer must know it to be false, or in the alternative, must assert it as of his own knowledge without knowing whether it is true or false;
7. The representer must intend to have the other person induced to act, or justified in acting upon it;
8. That person must be so induced to act or so justified in acting;
9. That person’s action must be in reliance upon the representation;
10. That person must suffer damage;
11. That damage must be attributable to the misrepresentation, that is, the statement must be the proximate cause of the injury.

Davis v. Re-Trac Manufacturing Corp., 276 Minn. 116, 117, 149 N.W.2d 37, 38-39 (1967).

a. Past or Present Facts.

Appellants claim Boever’s representations concerned future.intentions or opinions that do not constitute a basis for misrepresentation. See Cady v. Bush, 283 Minn. 105, 109, 166 N.W.2d 358, 361 (1969) (representations of expectation regarding future acts or events are nothing more than conjecture); Sievert v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

David Coyne v. Messerli & Kramer P.A.
895 F.3d 1035 (Eighth Circuit, 2018)
Mohrman & Kaardal, P.A. v. Gene Rechtzigel
Court of Appeals of Minnesota, 2015
FIA Card Services, N. A. v. Charles T. Gholl
Court of Appeals of Minnesota, 2014
Minnesota Forest Products, Inc. v. Ligna MacHinery, Inc.
17 F. Supp. 2d 892 (D. Minnesota, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
413 N.W.2d 878, 1987 Minn. App. LEXIS 4919, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lampert-lumber-co-v-ram-construction-minnctapp-1987.