Guy T. Bisbee Co. v. Granite City Investing Corp.

199 N.W. 14, 159 Minn. 238, 1924 Minn. LEXIS 613
CourtSupreme Court of Minnesota
DecidedMay 2, 1924
DocketNo. 23,820
StatusPublished
Cited by10 cases

This text of 199 N.W. 14 (Guy T. Bisbee Co. v. Granite City Investing Corp.) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Guy T. Bisbee Co. v. Granite City Investing Corp., 199 N.W. 14, 159 Minn. 238, 1924 Minn. LEXIS 613 (Mich. 1924).

Opinion

LrEES, C.

Appeal from the denial of a new trial of an action for the foreclosure of mechanics’ liens on the Breen Hotel in the city of St. Cloud.

Appellant claims that the lien of a mortgage it holds has priority over respondents’ liens because they waived their right to claim priority. In its answer appellant alleged that the hotel was in process of construction when the owner applied for a loan of $175,-000, to be secured by a mortgage, and that appellant refused to make the loan unless respondents’ liens were removed or made subordinate to the mortgage. It alleged that thereupon the respondents executed and caused delivery to be made to appellant of waivers in writing of any right of lien they had which might be superior to the mortgage.

The construction of the hotel was begun in 1919 by a corporation having as its active officers Henry J. Breen and John Hesse. In 1920 the funds of the corporation were running low and it became necessary to float a loan. Paul Cook, who conducted an insurance agency in St. Cloud and who had previously placed loans with appellant, undertook to procure the money. Claude Bennethum was appellant’s agent in Minnesota in charge of its loans. After inspecting the property with Cook, he transmitted an application for the loan to appellant. The application was accepted, subject to the condition that a satisfactory bond be furnished to protect the mortgage against existing mechanics’ liens. An application for the bond was made to the Maryland Casualty Company, accompanied [240]*240by the hotel company’s financial statement, which showed that the sum total of the company’s assets and the amount of the proposed loan would not cover the cost. of completing the building. Upon that showing the Casualty Company declined to write the bond, unless waivers of liens were furnished sufficient in amount to cover the difference between the cost of completing the building and the funds available for that purpose. Hesse undertook to secure the necessary waivers and obtained respondents’ signatures to an instrument which, by its terms, amounted to a waiver of all lien rights. This the Casualty Company would not accept, insisting that each lien claimant should sign a separate waiver of the right of priority over the mortgage. Cook prepared such waivers and he and Hesse procured the respondents’ signatures thereto. After referring to appellant’s mortgage, the waivers read as follows:-

“And the undersigned hereby agrees to protect said mortgage as a first lien * * * prior and superior to any lien or right of lien now filed or claimed * * * against said property.”

The trial court found that the waivers were obtained by means of representations made by the hotel company and all parties interested with it that, in consideration of their execution and delivery, the claims of the signers should be paid out of the proceeds of the mortgage loan; that each waiver was signed and delivered upon that express understanding; that none of the claims were paid; that the representations were known to be false by the persons who made them, were made to induce the respondents to give up their lien rights, and were relied upon. The court also found that appellant’s agents and the officers and agents of the hotel company were jointly interested in obtaining the waivers, and that appellant had full knowledge of the representations made to obtain them. It was therefore held that the waivers were void and judgment was ordered in respondents’ favor for the amount of their liens, with priority over the mortgage.

Appellant’s principal contentions are: (1) That the evidence does-not sustain the finding with respect to its knowledge of the making of the representations; (2) that the representations were of a prom[241]*241issory nature, and, unless they were made with no intention of fulfilling them, there was no actionable fraud.

If Bennethum knew that either Hesse or Cook had represented that respondents’ claims would be paid and had assumed to speak for appellant, and with that knowledge accepted the waivers in behalf of his company, the matter of Hesse and Cook’s prior authority ceases to be material.

It is well settled that one who adopts the unauthorized act of another, done in his behalf, and receives the benefits thereof, should be held to have adopted and ratified the instrumentalities by which such benefits were obtained. The cases so holding are collected in Roseberry v. Hart-Parr Co. 145 Minn. 142, 176 N. W. 175.

Cook prepared the waivers and testified that he told Bennethum he had to get them to obtain the indemnity bond and that he thought he kept Bennethum informed as to all the details. Asked whether he told him that respondents expected to have their claims paid out of the proceeds of the mortgage loan, he answered: “I didn’t have to tell him that. It was understood that was what the money was for.” But in the next breath he said: “I never explained to Bennethum any details of the lien waivers.”

Hesse testified that Cook brought Bennethum to him in St. Cloud; that he went to Bennethum’s office and talked with him about waivers; that he kept him informed as to the progress made in getting them and advised him of whatever he (Hesse) was doing in his efforts to get them; that at one time he and Cook were together at Bennethum’s office and talked with him, and that Cook went out to aid him in securing the waivers as a result of the talk. He asserted, however, that the only reason for getting them was the insistence of the Casualty Company that lien claims amounting to at least $60,000 must be waived before the indemnity bond would be written, and that neither he nor Cook were representing Benne-thum or his company in anything they did.

Bennethum testified that he never mentioned the subject of waivers to Hesse or Cook, did not know they were getting them or had them until they were turned over by the Casualty Company, but a vigorous and searching cross-examination finally elicited the state[242]*242ment that the matter of waivers was the subject of conversations he had with Hesse “when it came to a show-down.”

The general agent of the Casualty Company testified that Cook was the company’s local agent at St. Cloud, through whom the application for the bond was received, but that he was not directed to assist Hesse in getting the waivers and must have done so upon his own motion or at the instance of some one other than the Casualty Company. Cook and Bennethum had known each other for 20 years. Cook testified that he had “brokered” loans with him many times, that he had no authority to act on applications, but submitted them to Bennethum for his approval; that he received a commission when loans were accepted, and in this instance received appellant’s draft for $1,750 as his commission. Bennethum’s explanation of this was that the hotel company agreed to pay a commission of 5 per cent if the loan was made; that one-fifth of it went to Cook and the remainder to him; that appellant issued a voucher to him for $7,025, but he turned it back without cashing it, so in reality appellant received a profit of $7,000 in addition to interest at the rate of 7 per cent on the amount of the loan.

Bennethum knew that the application for the loan would uot be accepted unless an Indemnity bond was procured. To get the bond, a large portion of the lien claims must be released. Cook was interested in getting his commission. Bennethum was interested in getting $7,000, either for himself or his company. There was a substantial profit to be made if respondents’ liens were waived..

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cohen v. Cowles Media Co.
445 N.W.2d 248 (Court of Appeals of Minnesota, 1989)
Lampert Lumber Co. v. Ram Construction
413 N.W.2d 878 (Court of Appeals of Minnesota, 1987)
Wood v. Schlagel
375 N.W.2d 561 (Court of Appeals of Minnesota, 1985)
Carney v. Farmers & Merchants State Bank
263 N.W. 901 (Supreme Court of Minnesota, 1935)
Greear v. Paust
256 N.W. 190 (Supreme Court of Minnesota, 1934)
McDermott v. Ralich
247 N.W. 683 (Supreme Court of Minnesota, 1933)
Conolly v. Foster
242 N.W. 334 (Supreme Court of Minnesota, 1932)
Breeding v. Melson
143 A. 23 (Supreme Court of Delaware, 1927)
Engen v. Merchants & Manufacturers State Bank
204 N.W. 963 (Supreme Court of Minnesota, 1925)

Cite This Page — Counsel Stack

Bluebook (online)
199 N.W. 14, 159 Minn. 238, 1924 Minn. LEXIS 613, Counsel Stack Legal Research, https://law.counselstack.com/opinion/guy-t-bisbee-co-v-granite-city-investing-corp-minn-1924.