Wick v. Murphy

54 N.W.2d 805, 237 Minn. 447, 1952 Minn. LEXIS 737
CourtSupreme Court of Minnesota
DecidedAugust 15, 1952
Docket35,740
StatusPublished
Cited by25 cases

This text of 54 N.W.2d 805 (Wick v. Murphy) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wick v. Murphy, 54 N.W.2d 805, 237 Minn. 447, 1952 Minn. LEXIS 737 (Mich. 1952).

Opinion

Christianson, Justice.

Action to foreclose a mechanic’s lien for architectural services rendered to defendants by plaintiffs pursuant to contract. The trial court made findings and conclusions and ordered judgment for defendants. Plaintiffs appeal from an order denying their motion for a new trial.

Plaintiffs, W. T. Wick and L. H. Stansfield, both registered architects, are copartners doing business under the firm name of Wick & Stansfield at Mankato, Minnesota. Defendants, Cyril C. Murphy and Mary Helen Murphy, consulted plaintiffs in April 1949 with respect to remodeling their dwelling in Blue Earth, Minnesota. Preliminary conferences were held between the parties about the work to be done, and thereafter a contract dated May 4, 1949, was executed.

The contract in question appears to be a standard mimeographed form used by architects in making agreements with property owners for services. It did not specify the amount of the fee for the architectural services to be rendered nor estimate the amount the remodeling would cost. Following a recital of the purpose of the parties, the agreement sets forth the provisions material in the present case as follows:

“Ti-ie Architect agrees to perform for the above named work professional services in accordance with his 'Schedule of Professional Practice’ attached hereto, with the following exceptions: [none listed].
“Ti-ie Owner agrees to pay the Architect at the rate of Ten per cent (10%) hereinafter called the basic rate, computed and payable as stated in ‘Schedule of Professional Practice’, and to make any other payments and reimbursements arising out of said Schedule.”

*449 The “Schedule of Professional Practice,” after an enumeration of the professional services to be rendered by the architect, reads, insofar as here material, as follows:

“2. The Architect’s basic rate for such services, based upon the total cost of the work complete, is as mentioned in the agreement.
♦X- -X* * * *
“3. The Architect’s complete services are proportioned as follows:
“(a) 25% covers preliminary sketches and cost estimates.
“(b) 45% covers working drawings, details and printing.
“(c) 5% covers specifications.
“(d) 10 %_ covers approval of materials, selections of colors and fixtures and miscellaneous consultations; administration during construction.
“(e) 15% covers inspection and supervision of construction.
“4. Should the execution of any work designed or specified by the Architect or any part of such work be abandoned or suspended, the Architect is to be paid in the proportions of paragraph 3 (above) for the service rendered up to the time of such abandonment or suspension. Such payments will be due within 30 days after such abandonment or suspension.
“5. Payments to the Architect on his fee are made as follows:
“(a) Upon completion of the preliminary studies, a sum equal to twenty five per cent (25%) of the basic rate computed upon a reasonable estimated cost.
“(b) Upon completion of general working drawings and specifications, a sum sufficient to increase payments on the fee to sixty five per cent (65%) of the rate of commission as influenced by paragraphs 2a and 2b above, computed upon a reasonable estimated cost of the work on such completed specifications and drawings; or if bids have been received, then computed upon the lowest bona fide bid or bids. * * *
“(c) From time to time during the execution of work and in proportion to the amount of service rendered by the Architect, *450 payments made on account of the fee reach a sum. equal to the commission, computed upon the final cost of the work.
# * * * #
“8. When requested to do so, the Architect prepares or procures preliminary estimates on the cost of the work and he endeavors to keep the actual cost of the work as low as may he consistent with the purpose of the building and with proper workmanship and material, but no such estimate can be regarded as other than an approximation.
X- X* * # X*
“10. The words ‘cost of the work’ * * * are ordinarily to be interpreted as meaning the total of the contract sums incurred for the execution of the work, not including Architect’s and Engineer’s fees, but in certain cases — e.g., when labor or material is furnished by the Owner below its market cost or when old materials are re-used — the cost of the work is to be interpreted as the cost of all materials and labor necessary to complete work, as such would have been if all materials had been new and if all labor had been fully paid at market prices current when the work was ordered, plus contractor’s profits and expenses.”

In accordance with the contract, plaintiffs prepared certain plans and specifications, which were submitted to defendants and approved on July 22, 1949. Defendants never requested, and plaintiffs never gave them, any estimate of the cost of the work. Four contractors were asked to submit bids on the work, but only one bid was received. It was for $14,959.80 and did not include certain work to be done on a cost-plus percentage basis. No evidence was produced at the trial as to the reasonableness of this bid. After being advised of the bid on August 12, 1949, defendants abandoned their plans to remodel, at least for the time being, for the reasons that the remodeling could not be completed that summer and that the only bid received was much greater than the amount they had planned upon and was considerably in excess of the limitation of expense they had orally communicated to plaintiffs. Thereafter, plaintiffs submitted their bill for services rendered based upon a *451 percentage of the bid price, giving defendants credit for $250 which they previously had paid. Defendants refused to pay the bill, and this action was subsequently instituted.

Plaintiffs claim that they are entitled to receive from defendants under paragraph “4” of the contract, above quoted, 75 percent of the amount determined by applying to the amount of the bid received the 10 percent specified in the contract.

On the theory that the written contract was incomplete and that it did not constitute an integration of the agreement between the parties, the trial court admitted parol evidence of limitations defendants placed upon the cost of the improvement and the time in which it was to be completed. The trial court specifically found that the true agreement made by the parties was that the cost of the improvement should not exceed $8,500 and that the plans and specifications therefor were to be completed so that the contract could be let and the remodeling completed prior to the fall of 1949. The court further found that plaintiffs had wholly failed to perform the agreement between the parties. Therefore, it ordered judgment in defendants’ favor.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Todd Auge v. Fairchild Equipment, Inc.
982 F.3d 1162 (Eighth Circuit, 2020)
Staffing Specifix, Inc. v. Tempworks Mgmt. Servs., Inc.
913 N.W.2d 687 (Supreme Court of Minnesota, 2018)
Staffing Specifix, Inc. v. TempWorks Management Services, Inc.
896 N.W.2d 115 (Court of Appeals of Minnesota, 2017)
Cardiovascular Systems, Inc. v. Money
980 F. Supp. 2d 1102 (D. Minnesota, 2013)
Wilson v. AMERICAN RED CROSS, NORTHLAND CHAPTER
112 F. Supp. 2d 850 (D. Minnesota, 2000)
Untiedt v. Grand Laboratories, Inc.
552 N.W.2d 571 (Court of Appeals of Minnesota, 1996)
Katzner v. Kelleher Construction
545 N.W.2d 378 (Supreme Court of Minnesota, 1996)
Ecolab, Inc. v. Gartland
537 N.W.2d 291 (Court of Appeals of Minnesota, 1995)
Novus Equities Corp. v. Em-Ty Partnership
381 N.W.2d 426 (Supreme Court of Minnesota, 1986)
Grandnorthern, Inc. v. West Mall Partnership
359 N.W.2d 41 (Court of Appeals of Minnesota, 1984)
Malo v. Gilman
379 N.E.2d 554 (Indiana Court of Appeals, 1978)
ICC Leasing Corp. v. Midwestern MacHinery Co.
257 N.W.2d 551 (Supreme Court of Minnesota, 1977)
Salminen v. Frankson
245 N.W.2d 839 (Supreme Court of Minnesota, 1976)
Griswold & Rauma, Architects, Inc. v. Aesculapius Corp.
221 N.W.2d 556 (Supreme Court of Minnesota, 1974)
Paul W. Abbott, Inc. v. Axel Newman Heating & Plumbing Co.
166 N.W.2d 323 (Supreme Court of Minnesota, 1969)
Donnay v. Boulware
144 N.W.2d 711 (Supreme Court of Minnesota, 1966)
Ring v. Minnesota Road Builders, Inc.
116 N.W.2d 582 (Supreme Court of Minnesota, 1962)

Cite This Page — Counsel Stack

Bluebook (online)
54 N.W.2d 805, 237 Minn. 447, 1952 Minn. LEXIS 737, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wick-v-murphy-minn-1952.