Malo v. Gilman

379 N.E.2d 554, 177 Ind. App. 365, 1978 Ind. App. LEXIS 1001
CourtIndiana Court of Appeals
DecidedAugust 24, 1978
Docket3-876A199
StatusPublished
Cited by16 cases

This text of 379 N.E.2d 554 (Malo v. Gilman) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Malo v. Gilman, 379 N.E.2d 554, 177 Ind. App. 365, 1978 Ind. App. LEXIS 1001 (Ind. Ct. App. 1978).

Opinion

Staton, J.

Edward Malo, an architect, completed plans and specifications for Arnold Gilman, who sought to construct an office building. The construction bids received totaled $105,000, 50% more than the preliminary estimated cost of $70,000, which appeared in the contract between the men. Gilman was unable to secure financing and the building was never built. Malo brought an action to recover his fee as architect. Gilman counterclaimed for the $500 he had paid Malo. The trial court *366 found for defendant Gilman and granted his counterclaim. We affirm the judgment.

Malo agreed to provide architectural services to Gilman in the design and construction of an office building. Between May, 1967, and November, 1968, Malo expended considerable time and effort on the project. A verbal agreement was reached on July 28,1967. Gilman was assured that costs of construction could be kept below $20.00 per square foot. After talking to prospective tenants, Gilman decided he required 3,500 square feet in the building. A standard American Institute of Architects (A.I.A.) form contract was signed on May 14,1968. 1 Among the terms was the following:

“It is recognized that this written contract ratifies the similar verbal contract entered into July 28, 1967.
“The preliminary estimated cost of this project is Seventy Thousand Dollars, ($70,000.00).”

The contract also contained the following standard clause:

“3.4 Statements of Probable Construction Cost and Detailed Cost Estimates prepared by the Architect represent his best judgment as a design professional familiar with the construction industry. It is recognized, however, that neither the Architect nor the Owner has any control over the cost of labor, materials or equipment, over the contractors’ methods of determining bid prices, or over competitive bidding or market conditions. Accordingly, the Architect cannot and does not guarantee that bids will not vary from any Statement of Probable Construction Cost or other cost estimate prepared by him.”

Malo completed the plans and specifications for the project in September, 1968. In October, 1968, bids were solicited. The lowest total of bids received was approximately $128,000, which was negotiated down to $105,000. The bids were never accepted. Gilman indicated that the bids were unacceptable to him and that he was unable to secure financ *367 ing. In mid-December, Gilman sold the land on which the building was to have been erected.

Malo demanded payment of his fee for architectural services in the sum of $9,132.60. Gilman refused to pay. Malo brought an action to collect his fee. Gilman counterclaimed for the $500 he previously had paid Malo. The trial court denied Malo’s claim, but granted Gilman’s counterclaim.

We hold that the judgment of the trial court can be affirmed on either of two alternate theories: (1) that parol evidence was properly admitted to show a maximum cost limitation of approximately $70,000.00, which was exceeded unreasonably by Malo’s plans for construction; or (2) that the estimated cost figure appearing in the contract placed a reasonable limit on the actual cost of the project, which limit was exceeded unreasonably. 2 3 In either event, architect Malo breached' the contract and is not entitled to compensation under the contract.

I.

Parol Evidence to Show a Maximum Cost Limitation

On appeal, Malo argues that no fixed price, agreement appeared in the “fully integrated contract” for architectural services. The only figure appearing in the contract, $70,000.0.0,, was merely a preliminary estimated cost figure which was not binding, on the architect. 3 Further, *368 even if the trial court properly allowed evidence of a $20 per square foot cost limitation, Malo claims his final design plans contained 5,400 square feet, 4 50°/o more space than originally projected. In that case, the bids totaling $105,000 were in the right price range for a building costing $20 per square foot.

Gilman contends that evidence showing the existence of a $20 per square foot cost limitation (or $70,000 to $78,000 total for the project) was properly admitted, since the contract failed to contain a maximum cost limitation. Further, no significant changes in the project occurred to increase its size or cost.

Normally parol evidence may not be considered if it contradicts or supersedes matters intended to be covered by the written agreement. However, parol evidence may be admitted to supply an omission in the terms of the contract. 5 Caldwell v. United Presbyterian Church (Common Pleas 1961), 20 Ohio Ops. 2d 364, 88 Ohio L.Abs. 323, 180 N.E.2d 638; Spitz v. Brickhouse (1954), 3 Ill.App.2d 536, 123 N.E.2d 117. Many contracts for architectural services, as here, fail to include specific requirements such as the size, style, and character of the building, the number of rooms, the quality of the materials to be used, and, finally, the maximum cost. Yet, according to section 1.1.1 of the A.I.A. form contract,

“The Architect shall consult with the Owner to ascertain the requirements of the Project and shall confirm such requirements to the Owner.”

Thus, depending on the specific needs of the owner, these requirements may be integral parts of the contract for architectural services. Standley v. Egbert (1970), D.C.App., 267 A.2d 365, 367. A contract that fails to *369 set out the details agreed upon, then, is not a complete and integrated statement of the agreement. See Levy v. Leaseway System, Inc. (1959), 190 Pa.Super. 482, 154 A.2d 314. Parol evidence may be considered to determine the agreement with respect to these matters. See Annot., 69 A.L.R.3d 1353 (1976).

Ordinarily, the maximum cost of a project is agreed upon prior to commencement of design. The owner who plans to construct a building has in mind a figure for the maximum cost of construction, particularly where, as here, he must secure outside financing. The architect must design the project, keeping in mind this maximum cost limitation. Evidence of the maximum cost limitation should be admissible where the contract fails to show that figure. 6 As noted in an annotation to the Spitz case, 49 A.L.R.2d 679, 680 (1956):

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Shaun Perrill v. Brandy Perrill
126 N.E.3d 834 (Indiana Court of Appeals, 2019)
Digitech Computer, Inc. v. Trans-Care, Inc.
646 F.3d 413 (Seventh Circuit, 2011)
Hinkel v. Sataria Distribution & Packaging, Inc.
920 N.E.2d 766 (Indiana Court of Appeals, 2010)
Digitech Computer, Inc. v. Trans-Care, Inc.
583 F. Supp. 2d 984 (S.D. Indiana, 2008)
Wedmore v. Jordan Motors, Inc.
589 N.E.2d 1180 (Indiana Court of Appeals, 1992)
Strauss Veal Feeds, Inc. v. Mead & Hunt, Inc.
538 N.E.2d 299 (Indiana Court of Appeals, 1989)
Smithers v. Mettert
513 N.E.2d 660 (Indiana Court of Appeals, 1987)
In Re Greives
81 B.R. 912 (N.D. Indiana, 1987)
Franklin v. White
493 N.E.2d 161 (Indiana Supreme Court, 1986)
Sadler v. Sadler
428 N.E.2d 1305 (Indiana Court of Appeals, 1981)
Creech v. LaPorte Production Credit Ass'n
419 N.E.2d 1008 (Indiana Court of Appeals, 1981)
American National Bank & Trust Co. v. St. Joseph Valley Bank
389 N.E.2d 379 (Indiana Court of Appeals, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
379 N.E.2d 554, 177 Ind. App. 365, 1978 Ind. App. LEXIS 1001, Counsel Stack Legal Research, https://law.counselstack.com/opinion/malo-v-gilman-indctapp-1978.