Durand Associates, Inc. v. Guardian Investment Co.

183 N.W.2d 246, 186 Neb. 349, 1971 Neb. LEXIS 706
CourtNebraska Supreme Court
DecidedJanuary 29, 1971
Docket37598
StatusPublished
Cited by11 cases

This text of 183 N.W.2d 246 (Durand Associates, Inc. v. Guardian Investment Co.) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Durand Associates, Inc. v. Guardian Investment Co., 183 N.W.2d 246, 186 Neb. 349, 1971 Neb. LEXIS 706 (Neb. 1971).

Opinion

Spencer, J.

' This is a law action to recover fees for professional engineering services, pursuant to a contract for the erection of an apartment building which was never constructed because the construction bids, were substantially in excess of an alleged- estimate. Defendant Guardian Investment Company, hereinafter referred to as Guardian, cross-petitioned for? alleged -damages because of an inadequate' -‘estimate. At ■ the close' of the evidence, the trial court directed a verdict, for the defendants on plaintiff 's petition, ánd'for the plaintiff on the Guardian cross-petition.- Plaintiff perfected an ¡appeal and. defendant; .“Guardian, a cross-appeal'. - ' ' • ■"'

William H. Durand is • the president and sole'stockholder. of, the plaintiff corporation.. Durand is a licensed professional énginéer and in the practice‘of his profession designs buildings and other -structures. The-defend *351 ants, M. L. Strong and Theodore H. Lundt, are the sole stockholders of Guardian Investment Company, a corporation. Strong and Lundt, through another corporation, Elshire Investment Company, owned property at Forty-Second and Emile Streets in Omaha, Nebraska.

Sometime during the early part of 1962, Strong and Lundt visited with Durand about the construction of a medical clinic on their property For reasons not material here, the erection of a medical clinic was abandoned and the parties discussed the erection of an apartment building. Durand prepared preliminary plans for the apartment building. He was informed by the defendants that Guardian had no money and would have to borrow most of the cost of the building except for the cost of the site and certain costs which were to be borne by them. After preliminary plans and negotiations, Durand submitted a standard form of agreement between owner and architect to Strong and Lundt. Certain objections were made by them to the submitted contract, and Durand took it back to his office for revision. It was subsequently returned to them for signature by an associate of Durand. At this time, it had a construction cost estimate of $629,000 to which'the defendants objected. The undisputed evidence on this figure is the testimony of Strong,' as follows: “Well, I seen the 629,000, I said, "‘Well, Jack, this isn’t right, where did you get the 629,000?’- I.says-, ‘This building is to.be b.uilt for the $420,000 we had.previously discussed.’ So he gets on the phone and .calls. Mr; Durand, and he. tells me after, he says, ‘Well, Mr. Durand says go ahead and change it to 420,’ that his girl evidently took that'off of an estimate and put it in there. Q. Was it changed right then and there? A. It was'changed right there, and both of us initialed it.”

Before insertions, the contract, so far as material herein',’ read ¿s’ follows:“5’ PAYMENTS Payments to thee Architect on" account-.of his’fee-shall be made as follows, subject to the provisions of Article -4: * ■ • '

*352 “Upon completion of the preliminary studies, a sum equal to 25% of the basic rate computed upon a reasonable estimated cost. (Italics supplied.)

“During the period of preparation of specifications and general working drawings, monthly payments aggregating at the completion thereof, a sum sufficient to increase payments to 75% of the rate or rates of commission arising from this Agreement, computed upon a reasonable cost estimated on such completed specifications and drawings, or if bids have been received, then computed upon the lowest bona fide bid or bids.

“From time to time during the execution of work and in proportion to the amount of service rendered by the Architect, payments shall be made until the aggregate of all payments made on account of the Architect’s compensation under this Article, but not including any covered by the provisions of Article 4, shall be a sum equal to the rate or rates of commission arising from this Agreement, computed upon the final cost of the Project.

“Payments to the Architect, other than those on his compensation, fall due from time to time as his work is done or as costs are incurred.

“No deductions shall be made from the Architect’s compensation on account of penalty, liquidated damages, or other sums withheld from payments to contractors.”

The material insertion in the contract is as follows: “Payments to the architect will be made on a monthly basis, payments to be prorated equally over a twelve month period beginning with this contract date. Payments will be based on estimated construction costs until actual costs are determined at which time the amount of the payments will be revised accordingly. (Construction cost estimate $420,000.) WHD&Ass J.C.J. 1/7/62 MLS

“Painting and decorating; Ground and preparation; & All apartment furnishings excluded from project costs. WHD & Assoc J.C.J. 1/7/69 MLS.” Four payments *353 of $1,750 were made on the contract, obviously based upon the estimate of $420,000.

The big dispute in this action involves the interpretation of the contract. The proper construction of a written contract is a question of law to be determined by the courts. Bishop Cafeteria Co. v. Ford, 177 Neb. 600, 129 N. W. 2d 581. Plaintiff insists that the $420,000 figure was intended only as a figure for preliminary payment of fees to the architect. Defendants insist that the construction cost of the project was not to exceed $420,000, exclusive of painting and decorating, ground and preparation, and all apartment furnishings. The contract is the standard form used by the American Institute of Architects and was prepared by the plaintiff. Therefore, it must be strictly construed against the plaintiff and in favor of the defendants.

We agree with the construction of the contract by the trial court that the inserted paragraph is in conflict with article 5 and is controlling over it. Plaintiff’s argument on the meaning of the contract does not embrace the realities of such situations. We interpret the insertion in parentheses of the words “Construction cost estimate $420,000” to mean exactly what it says. The estimated cost of construction was $420,000, exclusive of the mentioned exclusions. It strains credulity to believe any businessman or private corporation would enter into a substantial building project without insisting on some estimate of cost. Plaintiff’s expert witness testified that a cost estimate is valuable information to give a client before entering into a contract, and that it would be very unusual for an architect not to discuss costs, for estimating costs are a part of the design of a project.

After plaintiff prepared the plans and specifications it took bids in conformity with the specifications. The low bids received totaled $724,535. While this figure may have embraced some of the exclusions, even then it is at least 72 percent above the construction estimate. These bids were submitted to Strong and Lundt, who *354 told Durand the cost was too high to permit them to proceed, and asked what could be done to lower it. Dur- and visited with some of the bidders, suggested the elimination of certain items, and came up with a modified bid of $652,728. This figure was still too high for the defendants and the project was abandoned.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Post, Buckley, Schuh & Jernigan, Inc. v. Monroe County
851 So. 2d 908 (District Court of Appeal of Florida, 2003)
Getzschman v. Miller Chemical Co., Inc.
443 N.W.2d 260 (Nebraska Supreme Court, 1989)
County of Polk v. Wombacher
426 N.W.2d 266 (Nebraska Supreme Court, 1988)
Williams Engineering, Inc. v. Goodyear
496 So. 2d 1012 (Supreme Court of Louisiana, 1986)
Overland Constructors, Inc. v. Millard School District
369 N.W.2d 69 (Nebraska Supreme Court, 1985)
Dockendorf v. Orner
293 N.W.2d 395 (Nebraska Supreme Court, 1980)
Swanson v. Baker Industries
615 F.2d 479 (Eighth Circuit, 1980)
Swanson v. Baker Industries, Inc.
615 F.2d 479 (Eighth Circuit, 1980)
Malo v. Gilman
379 N.E.2d 554 (Indiana Court of Appeals, 1978)
Palmer v. Dorn
243 N.W.2d 57 (Nebraska Supreme Court, 1976)
Kostohryz v. McGuire
212 N.W.2d 850 (Supreme Court of Minnesota, 1973)

Cite This Page — Counsel Stack

Bluebook (online)
183 N.W.2d 246, 186 Neb. 349, 1971 Neb. LEXIS 706, Counsel Stack Legal Research, https://law.counselstack.com/opinion/durand-associates-inc-v-guardian-investment-co-neb-1971.