Oxford Development Corp. v. Rausauer Builders, Inc.

304 N.E.2d 211, 158 Ind. App. 622, 1973 Ind. App. LEXIS 957
CourtIndiana Court of Appeals
DecidedDecember 3, 1973
Docket1-173A15
StatusPublished
Cited by10 cases

This text of 304 N.E.2d 211 (Oxford Development Corp. v. Rausauer Builders, Inc.) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Oxford Development Corp. v. Rausauer Builders, Inc., 304 N.E.2d 211, 158 Ind. App. 622, 1973 Ind. App. LEXIS 957 (Ind. Ct. App. 1973).

Opinion

Lybrook,

J.—Defendants-appellants Oxford Development Corporation, et al. (Oxford) appeal from the judgment of the trial court ordering foreclosure of mechanics’ liens in favor of plaintiff-appellee Rausauer Builders, Inc. (Rausauer) and defendant and cross-plaintiff-appellee Clyde Riddle & Sons (Riddle). The action stemmed from an alleged breach *624 of a Sub-Contract Agreement (contract) between Oxford and Rausauer.

The facts relevant to the issues on appeal are as follows:

On July 2, 1968, Oxford and Rausauer entered into a contract whereby Rausauer, as sub-contractor, agreed to furnish certain materials and perform certain work in the construction of an apartment project known as Beechwood Gardens in Indianapolis. Rausauer in turn hired Riddle to perform certain work.

Rausauer commenced work on the project in August of 1968. A dispute subsequently arose as to whether certain work performed was included within the contract or was an “extra” for which Rausauer was entitled to payment over and above the contract price. Oxford’s job superintendent, Hap Chandler, had directed Rausauer to complete the work in question. The work had in turn been performed by Riddle at Rausauer’s direction.

On October 13, 1969, Rausauer billed Oxford for the work as an “extra”. Following Oxford’s refusal to pay for the work in question, Rausauer ceased all work under the contract on October 30, 1969.

Rausauer and Riddle filed notices of intention to hold a lien upon Oxford’s premises, in the Office of the Recorder of Marion County. Rausauer subsequently filed its complaint for foreclosure of its lien, and Riddle then cross-claimed for foreclosure of its lien.

After hearing evidence on the issue of whether the disputed work was an “extra” or work encompassed within the contract, the court issued the following ruling:

“Court being duly advised now finds and adjudges that the underlaying done was extra work and not encompassed in the contract.”

Thereafter, the court heard evidence on Rausauer’s claim for additional sums for labor performed pursuant to the con *625 tract, on Riddle’s cross-claim for unpaid labor and foreclosure of its lien, and on Oxford’s counter-claim against Rausauer for damages resulting from an alleged breach of contract by Rausauer.

Judgment was entered in favor of Rausauer and Riddle against Oxford. The court found that there was due Rausauer from Oxford the sum of $17,268.71 plus $5400.00 attorney fees. It was also found that there was due Riddle from both Rausauer and Oxford the sum of $4801.00. Further due Riddle from Oxford was $1,087.00 plus $1,800.00 attorney fees.

The court adjudged that Rausauer and Riddle held liens against Oxford’s premises to the extent of their judgments and ordered the liens foreclosed.

Oxford appeals, raising the following issues for review:

1. Whether the court erred in finding that the work in dispute was an “extra” not encompassed in the contract.
2. Whether the court by its finding reformed the contract between Rausauer and Oxford, thereby committing error.
3. Whether the court erred in awarding Rausauer damages in excess of the sum due for performance of the disputed work.
4. Whether the award of attorney fees to Rausauer was excessive and not supported by the evidence.
5. Whether the assessment of attorney fees in favor of Riddle was erroneous as a matter of law.
6. Whether the assessment of damages against Oxford and in favor of Riddle was erroneous as a matter of law.

ISSUE 1.

The central controversy in this case is whether the installation of “underlayment” during the construction of the defendants’ apartment complex was an item of work included within the contract or an item of “extra” work for which Rausauer was entitled to payment over and above the contract price.

Oxford insists that the trial court erred as a matter of law *626 in construing the contract to exclude the installation of under-layment as an item of work to be performed thereunder.

In examining the court’s construction of the contract, we are mindful that our standard of review requires affirmance of a judgment if it can be sustained on any theory presented by the issues. Devine v. Grace Construction and Supply Co. (1962), 243 Ind. 98, 181 N.E.2d 862. Further, all reasonable presumptions are indulged in favor of the trial court, and this court will make no presumptions in favor of an appellant to sustain any alleged error. New York Central Ry. Co. v. Milhiser (1952), 231 Ind. 180, 106 N.E.2d 453.

The primary rule of construction is to ascertain and give effect to the parties’ intentions. To accomplish this end, the agreement should be construed as a whole. Ahlborn et al. v. City of Hammond (1953), 232 Ind. 12, 111 N.E.2d 70; Wiltse et al. v. Cornell (1970), 146 Ind. App. 447, 256 N.E.2d 572; Kuhn v. Kuhn et al. (1955), 125 Ind. App. 337, 123 N.E.2d 916.

Oxford argues that since the plans and specifications for the construction are expressly incorporated into the contract under paragraph FIRST of the sub-contract agreement and the plans and specifications provide for the installation of underlayment, the work is included within the contract as a matter of law.

Paragraph FIRST of the contract is as follows:

“FIRST. The Sub-contractor agrees to furnish all material and perform all work necessary to complete the carpentry and roofing of 51 buildings in Phases 1, 2, & 3 of apartment project known as Beechwood Gardens, 5725 East 30th St., Indianapolis, Indiana. Job Supt.—Hap Chandler
(Plans dated 12/28/67 and revised 2/22/68 and specks dated 2/22/68 inch addendum dated 1/5/68) for the above named structure, according to the plans and specifications (details thereof to be furnished as needed) of - - Architect, and to the full satisfaction of said Architect.”

*627 It is true that parties may, by express provision, make plans and specifications a part of their contract. Where this is done, those plans and specifications will control with the same force as though they were incorporated in the contract itself. Staley et al. v. New et al. (1952), 56 N.M. 756, 250 P. 2d 893; Warren et al. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

DeHaan v. DeHaan
572 N.E.2d 1315 (Indiana Court of Appeals, 1991)
Captain & Co., Inc. v. Stenberg
505 N.E.2d 88 (Indiana Court of Appeals, 1987)
Kennedy v. St. Joseph Memorial Hospital of Kokomo Indiana, Inc.
482 N.E.2d 268 (Indiana Court of Appeals, 1985)
Maxey v. Board of Zoning Appeals
480 N.E.2d 589 (Indiana Court of Appeals, 1985)
First National Bank of New Castle v. Acra
462 N.E.2d 1345 (Indiana Court of Appeals, 1984)
Malo v. Gilman
379 N.E.2d 554 (Indiana Court of Appeals, 1978)
Urbanational Developers, Inc. v. Shamrock Engineering, Inc.
372 N.E.2d 742 (Indiana Court of Appeals, 1978)
Evansville-Vanderburgh School Corp. v. Moll
344 N.E.2d 831 (Indiana Supreme Court, 1976)
City of Evansville v. Follis
315 N.E.2d 724 (Indiana Court of Appeals, 1974)

Cite This Page — Counsel Stack

Bluebook (online)
304 N.E.2d 211, 158 Ind. App. 622, 1973 Ind. App. LEXIS 957, Counsel Stack Legal Research, https://law.counselstack.com/opinion/oxford-development-corp-v-rausauer-builders-inc-indctapp-1973.