Levy v. Leaseway System, Inc.

154 A.2d 314, 190 Pa. Super. 482, 1959 Pa. Super. LEXIS 673
CourtSuperior Court of Pennsylvania
DecidedSeptember 16, 1959
DocketAppeal, 250
StatusPublished
Cited by7 cases

This text of 154 A.2d 314 (Levy v. Leaseway System, Inc.) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Levy v. Leaseway System, Inc., 154 A.2d 314, 190 Pa. Super. 482, 1959 Pa. Super. LEXIS 673 (Pa. Ct. App. 1959).

Opinion

Opinion by

Watkins, J.,

This appeal arose out of a complaint in assumpsit brought by a registered professional engineer, Jacob H. Levy, trading as Towne Engineering Company, the appellant, against Leaseway System Incorporated, the appellee, for compensation based on an alleged written agreement to prepare plans and specifications for a shop and office building at 31st Street and Glenwood Ave., Philadelphia, Pennsylvania. A copy of a letter prepared by the appellant and accepted by the appellee, which is the alleged contract upon which the suit is based reads as follows:

*484 “Subject: Shop and Office Bldg.,
31st St. and Glenwood Ave.
November 10, 1956.
“In confirmation of our verbal agreement of Nov. 7, 1956 we will prepare plans and specifications for the new Shop and Office Building to be erected at 31st St. and Glenwood Ave., Phila., Pa. for a basic fee of seven percent (7%) of the net final cost of construction of this project, our services for this basic fee will include: the preparation of preliminary plans for your approval; the preparation of detailed working drawings and specifications after approval of preliminary plans, required for the construction; furnishing 5 copies of such plans and specifications for your use; assisting in the negotiating and awarding of a general contract for the total work; and general supervision of the project during construction by periodic visits to the site as often as necessary, reporting on the progress and guarding against defects and deficiencies in the work of the Contractor but without a guarantee as to the performance of the contract by the Contractor; and the checking and approval of the Contractors requisition for payments.
“The basic fee is to be based upon the net final cost of construction, which net cost includes the cost of the entire work including labor, materials and use of equipment but not including cost of land or the engineering fee. This fee is compensation for our services and 70% of the total fee is to be paid upon completion of the contract plans and specifications, the balance of the fee to be paid in monthly payments until the aggregate of all payments equals the total amount due or 7% of the total cost of the construction of the project. Should the execution of the work planned and designed, or any part, be abandoned or suspended the engineer is to be paid in proportion an amount of the basic fee for the *485 services rendered up to the time of abandonment or suspension.
“The return of one signed copy, as noted below, will be a confirmation of your verbal authorization to proceed with our engineering services as noted above, and preliminary plans will be prepared as soon as possible for your consideration.”

The complaint avers that the plans and specifications were prepared in accordance with information furnished by the appellee; that they were completed and delivered to the appellee; that they were submitted for bids and that the lowest bid received was $59,555 so that the sum claimed to be due was $2,918.20.

The appellee denies that the letter of November 10, 1956 incorporated the entire agreement, but averred that the plans were never accepted by the appellee; that it was orally agreed between the parties that the total cost of the construction would not exceed $30,000 ; that the letter of November 10, 1956 was not the complete contract but merely set forth the fee schedule; that the appellee was unable to ascertain if the appellant had complied with the contract requirements until it received bids ranging from $87,585 to $59,555; that the appellee then rejected the plans and requested the appellant to comply with the agreement and prepare plans for a $30,000 building; that on February 16, 1957 the appellant submitted new plans of construction, estimated to cost $41,000 which the appellee also rejected. A copy of the letter of February 16, 1957 submitting the new plans reads as follows:

“In connection with our discussion yesterday, we are enclosing a print showing proposed revision to the plans furnished you on January 14. Basically the plan is the same, however the total area of building is smaller, the net size of the shop being 30 x 56, thus permitting a change in design of framing which re *486 duced the cost. We estimate the cost of the building construction to be approximately $36,000 and the cost of the outside work consisting of yard paving, chain link fence and driveways to be $5,000. These estimated figures are based upon materials equal or similar to those originally specified. The plumbing, heating and electrical work are basically the same as before, except reduced to conform with the reduced overall building area. The estimated costs might be somewhat reduced by the use of inferior materials or omission of needed facilities, but the increased cost of maintenance and operation will be far greater than any apparent reduction in first cost.
“In our discussion you mentioned a length of shop to be at least 60 feet, and although this length was never contemplated having started first with 30 ft. and then increasing to 54 ft. we investigated the possibility. The pencil line on the print indicates the extreme end of the building and of course reduces the turning area between building and fence line. The increase in cost would be negligible in this case as the increase in floor area by this small amount will not affect the major items of cost, which merely proves our point that cost area ratios are misleading.
“As suggested by the writer yesterday, have one of the original bidders work up a price based on this preliminary revision, as a check on our estimate of construction cost.”

This case was originally brought in the Court of Common Pleas, when, at the conclusion of the pleadings, the plaintiff’s motion for judgment on the pleadings was denied, and the case transferred to the Municipal Court. The court below at the trial refused to receive any evidence as to construction cost limitation on the ground that such evidence was outside the letter of November 10, 1956, which embodied the whole *487 contract, and was inadmissible under the parol evidence rule. Both sides rested and the court below directed a verdict in favor of the appellant.

The appellee filed motions for a new trial and judgment n.o.v. The Court en banc, after argument, dismissed the judgment n.o.v. but with the trial judge concurring, granted the motion for a new trial. Hence this appeal..

“The parol evidence rule . . . provides that where parties to an agreement commit their undertakings to a. writing with the intention that it shall formally and comprehensively evidence the terms of their agreement, the writing, when executed by the parties, cannot thereafter be made subject to parol alteration, contradiction, or variance by way of agreements or understandings had prior to or contemporaneously with the execution of the writing.” International Co. v. Hachmeister, Inc., 380 Pa. 407, 110 A. 2d 186 (1955).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Steinke v. Sungard Financial
First Circuit, 1997
Steinke v. Sungard Financial Systems, Inc.
121 F.3d 763 (First Circuit, 1997)
Daily Industries, Inc. v. Transport Trailer Service, Inc.
15 Pa. D. & C.3d 499 (Dauphin County Court of Common Pleas, 1979)
Malo v. Gilman
379 N.E.2d 554 (Indiana Court of Appeals, 1978)
Commonwealth v. BERGER
312 A.2d 100 (Commonwealth Court of Pennsylvania, 1973)
Gearhart Unemployment Compensation Case
168 A.2d 646 (Superior Court of Pennsylvania, 1961)
Keller & Voelker, Inc. v. Kellett Aircraft Corp.
159 A.2d 561 (Superior Court of Pennsylvania, 1960)

Cite This Page — Counsel Stack

Bluebook (online)
154 A.2d 314, 190 Pa. Super. 482, 1959 Pa. Super. LEXIS 673, Counsel Stack Legal Research, https://law.counselstack.com/opinion/levy-v-leaseway-system-inc-pasuperct-1959.