Allied Seed, LLC v. Norfarm Seeds, Inc.

CourtDistrict Court, D. Minnesota
DecidedMarch 24, 2021
Docket0:20-cv-01520
StatusUnknown

This text of Allied Seed, LLC v. Norfarm Seeds, Inc. (Allied Seed, LLC v. Norfarm Seeds, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Allied Seed, LLC v. Norfarm Seeds, Inc., (mnd 2021).

Opinion

UNITED STATES DISTRICT COURT DISTRICT OF MINNESOTA

Allied Seed, LLC, Case No. 20-cv-1520 (WMW/LIB)

Plaintiff, ORDER GRANTING DEFENDANT’S v. MOTION TO COMPEL ARBITRATION AND TO DISMISS Norfarm Seeds, Inc.,

Defendant.

This matter is before the Court on the Defendant’s motion to compel arbitration and to dismiss this case. (Dkt. 13.) For the reasons addressed below, the Defendant’s motion is granted. BACKGROUND This case arises out of a contract dispute relating to agricultural seed production. Plaintiff Allied Seed, LLC (Allied), is a Wyoming limited liability company with its principal place of business in Nampa, Idaho. Defendant Norfarm Seeds, Inc. (Norfarm), is a Minnesota corporation. Both companies work in the grass seed industry. In December 2014, Allied entered into a seed-production contract with Norfarm (Contract). Under the Contract, Norfarm agreed to produce seed that Allied would subsequently purchase for resale. The duration of the Contract was “3 Years with [an] option to extend.” To extend the Contract, Allied was required to notify Norfarm before the 2018 harvest (2018 Harvest Clause). The “Quantity” of seed to be produced under the Contract was “[t]he total production from 300 acres seeded Summer 2015” (Seeded Summer 2015 Clause). The Contract also incorporates the “NORAMSEED A.S.T.A.” (American Seed Trade Association) arbitration rules.1 Section XXV of these rules provides that: [A]ny difference between the parties, even if the difference is only recognized by one party, resulting from transactions started or concluded on the basis of the present Rules, and which cannot be settled amicably, shall be settled by binding arbitration in accordance with these Rules and the applicable procedural rules of the American Arbitration Association (AAA), . . . . (Emphasis added.) The dispute at issue here arises out of a January 25, 2019 purchase confirmation (2019 Purchase Confirmation), in which the parties executed an agreement for Allied to purchase seed from Norfarm’s 2018 harvest. Allied contends that this seed was of lesser quality than Norfarm was contractually obligated to provide. Allied commenced this lawsuit against Norfarm in July 2020, alleging breach of express warranty (Count I), breach of implied warranty of merchantability (Count II), breach of implied warranty of fitness for a particular purpose (Count III), intentional misrepresentation (Count IV), violation of Idaho’s Consumer Protection Act (Count V), violation of Minnesota’s Uniform Deceptive Trade Practices Act (Count VI, mislabeled Count VII), and violation of the Idaho Pure Seed Law (Count VII, mislabeled Count VIII). Norfarm moves to compel arbitration and to dismiss the complaint.

1 NORAMSEED refers to the North American Seed Rules, which are trade rules established by the seed industry. ANALYSIS I. Motion to Compel Arbitration Norfarm seeks to compel arbitration, arguing that the parties agreed to arbitrate any disputes arising under the Contract. Allied contends that the 2019 Purchase Confirmation is a new contract. As such, the terms of the Contract, including the

Contract’s arbitration terms, do not apply to this dispute. The Federal Arbitration Act (FAA), 9 U.S.C. §§ 1 et seq., requires the enforcement of written agreements to arbitrate disputes and reflects a “liberal federal policy favoring arbitration agreements.” Moses H. Cone Mem’l Hosp. v. Mercury Constr. Corp., 460 U.S. 1, 24 (1983). “[C]ontract provisions directing arbitration shall be

enforceable in all but limited circumstances.” Kelly v. Golden, 352 F.3d 344, 349 (8th Cir. 2003). A motion to compel arbitration must be granted if there is a valid arbitration agreement between the parties and the dispute falls within the scope of the arbitration agreement. 3M Co. v. Amtex Sec., Inc., 542 F.3d 1193, 1198 (8th Cir. 2008) (citing 9 U.S.C. § 4). Although state contract law governs whether an enforceable agreement

exists, federal law governs whether the dispute is within the scope of the parties’ arbitration agreement. Donaldson Co. v. Burroughs Diesel, Inc., 581 F.3d 726, 731 (8th Cir. 2009). A motion to compel arbitration is analyzed either as a motion to dismiss under Rule 12(b)(6), Fed. R. Civ. P., or as a motion for summary judgment under Rule 56, Fed. R. Civ. P., depending on whether “matters outside the pleadings” have been presented and considered. City of Benkelman v. Baseline Eng’g Corp., 867 F.3d 875, 881–82 (8th Cir. 2017); accord Seldin v. Seldin, 879 F.3d 269, 272 (8th Cir. 2018). A. Existence of an Arbitration Agreement State contract law governs whether the parties have entered into a valid agreement to arbitrate a particular matter. Keymer v. Mgmt. Recruiters Int’l, Inc., 169 F.3d 501, 504

(8th Cir. 1999). Here, as in any case arising under diversity jurisdiction, the choice-of- law rules for the state in which this Court sits apply. DCS Sanitation Mgmt., Inc. v. Castillo, 435 F.3d 892, 895 (8th Cir. 2006). Neither party disputes that Minnesota law applies.2 Under Minnesota law, contract formation requires the communication of a specific

and definite offer, acceptance of that offer, and consideration. See Pine River State Bank v. Mettille, 333 N.W.2d 622, 626–27 (Minn. 1983). Courts evaluate the objective conduct of the parties when determining whether the parties have entered into a valid and enforceable contract. Cederstrand v. Lutheran Brotherhood, 117 N.W.2d 213, 221 (Minn. 1962). A valid and enforceable contract does not exist when an essential term

remains uncertain. Triple B & G, Inc. v. City of Fairmont, 494 N.W.2d 49, 53 (Minn. Ct. App. 1992). Here, the parties dispute whether the duration of the Contract extends to actions taken pursuant to the 2019 Purchase Confirmation.

2 Allied argues that either Minnesota law or Idaho law could be applied because there is “no conflict” between Minnesota law and Idaho law as to any of the issues presented by this case and both states have “substantial relationships” to the disputed transaction. Norfarm does not appear to dispute the application of either Minnesota or Idaho law. Whether Idaho law applies need not be resolved for purposes of this instant dispute, however. Allied argues that the parties lack a contractual agreement to arbitrate this dispute because the Contract “expired and did not cover the transaction at issue.” According to Allied, the Contract ended “by its terms in December 2017.”3 Allied’s position implies that the three-year term began on the date the Contract was signed. By contrast, Norfarm argues that the “3 Years” referenced in the Contract refers to three crop years following

the 2015 establishment year.4 Consequently, according to Norfarm, the Contract covered the 2016, 2017, and 2018 crop years.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Green Tree Financial Corp.-Alabama v. Randolph
531 U.S. 79 (Supreme Court, 2000)
Green v. Supershuttle International, Inc.
653 F.3d 766 (Eighth Circuit, 2011)
Patrick D. Kelly v. Marc Golden
352 F.3d 344 (Eighth Circuit, 2004)
Travertine Corp. v. Lexington-Silverwood
683 N.W.2d 267 (Supreme Court of Minnesota, 2004)
Brookfield Trade Center, Inc. v. County of Ramsey
584 N.W.2d 390 (Supreme Court of Minnesota, 1998)
Donaldson Co., Inc. v. Burroughs Diesel, Inc.
581 F.3d 726 (Eighth Circuit, 2009)
3M Co. v. Amtex Security, Inc.
542 F.3d 1193 (Eighth Circuit, 2008)
Cederstrand v. Lutheran Brotherhood
117 N.W.2d 213 (Supreme Court of Minnesota, 1962)
Pine River State Bank v. Mettille
333 N.W.2d 622 (Supreme Court of Minnesota, 1983)
Wick v. Murphy
54 N.W.2d 805 (Supreme Court of Minnesota, 1952)
Chergosky v. Crosstown Bell, Inc.
463 N.W.2d 522 (Supreme Court of Minnesota, 1990)
TRIPLE B & G, INC. v. City of Fairmont
494 N.W.2d 49 (Court of Appeals of Minnesota, 1992)
Denelsbeck v. Wells Fargo & Co.
666 N.W.2d 339 (Supreme Court of Minnesota, 2003)
Unison Co., Ltd. v. Juhl Energy Development, Inc.
789 F.3d 816 (Eighth Circuit, 2015)
Storms, Inc. v. Mathy Construction Co.
883 N.W.2d 772 (Supreme Court of Minnesota, 2016)
Zetor North America, Inc. v. Ridgeway Enterprises
861 F.3d 807 (Eighth Circuit, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
Allied Seed, LLC v. Norfarm Seeds, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/allied-seed-llc-v-norfarm-seeds-inc-mnd-2021.