Western Concrete Structures Co. v. James I. Barnes Construction Co.

206 Cal. App. 2d 1, 23 Cal. Rptr. 506, 1962 Cal. App. LEXIS 1989
CourtCalifornia Court of Appeal
DecidedJuly 24, 1962
DocketCiv. 19981
StatusPublished
Cited by15 cases

This text of 206 Cal. App. 2d 1 (Western Concrete Structures Co. v. James I. Barnes Construction Co.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Western Concrete Structures Co. v. James I. Barnes Construction Co., 206 Cal. App. 2d 1, 23 Cal. Rptr. 506, 1962 Cal. App. LEXIS 1989 (Cal. Ct. App. 1962).

Opinion

AGEE, J.

The judgment herein awarded plaintiff, Western Concrete Structures Co., Inc., $18,373.70 as against defendant James I. Barnes Construction Co., and awarded defendant Seaboard Surety Co. $1,500 (attorney fees) as against Western. Each party appeals from the respective portions of the judgment which it deems to be unfavorable. The trial court made extensive findings of fact and each of these findings is supported by substantial evidence.

Much effort on this appeal is devoted to contentions that the trial court failed to make findings on many subordinate issues raised at the trial and on many factual allegations set forth in the pleadings. Many of the findings sought by defendants would necessarily be adverse to them and others are rendered superfluous by the findings made. Moreover, since it does not appear from the record that defendants requested any specific findings on any of the issues involved, we are not precluded by section 634 of the Code of Civil Procedure from inferring findings by necessary implication from those made, were it necessary. In our opinion, the findings made herein are adequate and are determinative of the case. Any failure to make more specific findings is immaterial. (See Daniel Orifice Fitting Co. v. Whalen, 198 Cal.App.2d 791, 801 [18 Cal.Rptr. 659]; Santos v. Wing, 197 Cal.App.2d 678, 683 [17 Cal.Rptr. 457] ; Williams v. Elliott, 127 Cal.App.2d 357, 361 [273 P.2d 953].)

Barnes had the general contract let by the Division of Architecture, Department of Public Works of the State of California, for the construction of ward buildings at the Sonoma State Hospital. Barnes later obtained the general contract for the construction of an administration building at the hospital. Seaboard was the surety on Barnes’ bond. Western is a specialist in construction work involving the prestressing and lifting of prestressed concrete slabs. In this type of operation, the concrete slabs which form the roof and floors of a building being constructed are poured at the ground level, prestressed, and then lifted into position by means of multiple electronically controlled hydraulic jacks attached to steel vertical lifting columns.

On September 5, 1956, Western and Barnes executed a subcontract under which Western was to prestress, lift and fix in place the concrete slabs to be used in the construction of *5 the ward buildings. (Western contends that it also became the subcontractor for the same type of work on the administration building but the trial court found to the contrary and did not allow Western any recovery thereon.)

Barnes was responsible for the scheduling of the commencement of Western’s operations. After several attempts at scheduling and rescheduling Western’s work, and pursuant to written communications between the parties, Western’s crew and equipment arrived from southern California at the jobsite on June 10, 1957, and completed the placing of its equipment in position on that day. The court found that Western was ready to begin the actual lifting operations on June 11th. However, because of work which Barnes was still doing on the slabs, they were not in a condition to be lifted, and Western’s crew and equipment were thereby caused to stand idle until June 17th. The trial court further found that Western had sustained a loss of $6,000 by reason of this enforced idleness and awarded such amount as damages. (Gollaher v. Midwood Constr. Co., 194 CaI.App.2d 640, 649 [15 Cal.Rptr. 292].) The ground upon which this recovery was allowed is that Barnes by its conduct had induced Western reasonably to rely to its detriment upon June 10th as its starting date.

When Western commenced its lifting operations on June 17th, some of the columns erected by Barnes, and upon which the slabs were to be lifted, were discovered to be defective. Defects were also found which involved the circular metal “collars” which were embedded in the slabs around the lifting columns and to which the hydraulic lifting jacks were to be attached. These defects were caused by Barnes and had to be corrected by Western. The trial court assessed Western’s damages in this respect at $2,400.

Barnes was entitled to retain 10 per cent of the progress payments to be made to Western under the subcontract until 30 days after Barnes had received its final payment on the general contract from the state. This payment was received on September 30, 1958. The judgment therefore includes the amount so retained by Barnes, $8,704.30, plus interest thereon from October 30, 1958, amounting to $1,269.40.

Western contends that interest on the retention payment should commence 30 days after July 1,1957, when it completed its work under the subcontract. We do not agree. The subcontract provides that such payment “shall be made within thirty days after completion of the work included in this con *6 tract and written acceptance by the Architect and full payment therefor by the Owner ...” (emphasis ours). The first of these conditions occurred when Western completed its work under the subcontract. The second condition did not occur until September 16, 1958, when the Department of Architecture accepted the project. The third condition occurred on September 30, 1958, when the state made the final payment called for under the general contract. The trial court found no ambiguity in the provision relating to when Western was entitled to receive the retention payment and neither do we.

Barnes and Seaboard both urge the defense of accord and satisfaction as to Western’s claims for $6,000 and $2,400. By invoice 52(23-3), dated June 21, 1957, Western billed Barnes for the final progress payment. The amount was adjusted to $28,636.20, in accordance with a deduction of $590 previously agreed upon by Barnes and Western in an exchange of letters dated February 8, 1957, and February 11, 1957, respectively. The invoice acknowledged previous payments of $21,226.05 and $28,476.45. The total amount of the contract, as adjusted, was $87,043. The payment of $28,636.20 under invoice 52 (23-3) was due July 15, 1957, and would leave the balance of $8,704.30 to be retained by Barnes, as provided in the contract.

By invoice 53(23-4), also dated June 21, 1957, Western billed Barnes for the charges of $6,000 and $2,400, discussed above.

On July 26th, Barnes remitted to Western a check in the amount of $28,636.20 by a letter of transmittal which stated: “Enclosed herewith find remittance in the amount of $28,636.20 for payment in full for services to date. We are also returning Invoice 53(23-4), which by previous correspondence we have advised you is an entirely unwarranted and unauthorized charge. ’ ’ There was no dispute as to either the fact of the obligation as stated in invoice 52(23-3) or the adjusted amount which Barnes was obliged to pay thereunder. Barnes ’ own witness so testified. However, typed across the face of the check was the notation: “Acceptance of this check acknowledges payment in full of all moneys due to date and specifically cancels Invoice 53(23-4) dated June 21, 1957.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Aliu v. Long Beach Unified School Dist. CA2/5
California Court of Appeal, 2014
deSaulles v. Community Hospital of Monterey
California Court of Appeal, 2014
Michell v. Olick
49 Cal. App. 4th 1194 (California Court of Appeal, 1996)
LITON GEN. ENG'G CON., INC. v. United Pac. Ins.
16 Cal. App. 4th 577 (California Court of Appeal, 1993)
Liton General Engineering Contractor, Inc. v. United Pacific Insurance
16 Cal. App. 4th 577 (California Court of Appeal, 1993)
Chavez v. Zapata Ocean Resources, Inc.
155 Cal. App. 3d 115 (California Court of Appeal, 1984)
Beach v. Western Medical Enterprises, Inc.
116 Cal. App. 3d 153 (California Court of Appeal, 1981)
Mitchell v. Siqueiros
582 P.2d 1074 (Idaho Supreme Court, 1978)
Acoustics, Inc. v. Trepte Construction Co.
14 Cal. App. 3d 887 (California Court of Appeal, 1971)
Southern California Acoustics Co. v. C. V. Holder, Inc.
456 P.2d 975 (California Supreme Court, 1969)
Pagán Fortis v. Garriga
88 P.R. 270 (Supreme Court of Puerto Rico, 1963)

Cite This Page — Counsel Stack

Bluebook (online)
206 Cal. App. 2d 1, 23 Cal. Rptr. 506, 1962 Cal. App. LEXIS 1989, Counsel Stack Legal Research, https://law.counselstack.com/opinion/western-concrete-structures-co-v-james-i-barnes-construction-co-calctapp-1962.