Sierra & San Francisco Power Co. v. Universal Electric & Gas Co.

241 P. 76, 197 Cal. 376, 1925 Cal. LEXIS 247
CourtCalifornia Supreme Court
DecidedOctober 31, 1925
DocketDocket No. S.F. 11025.
StatusPublished
Cited by21 cases

This text of 241 P. 76 (Sierra & San Francisco Power Co. v. Universal Electric & Gas Co.) is published on Counsel Stack Legal Research, covering California Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sierra & San Francisco Power Co. v. Universal Electric & Gas Co., 241 P. 76, 197 Cal. 376, 1925 Cal. LEXIS 247 (Cal. 1925).

Opinion

SHENK, J.

This is an appeal from a judgment in favor of the plaintiff for the sum of $13,359.68 on account of an alleged balance due for electrical energy furnished by the plaintiff to the defendant.

It is alleged in the complaint that on the ninth day of July, 1915, the parties hereto entered into a contract whereby the plaintiff agreed to sell and the defendant agreed to buy for a period of eight years all of the electrical energy that might be required by the defendant in the regular course of its business in excess of that which might be generated in its own plant; that the defendant agreed to pay for energy at the rate per month of $1.80 per kilowatt for the first 2,000 kilowatts maximum demand, with a sliding schedule downward for each successive 2,000 kilowatts maximum demand; that in addition thereto an energy charge was to be paid of four mills per kilowatt hour for energy taken as determined by the integrating watt hour meter readings; that pursuant to the contract the plaintiff sold and delivered energy to the defendant from August 1, 1918, to December 3, 1919, on account of which the total price to be paid was $255,-623.55; that the defendant had paid the sum of $241,249.71 and no more. Plaintiff prayed judgment for the difference, to wit, $14,373.84 and interest. The defendant answered denying the indebtedness, alleging a modification of said contract by mutual consent in January, 1917, the payment of bills by monthly remittances in accordance with the modified contract and the acceptance by the plaintiff of such payments in full satisfaction. The court found for the plaintiff and entered judgment for the amount demanded less the sum of $1,016.16, which the plaintiff admitted to be due to the defendant in accordance with the allegations of a counterclaim duly pleaded.

*379 The defendant contends that the evidence is insufficient to support the findings, that the judgment is not supported by the findings, and that the decision is against law.

It appears from the evidence that at all times involved in this action the plaintiff and the defendant were public utility corporations, the plaintiff being a wholesaler and the defendant a retailer of electrical energy in San Francisco; that the rates specified in the contract of July 9, 1915, provided first for an energy charge at a fixed rate per kilowatt hour for energy actually used, and, secondly, a service charge at a specified rate per kilowatt hour based upon the maximum demand during the month, the maximum demand being defined as “the sum of the greatest number of kilowatt hours taken by purchaser . . . during any four consecutive fifteen minute intervals during each month”; that the contracting parties operated under this contract until January, 1917, when the plaintiff endeavored to persuade the defendant to shut down its steam plant and take all of its power from the plaintiff. Defendant objected to the proposal on the ground that it was not assured of the reliability of the plaintiff’s service and that by operating its own steam plant it was enabled to reduce the peak load, thus lowering the maximum demand during the month and correspondingly decreasing the amount of service charge which it was required to pay. After negotiations, however, an oral agreement was entered into whereby the defendant was to shut down its steam plant, the plaintiff to operate its steam plant seven days a week and the maximum demand on which the service charge was based was to be figured at nine-tenths of the actual amount thereof. Thereafter letters were exchanged purporting to confirm the oral agreement. Under date of January 2, 1917, the plaintiff addressed a letter to the defendant as follows: “In consideration of the Universal Electric & G-as Company giving the Sierra & San Francisco Power Company additional load between the hours of 7:15 a. • m. and 11:00 p. m. to the full capacity of the present cable . . . this company will operate its steam plant between the hours of 7:15 a. m. and 11:00 p. m. and will also assume nine-tenths of the maximum demand being charged as the Tnaxirmirri demand charge, according to the contract. The minimum service charge under this arrangement is to be based upon 1500 kilowatts. Should your maximum demand *380 be less than 1500 kilowatts, then and in that event, the nine-tenths factor shall not apply. . . . Ton stated to the writer that you would operate this month, January, 1917, under the terms above named, in order to determine whether or not this would be satisfactory operative conditions.” On January 10, 1917, the defendant replied: “Confirming our recent conversation and your letter of January 2nd, 1917, we understand that should our peak load equal 1500 kilowatts or more we are to be billed for nine-tenths of whatever that peak may be, or at the old rate of $1.62 per k. w. Should the peak be less than 1500 k. w. then and in that event the rate to remain at $1.80 per k. w. Also, we understand that your steam plant is to run Sundays as on week' days. Trusting this will make a clear record of our understanding and thanking you for your courtesy in the matter, we remain,” etc. On January 15, 1917, the plaintiff in turn replied: “Referring to your letter of January 10th, I beg to advise you that your understanding does not agree with ours as to the application of the 9/10 factor. While the resulting bill would be the same in either event (viz.: by applying the 9/10 factor to the rate, according to your understanding, or applying the 9/10 factor to the peak, according to our understanding) it was our understanding that the peak and not the rate should be the method.”

It will be noted from the foregoing correspondence that, while there was some disagreement as to the application of the nine-tenths factor the result was the same as far as the revenues of the plaintiff and payments by the defendant were concerned, for in billing the defendant for energy furnished for the month of January, 1917, to and including the month of July, 1918, the plaintiff applied the nine-tenths factor in ascertaining the maximum demand charge and the bills were paid by the defendant as submitted. On July 31, 1918, the plaintiff gave to the defendant a written notice of termination of the special arrangement as follows: “Owing to the greatly increased cost of labor and materials and to more difficult operating conditions which have very largely increased the cost of production, we feel that the special concession covered by our letter of January. 15th, 1917, by Mr. W. L. McKinley, should not be longer continued. We will therefore cancel the arrangement covered by the *381 aforesaid letter and proceed on the contract basis beginning August 1st, 1918.”

After the notice of termination was given and continuously thereafter during the entire period covered by this controversy all bills rendered by the plaintiff were based on the full maximum demand charge in accordance with the original contract. Payments thereon were made by the defendant as hereinafter more particularly noted. On June 15, 1921, the plaintiff made formal demand for the payment of the difference between the amounts claimed to be due computed according to the original contract and the amounts paid computed on the basis of the reduced rate. Upon the refusal of the defendant to pay this action was brought.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Western Concrete Structures Co. v. James I. Barnes Construction Co.
206 Cal. App. 2d 1 (California Court of Appeal, 1962)
Reid v. Overland Machined Products
359 P.2d 251 (California Supreme Court, 1961)
Avery v. Schuman Co.
159 F. Supp. 906 (S.D. California, 1958)
Potter v. Pacific Coast Lumber Co.
234 P.2d 16 (California Supreme Court, 1951)
Goad v. Rogers
229 P.2d 791 (California Court of Appeal, 1951)
Pacific Magnesium, Inc. v. Westover
86 F. Supp. 644 (S.D. California, 1949)
D. E. Sanford Co. v. Cory Glass Coffee Brewer Co.
194 P.2d 127 (California Court of Appeal, 1948)
Gibbons v. Brewster
186 P.2d 459 (California Court of Appeal, 1947)
Ayoob v. Ayoob
168 P.2d 462 (California Court of Appeal, 1946)
Moore v. Bartholomae Corp.
159 P.2d 436 (California Court of Appeal, 1945)
Wallace v. Crawford
69 P.2d 455 (California Court of Appeal, 1937)
Ferryboatmen's Union v. Northwestern Pac. R.
84 F.2d 773 (Ninth Circuit, 1936)
Kirschbaum v. McCarthy
54 P.2d 8 (California Supreme Court, 1936)
Whepley Oil Co. v. Associated Oil Co.
44 P.2d 670 (California Court of Appeal, 1935)
Hansen v. Fresno Jersey Farm Dairy Co.
31 P.2d 359 (California Supreme Court, 1934)
Waterford Irr. Dist. v. Modesto Irr. Dist.
16 P.2d 275 (California Court of Appeal, 1932)
Waterford Irrigation District v. Modesto Irrigation District
127 Cal. App. 544 (California Court of Appeal, 1932)
Shortell v. Evans-Ferguson Corp.
277 P. 519 (California Court of Appeal, 1929)
Pacific Gas & Electric Co. v. Universal Electric & Gas Co.
271 P. 377 (California Court of Appeal, 1928)

Cite This Page — Counsel Stack

Bluebook (online)
241 P. 76, 197 Cal. 376, 1925 Cal. LEXIS 247, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sierra-san-francisco-power-co-v-universal-electric-gas-co-cal-1925.