MacIsaac & Menke Co. v. Cardox Corp.

193 Cal. App. 2d 661, 14 Cal. Rptr. 523, 1961 Cal. App. LEXIS 1756
CourtCalifornia Court of Appeal
DecidedJuly 12, 1961
DocketCiv. 24645
StatusPublished
Cited by19 cases

This text of 193 Cal. App. 2d 661 (MacIsaac & Menke Co. v. Cardox Corp.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
MacIsaac & Menke Co. v. Cardox Corp., 193 Cal. App. 2d 661, 14 Cal. Rptr. 523, 1961 Cal. App. LEXIS 1756 (Cal. Ct. App. 1961).

Opinion

SHINN, P. J.

Plaintiff MacIsaac and Menke Company brought suit against defendant Cardox Corporation to recover their reasonable costs for work performed under a written subcontract, as modified by an executed oral agreement. Defendant American Casualty Company of Reading, Pennsylvania, as surety for Cardox, was joined as a party defendant. The Department of Water and Power of the City of Los Angeles viras the owner of the Valley Steam Plant on which the work was done and was joined as a defendant since it held funds of $8,991.11 following service upon it of a withhold notice. Plaintiff recovered a judgment against Cardox for $15,623.79 and a judgment against both American Casualty and the department which was limited to their specific interests in the suit in the sum of $8,991.11. Interest was awarded from the date of the job completion, March 14, 1956, which was later modified to only allow interest from the date of judgment, August 27, 1959.

Defendants appeal from the judgment and plaintiff cross-appeals from the modification of the judgment allowing interest only from the date of the judgment.

The findings are 42 in number. They comprise 17 pages of evidentiary facts in the clerk’s transcript. When reduced to their essentials they establish the following: Cardox manufactures and installs its own type of fire protection systems; typical systems are of overhead construction except where, in specified hazard areas, undercover or underground piping is called for; Cardox furnished plaintiff drawings and specifications showing clearly indicated undercover or underground piping in limited areas, and overhead installation in the remainder; plaintiff bid on the work in reliance upon these drawings and specifications and contracted to do the work in accordance therewith. However, the contract of Cardox with the department was upon specification Number 8736 of the department which provided that the contractor should “arrange, locate, using pipe trenches wherever possible” and plaintiff’s contract called for installation in accordance with Cardox’s drawings and specifications and also specification Number 8736 of the department. As the work progressed in accordance with plaintiff’s contract and the drawings of *665 Cardox, the department came forward with long-delayed drawings which called for extensive undercover and underground installation far more extensive than was shown on the drawings and specifications of Cardox and considerably more expensive. As a result of negotiations between plaintiff and Cardox it was orally agreed that Cardox would stand the extra expense if plaintiff would do the extra work; plaintiff completed the work in reliance upon the promise of Cardox and Cardox refused to pay. The judgment holds Cardox to its promise. There was ample evidence of the promise and of plaintiff’s reliance upon it.

If the findings had been drawn and plaintiff’s case had been briefed on the theory that plaintiff’s rights rest upon the oral contract, the case on appeal would have been greatly simplified. All that preceded the oral contract would have had little significance.

Inasmuch as it is earnestly contended that the oral agreement was not supported by a consideration, was not as broad as the court found it to be, and was not binding upon Cardox, these arguments may be answered by reference to the following evidentiary facts found.

In April 1955, Cardox was bidding for the installation of a fire protection system in Units (3) and (4) for the Department of Water and Power of Los Angeles City. Cardox supplied to plaintiff its drawings Numbers FE33677 and FD33364 and certain Cardox mechanical specifications for part of the work. In these drawings, by means of broken lines, it was designated that in some areas piping and fittings were to be placed underground or undercover. By means of solid lines it was designated that in all other areas in Units (3) and (4), piping and fittings were to be placed overhead in the open and above floor levels.

Before bidding the job, plaintiff inspected the job site in company with a representative of Cardox. Cardox’s agent represented to plaintiff that the proposed installation would be the typical Cardox installation, and that the piping, fittings and equipment were to be located overhead, except that in certain areas, which were not then shown on any drawings except those of Cardox, they would be placed undercover. Plaintiff had previously installed for Cardox more than one hundred fire protection systems of the overhead type.

On April 19, 1955, plaintiff submitted a written bid of $18,890, including overhead expense and fee, in accordance *666 with drawings FE33677 and FD33364 and the Cardox specifications to do the work in 56 calendar days.

On May 31, 1955, Cardox entered into a written contract with the department of water and power agreeing to install the low pressure carbon dioxide system in Units (3) and (4) in accordance with the department specification Number 8736, and to complete the work in 120 calendar days.

In reliance upon the aforementioned Cardox drawings and verbal representations, a subcontract was executed by plaintiff on June 8, 1955, which recited that plaintiff’s work was to be performed in accordance with the Cardox drawings FE and FD, plaintiff’s bid letter of April 19,1955, the department specification Number 8736 and Cardox’s general and special specifications.

The department specification Number 8736 in addition to requiring that the contractor should “arrange, locate, using pipe trenches wherever possible,” further required that Cardox prepare drawings showing details of the proposed installation and submit them to the department for its approval, and that the system be installed in accordance with the approved drawings. The subcontract further provided that any changes or work involving extra compensation had to have written authority from Cardox.

Several days before July 18, 1955, Cardox directed plaintiff to commence work, even though at that time Cardox had not obtained the department’s approval of detail drawings, and even though Cardox’s mechanical equipment, which was to be installed by plaintiff, had not been delivered to the job site.

Cardox failed to furnish approved detailed drawings and on July 29, 1955, with the consent of Cardox, the department agreed to furnish plaintiff with approved detailed drawings. Cardox directed plaintiff to perform its work in accordance with the department’s specifications which were furnished at various times between July 29, 1955, and September 10, 1955. The department’s drawings required a large portion of plaintiff’s installation to be placed in trenches.

The installation in pipe trenches was a substantial deviation from the subcontract. It required plaintiff to acquire additional labor, materials and equipment and it substantially increased the cost of performing the work. Also, Cardox failed to deliver the mechanical equipment to the job site prior to August 23, 1955, and then it only delivered various portions thereof at various times thereafter. In addition, the department’s substituted drawings were not furnished simul *667 taneously, but were furnished at various times, which interfered with the scheduling of work and caused further delays and interruptions.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

TD General Co. v. Chimes Tower Investment CA2/2
California Court of Appeal, 2024
F.W. Spencer & Son v. Harris Construction CA5
California Court of Appeal, 2014
Northrop Corp. v. General Motors Corp.
807 N.E.2d 70 (Indiana Court of Appeals, 2004)
General Motors Corp. v. Northrop Corp.
685 N.E.2d 127 (Indiana Court of Appeals, 1997)
Nicholson-Brown, Inc. v. City of San Jose
62 Cal. App. 3d 526 (California Court of Appeal, 1976)
Gee v. Nieberg
501 S.W.2d 542 (Missouri Court of Appeals, 1973)
Esgro Central, Inc. v. General Insurance
20 Cal. App. 3d 1054 (California Court of Appeal, 1971)
Kelley v. R. F. Jones Co.
272 Cal. App. 2d 113 (California Court of Appeal, 1969)
Healy v. Brewster
251 Cal. App. 2d 541 (California Court of Appeal, 1967)
MacOmber v. State of California
250 Cal. App. 2d 391 (California Court of Appeal, 1967)
Coleman Engineering Co. v. North American Aviation, Inc.
420 P.2d 713 (California Supreme Court, 1966)
Eluschuk v. Chemical Engineers Termite Control, Inc.
246 Cal. App. 2d 463 (California Court of Appeal, 1966)
Lozano v. Jollensten
211 Cal. App. 2d 845 (California Court of Appeal, 1963)
Bleakley v. Carnes
209 Cal. App. 2d 577 (California Court of Appeal, 1962)
Western Concrete Structures Co. v. James I. Barnes Construction Co.
206 Cal. App. 2d 1 (California Court of Appeal, 1962)

Cite This Page — Counsel Stack

Bluebook (online)
193 Cal. App. 2d 661, 14 Cal. Rptr. 523, 1961 Cal. App. LEXIS 1756, Counsel Stack Legal Research, https://law.counselstack.com/opinion/macisaac-menke-co-v-cardox-corp-calctapp-1961.