Miller v. Brown

289 P.2d 572, 136 Cal. App. 2d 763, 1955 Cal. App. LEXIS 1555
CourtCalifornia Court of Appeal
DecidedNovember 8, 1955
DocketCiv. 16436
StatusPublished
Cited by14 cases

This text of 289 P.2d 572 (Miller v. Brown) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Miller v. Brown, 289 P.2d 572, 136 Cal. App. 2d 763, 1955 Cal. App. LEXIS 1555 (Cal. Ct. App. 1955).

Opinion

PETERS, P. J.

Stanley J. Brown, a builder, contracted to build a house for D. R. Miller, at a fixed price, plus extras. After the house was constructed it cost considerably more than the contract price. The parties disagreed over what items should be listed as extras. Miller paid most of the bills and brought this action against Brown to recover $9,416.78, that being the amount that Miller claims that the price of the house exceeded the contract price. Brown answered and cross-complained for $1,698.58, the amount he claimed was still due him. The trial court entered its judgment denying any relief to Miller on his complaint, and granted Brown $700 on his cross-complaint. Miller appeals from the judgment insofar as it is adverse to him, and Brown cross-appeals *766 from the portion of the judgment limiting his recovery to $700.

Basically, most of the problems on these two appeals are factual. The evidence on the basic issues is highly conflicting. We are, of course, bound to resolve all conflicts in favor of that evidence that supports the judgment. That evidence is as follows:

Sometime prior to the 29th of August, 1952, Miller and Brown entered into an undated written “Building Agreement.” There are several important provisions of that agreement which should be quoted. They are:

“1. The Builder, acting as an agent for the owner shall purchase all materials and supervise the performance of all required masonery, [sic] iron work, rough and finish carpentry, plastering, dry wall materials, painting, glass and glazing, roofing, and rough grading, for the one story residence to be constructed [for D. R Miller].... In accordance with plans and specifications and made a part hereof. . . .
“4. Owner shall pay the labor and material bills for the construction of the above described residence in the following manner: By depositing of money to take care of costs in a joint bank account as needed during process of construction ; both Owner and Builder to check and okay bills before payment; Builder to write checks for same on joint account . . .
“5. The Owner agrees that the Builder shall receive for his services the sum of 10% of the total cost of construction. . .
“6. It is further agreed that the Owner and Builder shall cooperate to keep the cost of construction down and that any benefit derived from same shall be credited to the Owner. Any changes or deviations from the plans and specifications shall be in writing and signed for by both Owner and Builder. . . .
“9. It is agreed that the total fees of the builder shall not exceed the sum of $2,100.00 although 10% of the cost may be in excess of this amount.
“10. The builder guarantees the owner that the total cost shall not exceed $28,000.00 provided that there are no changes in the plans as agreed upon.”

It will be noted that this agreement requires that the house shall be constructed “In accordance with plans and specifications” that are “made a part hereof.” One of the major controversies on these appeals is what was meant by that *767 phrase. Prior to the signing of the contract, Brown had received preliminary plans from Mr. Woodruff, the draftsman. These preliminary plans, among other things, (Ex. H) called for a basement, an oil heating system, plaster walls, hardwood floors and exterior brick veneer. They were used by Brown to secure estimates from subcontractors. On the basis of these estimates Brown submitted an estimate to Miller of $28,354.30 (Ex. 11). Miller was of the opinion that this was more expensive than he desired, and he and Brown agreed to certain changes. Based on these changes Brown submitted a document entitled: “Cost of Construction of Residence for Mr. and Mrs. D. R. Miller.” (Ex. B.) The costs here submitted totalled $26,400.55. Brown testified that this cost list was the basis for the undated agreement above quoted, and Miller admitted that this was so. Brown claims that the changes then agreed upon provided for omitting the basement, substituting a gas furnace for the oil furnace, using basement heating, and using 5/16" plank flooring for Bruce flooring. He also testified that at the time Exhibit B was agreed upon there were no other plans and specifications in existence. Construction on the building started August 29, 1952.

Woodruff, the draftsman, testified that he completed the original plans by July 31, 1952, and that on August 26th, at Brown’s request, he altered the original plans so as to swing the bedroom wing around towards the patio. This change is embodied in Exhibit 4. These altered plans, he testified, he finished on August 30, 1952, and then delivered them to Brown. Brown disputed this evidence. He testified that it was not until August 30, 1952, after construction began, that he received the plans embodied in Exhibit 3, and that he did not receive the revised plans swinging the bedroom around (Ex. 4) until September 2, 1952. He was definite that the bedroom revision was not agreed upon until after the undated agreement above quoted (Ex. 1) had been signed. This conflict was for the trial court.

Admittedly, on September 8, 1952, Brown filed a request for a building permit and included in the request Exhibit 3 even though by that date the bedroom revision embodied in Exhibit 4 had been agreed upon. Brown stated, however, that he did this because the plans for the bedroom revision were then incomplete, and, had incomplete plans been filed, the permit would have been denied.

*768 Thus, Brown’s testimony is that when the undated agreement (Ex. 1) referred to “plans and specifications” it meant the original plans plus the oral modifications made to reduce costs as shown by Exhibit B. Miller disputes this evidence. He claims that Exhibits 2 and 3 are the “plans and specifications” referred to in the undated agreement embodied in Exhibit 1, and that the only alterations to those was the swinging of the bedroom wing so as to create an “L” shaped house instead of the originally designed straight line shape.

When the house was completed its total cost had amounted to $37,602.78. Toward the end of construction a dispute arose between the parties over what were proper extras. At that time Miller admittedly approved extras amounting to about $3,800. At the trial, however, Miller contended that he approved extras in that amount only in the spirit of compromise, and that the correct figure for the extras was about $2,400. The parties were unable to settle the dispute by negotiation. Miller paid all but a very few of the outstanding bills, claiming he did so only because he wanted to prevent mechanic’s liens from being filed, and then brought this action for $9,416.78, the amount he claims is the difference between what he paid for the house and the contract cost, plus admitted extras and less certain claimed savings. Brown answered, and cross-complained for the amount of several bills he paid, for $700 remaining due for his services under the contract, and for 10 per cent of the value of the extras. The total amount prayed for in the cross-complaint was $1,698.58.

Miller is a real estate broker. The checkbook from which bills were paid was in his possession and he had all the canceled checks.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

ePresence, Inc. v. Evolve Software, Inc.
190 F. Supp. 2d 159 (D. Massachusetts, 2002)
East-West Capital Corp. v. Khourie
10 Cal. App. 3d 553 (California Court of Appeal, 1970)
Healy v. Brewster
251 Cal. App. 2d 541 (California Court of Appeal, 1967)
Distefano v. Hall
218 Cal. App. 2d 657 (California Court of Appeal, 1963)
Ehrlich v. McConnell
214 Cal. App. 2d 280 (California Court of Appeal, 1963)
Hearst Publishing Co. v. Abounader
196 Cal. App. 2d 49 (California Court of Appeal, 1961)
MacIsaac & Menke Co. v. Cardox Corp.
193 Cal. App. 2d 661 (California Court of Appeal, 1961)
1st Olympic Corp. v. Hawryluk
185 Cal. App. 2d 832 (California Court of Appeal, 1960)
Bonadiman-McCain, Inc. v. Snow
183 Cal. App. 2d 58 (California Court of Appeal, 1960)
Wilson v. Keefe
309 P.2d 516 (California Court of Appeal, 1957)

Cite This Page — Counsel Stack

Bluebook (online)
289 P.2d 572, 136 Cal. App. 2d 763, 1955 Cal. App. LEXIS 1555, Counsel Stack Legal Research, https://law.counselstack.com/opinion/miller-v-brown-calctapp-1955.