Wayland Lum Construction, Inc. v. Kaneshige

978 P.2d 855, 90 Haw. 417, 1999 Haw. LEXIS 237
CourtHawaii Supreme Court
DecidedJune 9, 1999
Docket20684
StatusPublished
Cited by19 cases

This text of 978 P.2d 855 (Wayland Lum Construction, Inc. v. Kaneshige) is published on Counsel Stack Legal Research, covering Hawaii Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wayland Lum Construction, Inc. v. Kaneshige, 978 P.2d 855, 90 Haw. 417, 1999 Haw. LEXIS 237 (haw 1999).

Opinion

Opinion of the Court by

RAMIL, J.

Claimant-appellant Wayland Lum Construction, Inc. (“Claimant”) appeals from the circuit court’s order denying his motion to confirm an arbitration award. On appeal, Claimant contends that: (1) the arbitrator exceeded the scope of his authority by amending his original award; and (2) the circuit court erred in concluding that the original award was not final and in confirming the amended award. For the reasons discussed below, we affirm the circuit court’s order.

I. BACKGROUND

In May 1995, respondents-appellees Melvin Kaneshige and Nancy Pace (collectively, “Respondents”) hired Claimant to remodel their house. The construction contract signed by the parties contained a standard arbitration clause under which the parties agreed to submit to arbitration any dispute arising under the contract.

*420 Sometime during the course of the project, disputes arose regarding the work rendered by Claimant. As a result, Respondents asked Claimant to stop work on the project and hired a new contractor to finish the job. After being discharged, Claimant asserted that it was entitled to more money under the contract.

Pursuant to the construction contract, the parties retained Louis L.C. Chang, Esq. (Arbitrator) as arbitrator and signed an “Arbitration Agreement” in June, 1996 granting the Arbitrator complete authority to decide the case. Under the Arbitration Agreement, the parties agreed, inter alia, to “arbitrate any and all claims relating to ... [disputes and claims of the parties regarding amounts owed under [the contract].” The arbitration clause further specified that the following services would be provided by the arbitrator:

a. Meetings and /or joint telephone conferences with the parties;
b. Conduct and administer pre-arbitration and arbitration hearings;
c. Review and research of any writings, documents or other materials related to this dispute;
d. Drafting of any and all letters, mem-oranda, arbitration order(s), arbitration order(s), arbitration award and/or documents of any type.

On November 25, 1996, after the conclusion of the arbitration hearing, the parties attended a meeting held by the Arbitrator. At that meeting, the Arbitrator stated that he would be circulating a draft decision for review and comment by the parties. The parties agreed to that procedure.

On January 3, 1997, the Arbitrator circulated a document entitled “Arbitrator’s Decision and Award” (the Draft Award). In the Draft Award, the Arbitrator awarded Claimant $23,588.39. The Draft Award also stated that “[t]his Arbitration Decision and Award constitutes the final determination and resolution of all issues and claims raised and addressed in this arbitration.” However, the last sentence of the Draft Award stated:

The Arbitrator retains jurisdiction to address, clarify, and resolve any issues or questions raised by the parties within fourteen (14) days hereof concerning modification, implementation, and or interpretation of this Arbitration Award and Decision.

After reviewing the Draft Award, Claimant disagreed with the amount of the Arbitrator’s award and, as a result, did not to move to confirm the award under HRS § 658-8. A few days later, Claimant made an ex parte call to the Arbitrator to ask for an increase of the amount of the Draft Award. After receiving the call, the Arbitrator joined Respondents to the call by telephone conference. During the telephone conference, all parties agreed that they would submit written requests for modification of the award to the Arbitrator within fourteen days.

Within the fourteen-day period, the parties presented written submissions to the Arbitrator. After reviewing the parties’ submissions, the Arbitrator concluded that he had made several mistakes. On February 25, 1997, the Arbitrator issued a final award (the Final Award) in which he lowered the amount awarded to Claimant to $3,223.61 from the amount of $23,588.39, as set forth in the Draft Award. The Final Award concluded as follows:

The Arbitrator’s Decision and Award dated January 3, 1997, as revised by this Supplemental and Final Decision and Award together shall constitute the Arbitrator’s Final Decision and Award being the final determination and resolution of all claims and issues raised and addressed in this arbitration.

Unlike the Draft Award, the Final Award did not contain language reserving jurisdiction to the arbitrator.

Having been awarded a lower amount by the Arbitrator’s Final Award, Claimant filed a motion in the circuit court to confirm the Draft Award of January 3,1997, arguing that the Arbitrator lacked authority to modify the Draft Award. In response, Respondents filed a cross-motion to confirm the Final Award of February 25,1997.

On May 1, 1997, the circuit court entered an order denying Claimant’s motion to confirm the Draft Award and granting Respondents’ motion to confirm the Final Award. *421 From this order, Claimant filed a timely notice of appeal to this court.

II. STANDARDS OF REVIEW

A. Statutory Construction

The issue whether the circuit court erred in confirming the Final Award of the Arbitrator requires an interpretation of HRS §§ 658-8, 1 658-9 2 and 658-10 3 (1993). The interpretation of a statute is a question of law reviewable de novo. Shimabuku v. Montgomery Elevator Co., 79 Hawai'i 352, 357, 903 P.2d 48, 52 (1995) (citation omitted).

B. Arbitration

Our review of arbitration awards is guided by the following principles. It is well settled that “[bjecause of the legislative'policy to encourage arbitration and thereby discourage litigation, judicial review of an arbitration is confined to ‘the strictest possible limits[.]”’ Mathewson v. Aloha Airlines, Inc., 82 Hawai'i 57, 69, 919 P.2d 969, 981 (1996) (quoting Arbitration Bd. of Directors of Ass’n of Apartment Owners of Tropicana Manor, 73 Haw. 201, 205, 830 P.2d 503, 507 (1992) (hereafter “Jeffers ”) (brackets in original) (citations omitted)); see also Excelsior Lodge Number One, Indep. Order of Odd Fellows v. Eyecor, Ltd., 74 Haw.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Krafchow v. Dongbu Insurance Co., Ltd. Consolidated With Case No. CAAP-21-0000517.
525 P.3d 697 (Hawaii Intermediate Court of Appeals, 2023)
Douglass v. Pflueger Hawaii, Inc.
135 P.3d 129 (Hawaii Supreme Court, 2006)
BFN-GREELEY, LLC v. Adair Group, Inc.
141 P.3d 937 (Colorado Court of Appeals, 2006)
Mandl v. Bailey
858 A.2d 508 (Court of Special Appeals of Maryland, 2004)
Hamada v. Westcott
74 P.3d 33 (Hawaii Supreme Court, 2003)
Flores v. Barretto
54 P.3d 441 (Hawaii Supreme Court, 2002)
Tatibouet v. Ellsworth
54 P.3d 397 (Hawaii Supreme Court, 2002)
Valrose Maui, Inc. v. MacLyn Morris, Inc.
105 F. Supp. 2d 1118 (D. Hawaii, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
978 P.2d 855, 90 Haw. 417, 1999 Haw. LEXIS 237, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wayland-lum-construction-inc-v-kaneshige-haw-1999.