RTI Connectivity Pte. Ltd. v. Gateway Network Connections, LLC

CourtDistrict Court, D. Hawaii
DecidedJuly 28, 2022
Docket1:22-cv-00302
StatusUnknown

This text of RTI Connectivity Pte. Ltd. v. Gateway Network Connections, LLC (RTI Connectivity Pte. Ltd. v. Gateway Network Connections, LLC) is published on Counsel Stack Legal Research, covering District Court, D. Hawaii primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
RTI Connectivity Pte. Ltd. v. Gateway Network Connections, LLC, (D. Haw. 2022).

Opinion

UNITED STATES DISTRICT COURT

DISTRICT OF HAWAII

RTI CONNECTIVITY PTE. LTD., a CIV. NO. 22-00302 LEK-RT Singapore private limited company and RUSSELL A. MATULICH,

Plaintiffs,

vs.

GATEWAY NETWORK CONNECTIONS, LLC,

Defendant.

ORDER GRANTING PLAINTIFFS’ MOTION FOR EXPEDITED ORDER TO CONFIRM AND ENFORCE PRE-AWARD RULING AND AWARD OF ARBITRATION PANEL

Before the Court is Plaintiffs RTI Connectivity Pte., Ltd. (“RTI-C”) and Russell A. Matulich’s (“Matulich” and collectively “Plaintiffs” or “Claimants”) Motion for Expedited Order to Confirm and Enforce Pre-Award Ruling and Award of Arbitration Panel (“Motion to Confirm”), filed on June 27, 2022 in state court. See Defendant Gateway Network Connections, LLC’s Notice of Removal, filed 7/11/22 (dkt. no. 1), Decl. of Randall C. Whattoff (“Whattoff Removal Decl.”), Exh. 1 (Motion to Confirm). Defendant Gateway Network Connections, LLC (“GNC” or “Respondent”) filed its memorandum in opposition on July 21, 2022. [Dkt. no. 11.] This matter came on for hearing on July 26, 2022. The Motion to Confirm is hereby granted for the reasons set forth below. BACKGROUND RTI-C and GNC are involved in an on-going arbitration. See Notice of Removal at ¶ 3 (noting the order before the Court in the Motion to Confirm is an interim ruling issued in a pending arbitration before Dispute Prevention & Resolution, Inc.

(“DPR”)); see also Motion to Confirm, Decl. of Leroy E. Colombe (“Colombe Decl.”), Exh. A (copy, without exhibits, of RTI-C’s Commercial Arbitration Rules Demand for Arbitration, dated 4/13/21 (“Arbitration Demand”)).1 Plaintiffs filed this action to confirm and enforce the DPR arbitration panel’s (“Arbitration Panel”) June 17, 2022 pre-award rulings and order (“6/17/22 Interim Order”). See Motion to Confirm at 2 (dkt. no. 1-3 at PageID #: 12).2

1 Although the Arbitration Demand was originally submitted to the American Arbitration Association, see Colombe Decl., Exh. A (Arbitration Demand) at 1 (dkt. no. 1-3 at PageID #: 25), the parties later agreed to have DPR conduct the arbitration proceeding. See id., Exh. H (Agreement to Participate in Binding Arbitration, dated August 4 and 17, 2021 (“Arbitration Agreement”)).

2 The 6/17/22 Interim Order is titled “Order Setting Evidentiary Hearing on Claimants’ Motion to Clarify the Panel’s June 7, 2022, Interim Order and Status Update Re: GNC’s Violation of the Panel’s June 7, 2022 Interim Order Granting RTI-C Customary Access and Service and Issuance of Temporary Restraining Order Restraining and Enjoining GNC’s [sic] from Denying Claimnts [sic] Customary Access and Service at the GNC Data Center.” See Colombe Decl., Exh. G at 1 (dkt. no. 1-3 at PageID #: 111). According to the Arbitration Demand, RTI-C “is a Singapore private limited company with its principal place of business in Singapore” and Matulich, an individual who resides in California, is a former board member and chief executive officer (“CEO”) of GNC. [Colombe Decl., Exh. A (Arbitration

Demand) at Attachment A, § I (dkt. no. 1-3 at PageID #: 27).] GNC states it is a Guam limited liability company (“LLC”) with two members: Asia Connectivity Elements, Inc. (“ACE”), a Guam corporation with its principal place of business in Guam; and Teleguam Holdings, LLC (“Teleguam”), a Delaware LLC. Teleguam has one member - Teleguam Holdings, Inc., a Delaware corporation with its principal place of business in Guam. [Notice of Removal at ¶¶ 15-15.b.] The Arbitration Panel summarized the background of the parties’ dispute as follows: This arbitration involves, in part, a dispute under a master license and service agreement dated July 1, 2020, hereafter the MSA. Under the MSA, GNC granted RTI-C a non-exclusive revocable license to use certain space at GNC’s data center in Guam [(“Data Center”)], so that it could install, operate, and maintain its equipment.[3]

On December 31, 2020, Claimant Russell Matulich was removed as the CEO of one of the

3 The equipment at issue relates to “the subsea fiber optic cable business.” Cf. Colombe Decl., Exh. A (Arbitration Demand) at Attachment A, § II (dkt. no. 1-3 at PageID #: 27); id. (dkt. no. 1-3 at PageID #: 30); id. at § VII (dkt. no. 1-3 at PageID #: 34-35). members of GNC. GNC claims that Matulich’s removal as CEO of one of GNC’s members automatically removed him as a director of GNC. RTI-C and Matulich dispute that Matulich was effectively removed as a director of GNC.

After Matulich’s removal as CEO, GNC took actions under the MSA, which required the unanimous approval of the board of directors of GNC. These actions included issuing approximately $500,000 in invoices to RIT-C dating back to July 2020 and threatened to turn off RTI-C’s equipment at the GNC Data Center.

RTI-C paid GNC under protest and initiated litigation and in April 2020, this arbitration. RTI-C has paid $813,835.00 of the $1,137,234 in GNC invoices and is disputing the remainder in this arbitration. RTI-C was fully paid up on rent until the start of the arbitration in April when it stopped paying approximately 50% of GNC’s monthly charges, asserting that said amount is the undisputed portion of the charges. The remaining charges claimed by GNC, along with the validity of the MSA, are at issue in this arbitration.

[Colombe Decl., Exh. B (Order Granting Claimant’s Emergency Request for an Interim Order to Maintain the Status Quo at Gateway Network Connection, LLC’s Data Center, dated 9/10/21 (“9/10/21 Interim Order”)) at 2 (dkt. no. 1-3 at PageID #: 40).] The 9/10/21 Interim Order was entered in response to Plaintiffs’ Emergency Request for an Interim Order to Maintain the Status Quo at the Gateway Network Connection LLC’s Data Center, which the Arbitration Panel heard on September 3, 2021 (“First Emergency Motion”). See id. at 1 (dkt. no. 1-3 at PageID #: 39).] The Arbitration Panel found that GNC has locked RTI-C out of its space and is not allowing RTI-C to install, operate, and maintain its equipment. If GNC is allowed to continue to do so, RTI-C will be deprived of the use and utility of its space at the GNC Data Center and thus the ability to secure the fruits of this arbitration, should RTI-C prove successful in its claim that GNC’s 2021 invoices of unbilled 2020 services and other heretofore disputed invoices are invalid.

. . . .

Rule 24 of the DPR Rules empowers the panel to issue interim awards to maintain the status quo until the award of the arbitrators is rendered or the controversy is otherwise resolved. The panel finds that it is reasonable and necessary to maintain the status quo related to the access and use by RTI-C of the licensed space at the GNC Data Center pending a resolution of the dispute over the validity of the MSA and the invoices issued by GNC to RTI-C.

[Id. at 3 (dkt. no. 1-3 at PageID #: 41) (emphases added).] The 9/10/21 Interim Order: required GNC to provide, until December 1, 2021, RTI-C “with the customary access and service that it was providing to RTI-C prior to December 31, 2020” (“Customary Access and Services”); and required RTI-C to make all payments and comply with all terms of the MSA, unless the payment or MSA term was disputed in the arbitration (“Undisputed Payments and Terms”). [Id. at 4 (dkt. no. 1-3 at PageID #: 42).] On October 22, 2021, Plaintiffs filed their Emergency Request for an Order Compelling GNC to Provide Additional Power to RTI-C’s Cage and Request for Sanctions (“Second Emergency Motion”). [Mem. in Opp., Decl. of Randall C. Whattoff (“Whattoff Opp. Decl.”), Exh. 5.] The Arbitration Panel denied the Second Emergency Motion because Plaintiffs “fail[ed] to demonstrate that maintaining the status quo requires GNC to

provide additional power to the RTI-C cage on terms that were not specifically agreed to prior to the initiation of this arbitration.” [Id., Exh.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United Steelworkers v. Enterprise Wheel & Car Corp.
363 U.S. 593 (Supreme Court, 1960)
First Options of Chicago, Inc. v. Kaplan
514 U.S. 938 (Supreme Court, 1995)
Ventress v. Japan Airlines
603 F.3d 676 (Ninth Circuit, 2010)
Hall Street Associates, L. L. C. v. Mattel, Inc.
552 U.S. 576 (Supreme Court, 2008)
Johnson v. Gruma Corp.
614 F.3d 1062 (Ninth Circuit, 2010)
Metzler Contracting Co. LLC v. Paul Stephens
479 F. App'x 783 (Ninth Circuit, 2012)
Oxford Health Plans LLC v. Sutter
133 S. Ct. 2064 (Supreme Court, 2013)
Wayland Lum Construction, Inc. v. Kaneshige
978 P.2d 855 (Hawaii Supreme Court, 1999)
Gadd v. Kelley
667 P.2d 251 (Hawaii Supreme Court, 1983)
Association of Flight Attendants v. Aloha Airlines, Inc.
158 F. Supp. 2d 1200 (D. Hawaii, 2001)
Metzler Contracting Co. LLC v. Stephens
774 F. Supp. 2d 1073 (D. Hawaii, 2011)
Tatibouet v. Ellsworth
54 P.3d 397 (Hawaii Supreme Court, 2002)
Kenneth H. Hughes, Inc. v. Aloha Tower Development, Corp.
654 F. Supp. 2d 1142 (D. Hawaii, 2009)
Balberdi v. Fedex Ground Package System, Inc.
209 F. Supp. 3d 1160 (D. Hawaii, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
RTI Connectivity Pte. Ltd. v. Gateway Network Connections, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rti-connectivity-pte-ltd-v-gateway-network-connections-llc-hid-2022.