VanVoorhees v. Dodge

679 A.2d 1077, 1996 Me. LEXIS 166
CourtSupreme Judicial Court of Maine
DecidedJuly 11, 1996
StatusPublished
Cited by55 cases

This text of 679 A.2d 1077 (VanVoorhees v. Dodge) is published on Counsel Stack Legal Research, covering Supreme Judicial Court of Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
VanVoorhees v. Dodge, 679 A.2d 1077, 1996 Me. LEXIS 166 (Me. 1996).

Opinion

RUDMAN, Justice.

Peter Dodge appeals from a judgment entered after a jury-waived trial in the Superi- or Court (Washington County, Marsano, J.) awarding compensatory damages and attorney fees to Wayne and Barbara VanVoo-rhees. On appeal Dodge challenges, inter alia, the court’s factual findings with respect to his breach of a contract and the court’s award of attorney fees to the VanVoorhees pursuant to the Home Construction Contracts Act, 10 M.R.SA §§ 1486-90 (Supp. 1995), and the Maine Unfair Trade Practices Act, 5 M.R.SA. § 213 (1989 & Supp.1995) (UTPA). We affirm the judgment.

In May 1991 the VanVoorhees poured a foundation on their shorefront lot in Machias-port. Soon thereafter, Wayne VanVoorhees was contacted by Peter Dodge, who described himself as a construction consultant and designer whose job was to “oversee the building of a house.” The VanVoorhees ultimately met with Dodge and hired him to design their home and to provide consulting services. Dodge agreed that once construction began he would provide the VanVoo-rhees with materials “at cost.” Over the next year, between June 1991 and July 1992, Dodge developed plans for a 2300-square-foot home.

As plans for the home began to crystallize, Dodge sent a letter to the VanVoorhees estimating that the cost of constructing the home would be between $65 and $85 per square foot, which amounted to an estimated cost of construction of between $150,000 and $200,000. The VanVoorhees told Dodge they did not want the cost of the home to exceed $150,000 and Dodge assured them, both verbally and in writing, that he could construct the home at that cost.

Construction on the home began in earnest in August of 1992 with Dodge promising a completion date (for at least the home’s carriage house apartment) of late October or early November of the same year. Dodge was the party responsible for the day-to-day management of the construction site including the selection and supervision of the subcontractors and the ordering of materials. Although Dodge testified to the contrary, four experienced subcontractors each testified that work on the VanVoorhees’ home suffered because of Dodge’s incompetence both as a designer and a manager. Subcontractors were repeatedly called to the site when the home was not ready for them to begin their portion of the project, windows were mismeasured, rooms were poorly designed requiring redesigning during the construction process, and certain portions of the construction occurred out of sequence, result *1080 ing in damage to the home and additional cost.

As summer quickly turned to autumn and with winter fast approaching, several factors led the VanVoorhees to dismiss Dodge. First, the VanVoorhees came to the realization that no part of their new home would be completed by late October or early November as promised by Dodge. Second, the VanVoorhees learned that Dodge had broken his “at cost” promise to them by charging them more than $37,000 for windows that cost approximately $30,000 and that never were delivered. Third, Dodge informed the VanVoorhees that the final cost of construction for the home would exceed his $150,000 estimate by between $80,000 and $90,000.

After discharging Dodge, the VanVoorhees continued the construction of their home as the weather and their finances permitted. As a result of Dodge’s failure to complete the home by November 1992, the VanVoorhees incurred additional rental and living expenses from November 1992 until September 1993 while they awaited completion of the carriage house apartment. Additionally, by the time of the trial the amounts expended to build the home had burgeoned to almost $300,000.

The VanVoorhees filed a seven-count complaint against Dodge alleging, inter alia, breach of contract and violation of the UTPA. Dodge responded to VanVoorhees’ complaint and brought a counterclaim alleging monies to be due to him. Following a jury-waived trial, the court found that there was an oral contract between Dodge and the VanVoo-rhees for the construction of the house and that Dodge had breached the contract. Based on the breach of contract the court awarded the VanVoorhees $34,000 in restitution for the undelivered windows, $35,000 in compensatory damages, and $4,000 in consequential damages. Additionally, the court found that Dodge had violated the Home Construction Contract Act and, thereby, the UTPA, by failing to provide the VanVoorhees with a written contract. The court awarded the VanVoorhees $3,500 in attorney fees pursuant to the UTPA. The court further awarded the VanVoorhees judgment on Dodge’s counterclaim.

I

Breach of Contract

Dodge first contends that the court erred in finding that he had breached his contract with the VanVoorhees. We disagree.

“It is the duty of the fact-finder to determine the existence of the parol contract, its extent and limitations, in other words, to find not only what language was used, but its purport and meaning.” Dehahn v. Innes, 356 A.2d 711, 716 (Me.1976). Similarly, the question of whether there has been a breach of contract is a question of fact. See Marcus v. Lee S. Wilbur & Co., 588 A.2d 757, 759 (Me.1991). We will not set aside the factual findings of the trial court unless they are clearly erroneous. Barker v. St. Mary’s Regional Medical Ctr., 663 A.2d 44, 46 (Me.1995). A trial court’s factual finding is “clearly erroneous” if there is no competent evidence in the record to support it. FDIC v. Proia, 663 A.2d 1252, 1254 (Me.1995).

The court’s finding that Dodge and the VanVoorhees had entered into a contract and that Dodge had breached the contract is not clearly erroneous.

To establish a legally binding agreement the parties must have mutually assented to be bound by all its material terms; the assent must be manifested in the contract, either expressly or impliedly; and the contract must be sufficiently definite to enable the court to determine its exact meaning and fix exactly the legal liabilities of the parties.

Roy v. Danis, 553 A.2d 663, 664 (Me.1989) (citations omitted). The determination of the credibility of the witnesses is a matter solely within the province of a presiding judge acting as the finder of fact, and the court here was free to discount or entirely ignore testimony the presiding judge found to be incredible. See Gray v. Gray, 609 A.2d 694, 697 (Me.1992). Competent evidence on the record supports both the court’s finding that Dodge had agreed to design and build the VanVoorhees’ home in return for the Van-Voorhees’ promise to pay him at an hourly *1081 rate for his services and that Dodge had breached this agreement by failing to provide materials “at cost” and by failing to complete construction of portions of the home on time.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

H.A.T., LLC v. Greenleaf Apartmetns, LLC
2026 ME 20 (Supreme Judicial Court of Maine, 2026)
Kathy S. Brown v. Compass Harbor Village Condominium Association
2020 ME 44 (Supreme Judicial Court of Maine, 2020)
John Sweet II v. Carl E. Breivogel
2019 ME 18 (Supreme Judicial Court of Maine, 2019)
Sweet v. Breivogel
201 A.3d 1215 (Supreme Judicial Court of Maine, 2019)
Cole v. Dow
Maine Superior, 2016
Philip C. Tobin v. Philip N. Barter
2014 ME 51 (Supreme Judicial Court of Maine, 2014)
Estate of Michael Lewis v. Concord General Mutual Insurance Company
2014 ME 34 (Supreme Judicial Court of Maine, 2014)
Pelletier v. Pelletier
2012 ME 15 (Supreme Judicial Court of Maine, 2012)
Bordetsky v. Charron
Maine Superior, 2012
Coastal Ventures v. Alsham Plaza, LLC
2010 ME 63 (Supreme Judicial Court of Maine, 2010)
AQUILA, LLC v. City of Bangor
640 F. Supp. 2d 92 (D. Maine, 2009)
Treadwell v. J.D. Construction Co.
2007 ME 150 (Supreme Judicial Court of Maine, 2007)
SUZMAN v. Crisp
489 F. Supp. 2d 103 (D. Maine, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
679 A.2d 1077, 1996 Me. LEXIS 166, Counsel Stack Legal Research, https://law.counselstack.com/opinion/vanvoorhees-v-dodge-me-1996.