John Sweet II v. Carl E. Breivogel

2019 ME 18
CourtSupreme Judicial Court of Maine
DecidedJanuary 29, 2019
StatusPublished
Cited by10 cases

This text of 2019 ME 18 (John Sweet II v. Carl E. Breivogel) is published on Counsel Stack Legal Research, covering Supreme Judicial Court of Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
John Sweet II v. Carl E. Breivogel, 2019 ME 18 (Me. 2019).

Opinion

MAINE SUPREME JUDICIAL COURT Reporter of Decisions Decision: 2019 ME 18 Docket: Han-18-196 Argued: December 11, 2018 Decided: January 29, 2019

Panel: SAUFLEY, C.J., and ALEXANDER, MEAD, GORMAN, JABAR, HJELM, and HUMPHREY, JJ.

JOHN SWEET II

v.

CARL E. BREIVOGEL et al.

HUMPHREY, J.

[¶1] In this appeal involving a dispute over payment for the construction

of a traditional timber frame home, we consider the connection between the

Home Construction Contracts Act (HCCA) and the Unfair Trade Practice Act

(UTPA), take this opportunity to underscore the significance of the statutory

requirement that construction contracts be formalized in writing, and affirm

the judgment. See 5 M.R.S. § 213(1), (2) (2017); 10 M.R.S. §§ 1487, 1490 (2017).

I. BACKGROUND

[¶2] The following facts are drawn from the court’s judgment and are

supported by competent evidence in the record. See Gravison v. Fisher,

2016 ME 35, ¶ 3, 134 A.3d 857. 2

[¶3] John Sweet II is a sole proprietor who specializes in the construction

of traditional timber frame homes, which involve a high level of labor, time, and

craftmanship. In February 2013, Carl E. and Elizabeth A. Breivogel contacted

Sweet through his construction-business website and inquired about building

“an enclosed, [weathertight] frame home” on land they own on Mount Desert

Island.

[¶4] In March 2013, the Breivogels traveled to Maine and met with Sweet

at his self-constructed timber frame home. During that visit, the Breivogels

viewed Sweet’s workshops as well as two other timber frame homes that Sweet

had constructed. While the parties did not reach any agreements that day,

Sweet did provide the Breivogels with some information about the relative

costs of the homes they visited. Specifically, he told the Breivogels that it would

cost approximately $500,000 to build a 28’ x 30’ completed home like his and

$400,000 to construct the 32’ x 32’ home they visited that was little more than

a “dried shell” or “weathertight” home.1

1 In their testimony, Sweet and his son, John Sweet III, explained that a “dried shell” or “weathertight” home refers to a building that has a traditional timber frame, a roof, and exterior walls, but does not have electricity, plumbing, fixtures, or completed rooms. Because cutting into the timbers after the frame is complete compromises the home’s structure and integrity, a dried shell is often built with an overall plan for the completed home in mind. In contrast, a completed home ready for occupancy includes features such as a kitchen, functioning bathrooms, light fixtures, and internal walls for rooms. 3

[¶5] After that meeting, the parties continued to communicate via email.

In one exchange dated March 26, 2013, the parties began to discuss the costs

associated with building a saltbox style2 timber frame home. The Breivogels

asked Sweet whether it would be possible to build a home of this style for

$275,000, not including the septic system for which the Breivogels would make

other arrangements. Sweet responded that it was possible, but difficult to be

certain at that early stage of the discussion because “the devil[’]s in the details.”

[¶6] From that point forward, the parties did not share the same

understanding of the scope and cost of the work Sweet was to perform. Sweet

believed that the Breivogels wanted him to construct an enclosed, weathertight

timber frame home—including only a frame, walls, roof, insulation, doors,

windows, chimney, and exterior shingles. In contrast, the Breivogels believed

that they had requested a fully completed home, ready for occupancy, costing

no more than $275,000.

[¶7] In April 2013, the Breivogels authorized Sweet to begin

construction; however, the parties never signed a contract. When the

Breivogels inquired when the parties would formalize the terms of the project,

2 A saltbox style home is “a house . . . having two stories in front and one at the rear, and a gable

roof with a much longer slope at the rear.” Saltbox, Webster’s New World College Dictionary (5th ed. 2016). 4

Sweet insisted that he had never signed a written contract in over thirty years

of business. The parties did, however, arrange that the Breivogels would be

billed biweekly and pay for all materials and any labor at $32 an hour.

[¶8] Sweet and his team began construction of a dried shell structure in

the summer of 2013 and completed the work in December of that year.

Throughout the project, Sweet sent numerous emails to the Breivogels

containing photographs depicting the progress on their home. He also

provided biweekly invoices; despite these frequent communications, however,

Sweet’s overall record-keeping process throughout the project was highly

informal.

[¶9] After December, both parties understood that work on the home

would progress beyond the dried shell phase. At that point, the Breivogels

determined, without informing Sweet, that they would have Sweet continue to

work on the project, but would initiate legal action against him after they

obtained a certificate of occupancy. They intended to seek damages for

payments made in excess of $275,000. The Breivogels continued to pay Sweet

until May 4, 2014. Construction of the home was completed and the Breivogels

received their certificate of occupancy on May 15, 2014. 5

[¶10] In total, Sweet billed the Breivogels $602,250.98 for materials and

services. The Breivogels had paid $601,195.75. After the Breivogels refused to

tender any further payments, Sweet placed a $51,953.94 lien on the home for

unpaid labor and brought this action against the Breivogels for that amount

plus interest.3 The Breivogels asserted counterclaims for negligence, breach of

contract, fraud, negligent misrepresentation, breach of the implied warranty of

workmanship, and a violation of the UTPA.

[¶11] The Superior Court (Hancock County, R. Murray, J.) concluded that

Sweet was entitled to the money that he had already received from the

Breivogels for the home under the theory of quantum meruit; however, the

court also determined that Sweet had actually overcharged the Breivogels by

$640.77 for the work performed by a tiler. With respect to the Breivogels’

counterclaims, the court concluded that they failed to establish that Sweet was

negligent, had breached any contractual obligation to perform in a

workmanlike manner, or had breached any implied warranty relating to

workmanship. It also determined that Sweet did not commit fraud or negligent

misrepresentation. However, the court did find that Sweet violated the HCCA

3 Although the record is sparse with regard to the basis for this amount, Sweet testified that he

filed the lien to recover money owed to him for his own labor and for work performed on the project by the plumbing contractor. 6

by failing to furnish a written contract, which was prima facie evidence of a

UTPA violation.

[¶12] The Breivogels filed a motion for amended and additional findings

of fact and conclusions of law. The court declined to amend the factual findings,

but awarded the Breivogels $3,832.43 in costs and $30,000 in attorney fees as

permitted by the UTPA. The Breivogels timely appealed. M.R. App. P. 2A(a),

2B(c).

II. DISCUSSION

[¶13] The Breivogels contend that the Superior Court erred in

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fair Friend Enterprise Co., Ltd. v. CNC Systems, Inc.
2025 ME 37 (Supreme Judicial Court of Maine, 2025)
Chase v. MaineHealth
Maine Superior, 2023
Norton v. Norton
Maine Superior, 2023
Alexander v. Cote
Maine Superior, 2022
Fortney & Weygandt, Inc. v. Lewiston DMEP IX
2022 ME 5 (Supreme Judicial Court of Maine, 2022)
Matthew Pollack v. Jessica Fournier
2020 ME 93 (Supreme Judicial Court of Maine, 2020)

Cite This Page — Counsel Stack

Bluebook (online)
2019 ME 18, Counsel Stack Legal Research, https://law.counselstack.com/opinion/john-sweet-ii-v-carl-e-breivogel-me-2019.