Alexander v. Cote

CourtSuperior Court of Maine
DecidedNovember 14, 2022
DocketANDcv-19-163
StatusUnpublished

This text of Alexander v. Cote (Alexander v. Cote) is published on Counsel Stack Legal Research, covering Superior Court of Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Alexander v. Cote, (Me. Super. Ct. 2022).

Opinion

STATE OF MAINE SUPERIOR COURT ANDROSCOGGIN, SS. CIVIL ACTION DOCKET NO. CV-19-163

) RICHARD ALEXANDER, ) ) Plaintiff ) ) vs. ) DECISION AND JUDGMENT ) MICHAEL COTE, ) Individually and doing business as ) M&M CONSTRUCTION Ent. Inc. ) and ) M&M CONSTRUCTION ) ) Defendant )

On September 12, 2019, Plaintiff Richard Alexander (hereafter "Alexander") filed with the

comt a ten count complaint against Defendant Michael Cote and M&M Construction (hereafter

"Cote") alleging Violations of the Home Construction Contract Act, 10 M.R.S.A. §§ 1486 et seq.,

Unfair Trade Practices, 5 M.R.S.A. §207 Negligence, Breach of Contract, Breach of Warranty,

Fraudulent Misrepresentation and Conversion. Cote timely answered. Trial on the matter was held on

October 31, 2022, jury waived. At trial, testimony was received from Alexander, Cote, and Mike

Schade of Androscoggin Builders and Maintenance, Plaintiff's designated expert. The following

exhibits were also admitted (Plaintiff's Exhibits hereafter P. Ex. , and Defense Exhibit hereafter D.

Ex._):

P. Ex. 1- Demand Letter served upon Cote pursuant to 5 M.R.S.A. §213 and 10 M.R.S.A. §

1486;

P.Ex. 22- Design Drawing;

P. Ex. 23-Contract Dated October 12, 2018 for deck; P. Ex. 24- Contract Dated October 12, 2018 for Addition;

P. Ex. 27a- Check for $9,375.00;

P. Ex. 27b- Check for $8,735.50;

P. Ex. 28- Contract dated January 9, 2019 with Androscoggin Builders;
P. Ex 29- Opinion Letter dated March 13, 2019 by Mike Schade;
P. Ex. 30- Plaintiffs Expert Witness Designation;
P. Ex. 30a- Building design schematic by Mike Schade;
P. Ex. 36- Photograph of Cote's yard sign;
P. Ex. 37- Photographs of work completed by Cote;
P. Ex. 41- Text messages by Cote seeking laborers;
P. Ex. 41a- Photographs of deck as completed by Mike Schade;
P. Ex. 42- Facebook posts by Cote adve1tising for sale his van;
P. Ex. 43- Facebook posts by Cote advertising for sale his van; and
D. Ex. 1- Labor and material lists by Cote.

Findings of Fact.

Based upon the testimony presented and exhibits admitted, the court makes the following

findings of fact ­

In the fall of 2018, Alexander made a post on Face book indicating that he was in search of a

contractor to construct at this home at 55 Bailey Avenue in Lewiston a new addition and deck. Cote

responded to the post and the two met at Alexander's home to discuss the project. After Cote presented

Alexander with some preliminary drawings, Cote presented Alexander with two estimates, one for a

14' x 14' deck and the second for a 24' x 24' addition. ( P. Ex' s. 23 and 24 ). The estimate for the deck

2 was for $5,625.00 and the estimate for the addition was $6,437.50. Both estimates represented Cote

was "fully insured". (Id.). Although Cote told Alexander he also drove a school bus patt-time, he

represented to Alexander that he had a crew, and all of the tools and equipment to do the job. Relying

on those representations, both estimates were signed by Alexander and Cote on October 17, 2018.

(Id.) Both estimates contained a payment schedule. (Id.) The estimate for the deck required payments

of $2937.50 at time of signing and $1468.75 upon completion of supports and framing. (Id.) The

estimate for the addition required payments of$64 37 .50 at time of signing, $3218. 75 upon completion

of supports and framing, and $3218.75 upon completion of all work. (Id.) Alexander paid to Cote

$9375.00 at time of signing of the two estimates, being the total of both estimates due at that time.

(P.Ex. 27a).

The court finds that the two estimates signed by the parties on October 17, 2018 accurately

reflected the price and scope of work to be completed by Cote. Both contracts however failed to

comply with the Home Construction Contract Act (HCCA) and failed to contain several required

provisions. Specifically, both contracts failed to contain provisions setting forth the work dates,

required warranty language, dispute resolution alternatives, change order requirements, and required

warnings and notices regarding consumer protection. (See 10 M.R.S.A. §1487). And both contracts

violated the initial down payment limitation of 1/3 of the total contract price. (See 10 M.R.S.A.

§1487(5)). As will be discussed herein, the violations in these two contracts are material to the dispute

evolving between the parties, and finds that the two contracts violate the HCCA. Accordingly, the

court finds that Cote has violated the Unfair Trade Practices Act (UTPA), 5 M.R.S.A. 207. (See 10

M.R.S.A. §1490; see also State v. Breivogel, 2019 ME 18, ~21.

3 Although the contracts were silent regarding work dates and warranty, from the testimony,

the court finds that the parties mutually contemplated the work would be completed in a reasonable

time, in a generally skillful manner up to customary building standar·ds.

After the contracts were signed, Cote had difficulty lining up laborers to assist him to do the

job. On October 31, 2018 and November 7, 2018, Cote made posts on Facebook soliciting workers.

(P.Ex. 41). When Cote did start work on the project, the only help he had was an older gentleman,

who soon quit, and then later Cote's daughter worked some on the project. Seeing that work was

being delayed, Alexander gave Cote the names of a couple men he knew who had done some work

in the neighborhood. Cote's inability to hire workers delayed the project, and also revealed he had

misrepresented that he had a crew and could timely complete the project.

The project was also delayed by some code compliance issues. Although the evidence was

not particularly clear, the cowt infers that a setback issue led to an alteration of the addition portion

of the project. Cote also testified that the local code enforcement officer had imposed more stringent

requirements for the depth the concrete piers had to be bmied in the ground. Cote altered the scope of

work for the addition, likely incurring more cost, but no change orders or amendments to the contracts

were signed. Cote did however request Alexander remit more money. On November 16, 2018,

Alexander tendered a check in the amount of $8,735.50, which was applied towards both contract

projects. (P.Ex's. 23, 24, 27a, and 27b).

As the days went by with work advancing slowly, Alexander became very concerned about

the quality of the work that had been perf01med. After spealdng with individuals who had some

experience in the field, Alexander was concerned that the piers were installed unevenly, blocks of

wood or shims were required for leveling, there were no attachment bolts in the piers, and the structure

was not square or level. Alexander was also concerned that Cote was rar·ely on-site, and the laborers,

4 who were not well skilled, were working unsupervised. Alexander presented his concerns to Cote,

which Cote did not take well. Alexander also requested Cote provide him with proof of insurance,

which Cote never produced. Alexander and Cote argued a number of times over these issues. 1 On the

final occasion when Alexander again requested Cote provide proof of insurance, Alexander removed

Free access — add to your briefcase to read the full text and ask questions with AI

Related

John Sweet II v. Carl E. Breivogel
2019 ME 18 (Supreme Judicial Court of Maine, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
Alexander v. Cote, Counsel Stack Legal Research, https://law.counselstack.com/opinion/alexander-v-cote-mesuperct-2022.