Bachelder's Construction v. Jo Ann Harris

CourtSuperior Court of Maine
DecidedDecember 12, 2023
DocketKENcv-18-158
StatusUnpublished

This text of Bachelder's Construction v. Jo Ann Harris (Bachelder's Construction v. Jo Ann Harris) is published on Counsel Stack Legal Research, covering Superior Court of Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bachelder's Construction v. Jo Ann Harris, (Me. Super. Ct. 2023).

Opinion

STATE OF MAINE SUPERIOR COURT KENNEBEC, ss. CIVIL ACTION DOCKET NO. CV-18-158

BACHELDER’S ) CONSTRUCTION, INC., ) Plaintiff,

V. DECISION AND ORDER JO ANN HARRIS, Defendant.

This case arises from allegations that Defendant Jo Ann Harris (“Harris”) failed to pay in full for renovations Plaintiff Bachelder’s Construction, Inc. (“Bachelder’s Construction”) made to her home. After trial, the court concludes that Bachelder’s Construction is entitled to recovery on a theory of quantum meruit and is entitled to statutory penalties, attorney fees, and costs under the prompt payment statute.

PROCEDURAL HISTORY

In a complaint filed on September 10, 2018, Bachelder’s Construction alleged claims of breach of contract (Count I), unjust enrichment (Count II), quantum meruit (Count ID, and violation of the prompt payment statute, 10 M.R.S. § 1111 et seq. (Count IV). The court conducted a bench trial on November 20, 2023, at which Bachelder’s Construction was represented by counsel and Harris represented

herself. The court received several exhibits in evidence and heard from three witnesses: (1) Walter Bachelder, Jr. (“‘Bachelder”), who is the owner of Bachelder’s Construction, (2) his son, also named Walter Bachelder, and (3) Harris.

FINDINGS OF FACT

Bachelder is an experienced contractor who has owned Bachelder’s Construction for more than 20 years. In 2017, Harris, who had recently moved to Fryeburg, contacted Bachelder by telephone to arrange for some minor renovations to her new home. The initial agreement was for Bachelder’s Construction to replace ten windows and a sliding door. Neither the scope of the work nor the agreed-upon cost was reduced to writing.!

On August 26, 2017, Harris gave Bachelder a check for $6,300, which Bachelder used to cover the cost of the new windows he purchased for the project. Shortly thereafter, Bachelder, assisted by his son and another employee, began work at Harris’s home. Upon starting the renovations, the men discovered rotted flooring and rim joists that needed to be replaced. Harris was present at the home and agreed to expand the scope of work to address the rot. She also agreed to Bachelder’s suggestion that he replace two additional doors and a small deck.

Again, no written contract was signed regarding these additional renovations.

1 Bachelder testified that he does not always prepare written contracts for residential construction jobs, but that he provided Harris with a written proposal before beginning the work. The plaintiff was unable to produce this initial proposal for trial, however. While the plaintiff did offer into evidence a document labeled “proposal” (admitted at trial as Plaintiffs Exhibit 2), the court finds, based on the date of the document and the work referenced therein, that Bachelder prepared this document as a bill after the agreed-upon work had been completed.

2 Bachelder’s Construction finished the agreed-upon renovations in about a week. Aside from some minor complaints about the crew’s cleanup efforts and a door latch that was installed upside down, Harris did not raise any concerns about the quality of the workmanship. Upon completion of the work, Bachelder informed Harris that she owed $11,089, which Bachelder had calculated as the total cost of the labor and materials less the $6,300 Harris already paid. To arrive at a final bill, Bachelder, consistent with industry standards, typically multiplies the price of materials by 2 or 2 % and then adds 10% to cover supplies.

On September 25, 2017, the day Bachelder’s Construction completed its work, Harris wrote a check for $11,089 as requested and gave it to Bachelder. Shortly thereafter, Harris spoke by telephone with her husband? about the costs of the renovations, and then called Bachelder to tell him that she was canceling the check as she believed the bill was too high. Two days later, Harris drove to Augusta and handed Bachelder a check for $1,700 marked with the words “Final Payment.” Harris believed that the $6,300 she paid previously covered the window installation, and that $1,700 was all that was owed for the extra work Bachelder’s Construction did to replace the deck and rotted materials. In fact, those two amounts together, totaling $8,000, would not even have covered the cost of materials Bachelder procured to complete the project, which was nearly $10,000. See Pl.’s Ex. 2.

Bachelder, furious that Harris had not paid him the requested amount, never

cashed the $1,700 check. This lawsuit followed.

? Harris and her husband were separated at the time and not living together. DISCUSSION

Bachelder’s Construction alleges that it is entitled to recover $11,089 for breach of contract (Count I), or the unjust enrichment conferred on Harris in the form of its labor and materials (Count II), or the reasonable value of its labor and materials in quantum meruit (Count III). The plaintiff also requests attorney fees, court costs, and $7,894.08 in statutory penalties under the Prompt Payment Act.

Bachelder’s Construction bears the burden of proving its claims by a preponderance of the evidence. Petit v. Key Bank of Maine, 688 A.2d 427, 431 (Me. 1996) (“We have long recognized and applied the general rule that a plaintiff's burden of proof in a civil action is to establish each factual element of a claim by a preponderance of the evidence.”).

A. Breach of Contract, Unjust Enrichment, and Quantum Meruit

The court finds that Bachelder’s Construction has not established the existence of a valid and enforceable contract, which requires “‘a meeting of the minds of the parties to the contract, i.e. a mutual assent to be bound by its terms... .” Sarchi v. Uber Techs., Inc., 2022 ME 8, § 15, 268 A.3d 258 (quoting Ouelletie v. Bolduc, 440 A.2d 1042, 1045 (Me. 1982)). The parties did not agree on

the specific cost of the renovations and never entered into a written agreement.’ See

3 However, the parties understood that the cost would exceed $3,000. The Home Construction Contracts Act (HCCA), 10 M.R.S. §§ 1486-1490, provides in pertinent part that a “home construction contract for more than $3,000 in materials or labor must be in writing,” id. § 1487, subject to civil penalties, id. § 1490. In this case, Harris did not bring a counterclaim alleging an HCCA violation. Sweet v. Breivogel, 2019 ME 18, ¥ 15, 201 A.3d 1215 (affirming Superior Court’s determination that no express contract was formed where “throughout the construction process, the parties held different understandings of the work to be performed and the total cost of the project’).

The lack of an enforceable contract does not end the analysis. Instead, Bachelder’s Construction is entitled to damages under a theory of quantum meruit, which “involve[s] recovery for services or materials provided under an implied contract, which is a contract inferred from the conduct of the parties.” Runnells v. Quinn, 2006 ME 7, { 10, 890 A.2d 718 (citing Paffhausen v. Balano, 1998 ME 47, {| 6, 708 A.2d 269)).4 “A valid claim in quantum meruit requires: that (1) services be rendered to the defendant by the plaintiff; (2) with the knowledge and consent of the defendant; and (3) under circumstances that make it reasonable for the plaintiff to expect payment.” Id. (quoting Paffhausen, 1998 ME 47, { 8, 708 A.2d 269).

ce

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Runnells v. Quinn
2006 ME 7 (Supreme Judicial Court of Maine, 2006)
Colvin v. Barrett
118 A.2d 775 (Supreme Judicial Court of Maine, 1955)
Cellar Dwellers, Inc. v. D'ALESSIO
2010 ME 32 (Supreme Judicial Court of Maine, 2010)
Jenkins, Inc. v. Walsh Bros., Inc.
2001 ME 98 (Supreme Judicial Court of Maine, 2001)
Paffhausen v. Balano
1998 ME 47 (Supreme Judicial Court of Maine, 1998)
Advanced Construction Corp. v. Pilecki
2006 ME 84 (Supreme Judicial Court of Maine, 2006)
Estate of White
521 A.2d 1180 (Supreme Judicial Court of Maine, 1987)
Ouellette v. Bolduc
440 A.2d 1042 (Supreme Judicial Court of Maine, 1982)
Petit v. Key Bank of Maine
688 A.2d 427 (Supreme Judicial Court of Maine, 1996)
John Sweet II v. Carl E. Breivogel
2019 ME 18 (Supreme Judicial Court of Maine, 2019)
Fortney & Weygandt, Inc. v. Lewiston DMEP IX, LLC
2019 ME 175 (Supreme Judicial Court of Maine, 2019)
Cummings v. Bean
2004 ME 93 (Supreme Judicial Court of Maine, 2004)
Fortney & Weygandt, Inc. v. Lewiston DMEP IX
2022 ME 5 (Supreme Judicial Court of Maine, 2022)
Patricia Sarchi v. Uber Technologies, Inc.
2022 ME 8 (Supreme Judicial Court of Maine, 2022)
Sweet v. Breivogel
201 A.3d 1215 (Supreme Judicial Court of Maine, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
Bachelder's Construction v. Jo Ann Harris, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bachelders-construction-v-jo-ann-harris-mesuperct-2023.