Sweet v. Breivogel

201 A.3d 1215
CourtSupreme Judicial Court of Maine
DecidedJanuary 29, 2019
DocketDocket: Han-18-196
StatusPublished
Cited by9 cases

This text of 201 A.3d 1215 (Sweet v. Breivogel) is published on Counsel Stack Legal Research, covering Supreme Judicial Court of Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sweet v. Breivogel, 201 A.3d 1215 (Me. 2019).

Opinion

HUMPHREY, J.

[¶1] In this appeal involving a dispute over payment for the construction of a traditional timber frame home, we consider the connection between the Home Construction Contracts Act (HCCA) and the Unfair Trade Practice Act (UTPA), take this opportunity to underscore the significance of the statutory requirement that construction contracts be formalized in writing, and affirm the judgment. See 5 M.R.S. § 213(1), (2) (2017) ; 10 M.R.S. §§ 1487, 1490 (2017).

I. BACKGROUND

[¶2] The following facts are drawn from the court's judgment and are supported by competent evidence in the record. See Gravison v. Fisher , 2016 ME 35, ¶ 3, 134 A.3d 857.

[¶3] John Sweet II is a sole proprietor who specializes in the construction of traditional timber frame homes, which involve a high level of labor, time, and craftmanship. In February 2013, Carl E. and Elizabeth A. Breivogel contacted Sweet through his construction-business website and inquired about building "an enclosed, [weathertight] frame home" on land they own on Mount Desert Island.

[¶4] In March 2013, the Breivogels traveled to Maine and met with Sweet at his self-constructed timber frame home. During that visit, the Breivogels viewed *1218Sweet's workshops as well as two other timber frame homes that Sweet had constructed. While the parties did not reach any agreements that day, Sweet did provide the Breivogels with some information about the relative costs of the homes they visited. Specifically, he told the Breivogels that it would cost approximately $ 500,000 to build a 28' x 30' completed home like his and $ 400,000 to construct the 32' x 32' home they visited that was little more than a "dried shell" or "weathertight" home.1

[¶5] After that meeting, the parties continued to communicate via email. In one exchange dated March 26, 2013, the parties began to discuss the costs associated with building a saltbox style2 timber frame home. The Breivogels asked Sweet whether it would be possible to build a home of this style for $ 275,000, not including the septic system for which the Breivogels would make other arrangements. Sweet responded that it was possible, but difficult to be certain at that early stage of the discussion because "the devil[']s in the details."

[¶6] From that point forward, the parties did not share the same understanding of the scope and cost of the work Sweet was to perform. Sweet believed that the Breivogels wanted him to construct an enclosed, weathertight timber frame home-including only a frame, walls, roof, insulation, doors, windows, chimney, and exterior shingles. In contrast, the Breivogels believed that they had requested a fully completed home, ready for occupancy, costing no more than $ 275,000.

[¶7] In April 2013, the Breivogels authorized Sweet to begin construction; however, the parties never signed a contract. When the Breivogels inquired when the parties would formalize the terms of the project, Sweet insisted that he had never signed a written contract in over thirty years of business. The parties did, however, arrange that the Breivogels would be billed biweekly and pay for all materials and any labor at $ 32 an hour.

[¶8] Sweet and his team began construction of a dried shell structure in the summer of 2013 and completed the work in December of that year. Throughout the project, Sweet sent numerous emails to the Breivogels containing photographs depicting the progress on their home. He also provided biweekly invoices; despite these frequent communications, however, Sweet's overall record-keeping process throughout the project was highly informal.

[¶9] After December, both parties understood that work on the home would progress beyond the dried shell phase. At that point, the Breivogels determined, without informing Sweet, that they would have Sweet continue to work on the project, but would initiate legal action against him after they obtained a certificate of occupancy. They intended to seek damages for payments made in excess of $ 275,000. The Breivogels continued to pay Sweet until May 4, 2014. Construction of the home was completed and the Breivogels *1219received their certificate of occupancy on May 15, 2014.

[¶10] In total, Sweet billed the Breivogels $ 602,250.98 for materials and services. The Breivogels had paid $ 601,195.75. After the Breivogels refused to tender any further payments, Sweet placed a $ 51,953.94 lien on the home for unpaid labor and brought this action against the Breivogels for that amount plus interest.3 The Breivogels asserted counterclaims for negligence, breach of contract, fraud, negligent misrepresentation, breach of the implied warranty of workmanship, and a violation of the UTPA.

[¶11] The Superior Court (Hancock County, R. Murray, J. ) concluded that Sweet was entitled to the money that he had already received from the Breivogels for the home under the theory of quantum meruit; however, the court also determined that Sweet had actually overcharged the Breivogels by $ 640.77 for the work performed by a tiler. With respect to the Breivogels' counterclaims, the court concluded that they failed to establish that Sweet was negligent, had breached any contractual obligation to perform in a workmanlike manner, or had breached any implied warranty relating to workmanship. It also determined that Sweet did not commit fraud or negligent misrepresentation. However, the court did find that Sweet violated the HCCA by failing to furnish a written contract, which was prima facie evidence of a UTPA violation.

[¶12] The Breivogels filed a motion for amended and additional findings of fact and conclusions of law. The court declined to amend the factual findings, but awarded the Breivogels $ 3,832.43 in costs and $ 30,000 in attorney fees as permitted by the UTPA. The Breivogels timely appealed. M.R. App. P. 2A(a), 2B(c).

II. DISCUSSION

[¶13] The Breivogels contend that the Superior Court erred in (1) determining that they did not meet their burden of proof as to their counterclaims for fraud, negligent misrepresentation, and breach of contract; (2) calculating the damages recoverable under the UTPA stemming from Sweet's violation of the HCCA; and (3) awarding an insufficient amount of attorney fees. We disagree and affirm the trial court's judgment in full.

A. The Breivogels' Counterclaims

[¶14] Because, at trial, the Breivogels had the burden of proof on each of their counterclaims and the Superior Court concluded that they failed to meet their burden, we must determine whether, on appeal, they have demonstrated that "a contrary finding is compelled by the evidence." Gravison, 2016 ME 35, ¶ 31, 134 A.3d 857 (quotation marks omitted); see also Young v. Lagasse , 2016 ME 96

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fair Friend Enterprise Co., Ltd. v. CNC Systems, Inc.
2025 ME 37 (Supreme Judicial Court of Maine, 2025)
Norton v. Norton
Maine Superior, 2023
Fortney & Weygandt, Inc. v. Lewiston DMEP IX
2022 ME 5 (Supreme Judicial Court of Maine, 2022)
Matthew Pollack v. Jessica Fournier
2020 ME 93 (Supreme Judicial Court of Maine, 2020)

Cite This Page — Counsel Stack

Bluebook (online)
201 A.3d 1215, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sweet-v-breivogel-me-2019.