Lowe v. SRT Custom Building, Inc.

CourtSuperior Court of Maine
DecidedApril 12, 2022
DocketCUMbcd-cv-21-48
StatusUnpublished

This text of Lowe v. SRT Custom Building, Inc. (Lowe v. SRT Custom Building, Inc.) is published on Counsel Stack Legal Research, covering Superior Court of Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lowe v. SRT Custom Building, Inc., (Me. Super. Ct. 2022).

Opinion

STATE OF MAINE BUSINESS AND CONSUMER COURT Cumberland, ss. LOCATION: Portland DOCKET NO: BCD-CIV-2021-00048

AMANDA LOWE, ) Plaintiff, ) ) v. ) JUDGMENT IN FAVOR OF ) DEFENDANTS FOLLOWING BENCH SRT CUSTOM BUILDING, INC., ) TRIAL JASON M. THERIAULT, and ) SHAWN R. THERIAULT, ) Defendants. )

This case is about a dispute between a homeowner and the construction company hired to

complete a large home renovation. Because the homeowner requested numerous change orders

the project ran out of funds, the homeowner refused to continue paying the builders, and the

builders stopped work on the project. The issues of liability and damages were bifurcated, and the

liability case was tried to the Bench on June 22, 2022. Plaintiff Amanda Lowe (“Lowe”) and

Defendant Shawn R. Theriault (“Theriault”) testified.

At the close of Lowe’s case, Defendants orally moved for a directed verdict. On the record,

the Court granted the motion in part 1 but denied it in part in respect to two counts: breach of

contract (Count I), and violation of Maine’s Unfair Trade Practices Act (Count VIII). As explained

on the record, the Court also declined to allow Lowe to pierce the corporate veil. For the reasons

1 The court granted Defendants’ motion for a directed verdict on the following counts: Breach of Expressed Warranties (Count II), Breach of Implied Warranties (Count III), Violations of the Home Constructions Contracts Act (Count IV); Constructions Contract (V), Conversion (VI), and Uniform Deceptive Trade Practices Act (VII).

1 discussed below, the Court determines Plaintiff has not satisfied her burden as to liability and the

Court grants judgment to Defendants on Counts I and VIII.

I. Findings of Facts

Based on the evidence adduced at trial, and drawing all reasonable inferences therefrom,

the Court makes the following findings of fact.

On June 16, 2020, Lowe entered into a written construction contract with Defendant SRT

Custom Building, Inc. (“SRT”) to complete a two-story addition off the back of her home in

Yarmouth, Maine. Paragraph nine (9) of the contract, Resolution of Disputes, was initialed, but

the parties failed to select whether disputes would be resolved by binding arbitration or by

mediation. SRT sent Lowe the contract expecting her to select an option, but she returned it without

doing so. The parties agreed to a contract price of $169,435.00 subject to any additional change

orders. Three written change orders were executed in writing, but as will be discussed below, Lowe

made many change orders not memorialized in writings.

Lowe’s home was originally a two-story Cape style home measuring about 900 square feet

total. After the two-story home addition, the home is closer to 2,000 square feet. The original

contract covered a master bedroom, a bathroom, a laundry room, a deck, a small room between

the deck and the main house, a crawl space, and one bedroom upstairs. The original contract did

not include any work on the interior or exterior work of the existing structure other than what was

required to complete the addition.

The scope of the project grew significantly beyond the initial contract due to Lowe making

numerous changes. Only three change orders, all of them modest, were memorialized in writing

by SRT. The unwritten, oral changes made by Lowe included tiling; new kitchen cabinets and

countertops; basement storage under the addition that required excavation of the basement storage

2 area, a concrete slab, and seven-foot foundation wall; plan modifications to account for an increase

in elevation of the addition caused by the basement storage area; and an increase in HVAC

throughout the home. Lowe also requested SRT change thirteen (13) white windows in the original

structure to match the black windows she selected for the addition. Changing the windows entailed

removing and reinstalling the external siding, removing the old windows, installing the new

windows, interior sheet rock, and adding the trim. While SRT had the siding off, SRT also needed

to address rot issues around the windows. The windows, old siding, and debris from replacing the

windows in the existing structure also increased the cost of the dumpster; the cost increase was not

considered in the original dumpster quote.

The kitchen Lowe added to the project went significantly overbudget due to Lowe’s

decisions and requests. When Lowe requested kitchen cabinets be installed, SRT quoted her and

made an allowance for one wall of seven prefabricated cabinets with formica-type countertops.

SRT sent Lowe to Hammond Lumber to purchase the cabinets with a blank check 2; however, Lowe

overspent on the cabinets by purchasing custom cabinets with an island. The costs of countertops

increased as well due to Lowe also selecting a higher quality counter and an increase for square

footage due to the addition of the island; she spent nearly double the allowed amount. Lowe stated

the overages were due to SRT not providing guidance on what she should buy; however, she was

aware of the allowance amounts.

Lowe and her husband demoed a brick chimney themselves; but in doing so, they tore

down a closet to gain access to it.3 This resulted in SRT having to repair the corner of the house

2 SRT provided Lowe with a blank check to purchase cabinets and another for counters due to the project not being far enough along for the bank to release money for those purchases but the orders needing to be submitted due to supply chain delays of 6-8 weeks between ordering and receiving the items. Lowe never refunded the amounts used to purchase the counters and cabinets, which amounted to about $5,000, despite the bank later releasing the funds. 3 Lowe and her husband also did the insulation work in the home.

3 effected by the chimney demo despite the work not being included in the original contract. The

additional cost of disposing of the brick in the dumpster was also not considered in the original

contract.

The project was further complicated due to a momentous change in Lowe’s living plans.

Originally, Lowe was going to be living with her mother during the construction. Lowe’s mother’s

home suffered a fire, so Lowe ended up living in the home during the construction. Lowe’s living

in the home changed the cost and timeline of the project due to SRT needing to keep the house

habitable every day. For the house to be habitable, SRT had to ensure the house was warm, had a

functional bathroom, and running utilities. To accommodate this, the bathroom on the remodel had

to be built first before demoing anything else in the home. Further Lowe’s occupancy of the home

also made demoing and building more difficult and costly. For example, SRT had to build a

temporary insulated back wall every night that had to be removed the next morning before

resuming work. SRT also had to install the kitchen cabinets three times. The first time was to allow

some plumbing work to be completed. The second installation was quickly done to allow Lowe to

host Christmas at the home. And the final time was to allow SRT to install the cabinets properly

after the quick holiday installation to ensure they were installed properly.

Tiling was also not included in the original contract but was added to the scope of the work

at Lowe’s request so there was no allowance for tiling in the contract. SRT originally expected to

prepare the floor by installing cerement boards and stiffening up the floor with structural supports.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Maine Energy Recovery Co. v. United Steel Structures, Inc.
1999 ME 31 (Supreme Judicial Court of Maine, 1999)
Wholesale Sand & Gravel, Inc. v. Decker
630 A.2d 710 (Supreme Judicial Court of Maine, 1993)
John Sweet II v. Carl E. Breivogel
2019 ME 18 (Supreme Judicial Court of Maine, 2019)
Sweet v. Breivogel
201 A.3d 1215 (Supreme Judicial Court of Maine, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
Lowe v. SRT Custom Building, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/lowe-v-srt-custom-building-inc-mesuperct-2022.