Cellar Dwellers, Inc. v. D'ALESSIO

2010 ME 32, 993 A.2d 1, 2010 Me. LEXIS 32, 2010 WL 1307477
CourtSupreme Judicial Court of Maine
DecidedApril 6, 2010
DocketDocket: Sag-09-298
StatusPublished
Cited by20 cases

This text of 2010 ME 32 (Cellar Dwellers, Inc. v. D'ALESSIO) is published on Counsel Stack Legal Research, covering Supreme Judicial Court of Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cellar Dwellers, Inc. v. D'ALESSIO, 2010 ME 32, 993 A.2d 1, 2010 Me. LEXIS 32, 2010 WL 1307477 (Me. 2010).

Opinion

JABAR, J.

[¶ 1] Dominic D’Alessio Jr. appeals from a judgment entered in the District Court (West Bath, Worth, J.) in favor of Cellar Dwellers, Inc. following a jury-waived trial on Cellar Dwellers’ claims for breach of contract, quasi-contract, unjust enrichment, and enforcement of a mechanic’s lien. In addition to awarding Cellar *3 Dwellers $6468.25 in damages, the court awarded penalties, prejudgment interest, and attorney fees pursuant to the prompt payment statute, see 10 M.R.S. §§ 1111— 1120 (2009). 1 D’Alessio argues that the court erred because: (1) no competent evidence supports the court’s finding that D’Alessio’s actions constituted a material breach discharging Cellar Dwellers’ contractual obligations; and (2) Cellar Dwellers was not entitled to penalties, interest, and attorney fees. 2 We affirm in part, vacate in part, and remand to the District Court for further proceedings.

I.BACKGROUND

[¶ 2] Cellar Dwellers, a Maine corporation, provides plumbing and heating services through its sole shareholder and president, James Peacock, a licensed master plumber and oil burner technician. In 2006, Cellar Dwellers entered into three contracts with D’Alessio to install plumbing and heating in D’Alessio’s new home in Brunswick.

A. The Contracts

1. Plumbing Contract

[¶ 3] In a written contract dated July 12, 2006, Cellar Dwellers agreed to install “Internal Plumbing” in D’Alessio’s home for $28,995. The contract noted that the price was “accurate within 10%,” and stated that payment would be rendered in three installments: $12,000 due at the “start of rough in”; $12,000 due at the “completion of the rough in”; and the remaining balance due upon “completion of [Cellar Dwellers’] work.”

2. Heating Contract

[¶ 4] In a second written contract dated October 6, 2006, Cellar Dwellers agreed to install a “Hot Water Baseboard Heating System” in D’Alessio’s home for $27,995. The contract described this price as “accurate within 5%,” and stated that payment would be rendered in three installments: $10,000 due at the “start of the job”; $10,000 due upon “piping out of boiler and tank”; and the remaining balance due upon “completion of [Cellar Dwellers’] work.”

3. Vacuum Contract

[¶ 5] In late 2006, Cellar Dwellers orally agreed to install a central vacuum system in D’Alessio’s home. Although the parties never specified the cost for this job in writing, D’Alessio agreed to pay Cellar Dwellers’ normal hourly rate.

B. Performance of the Contracts

[¶ 6] Cellar Dwellers began work on D’Alessio’s home in the fall of 2006. D’Al-essio timely paid Cellar Dwellers the $12,000 and $10,000 initial installments in accordance with the Plumbing and Heating Contracts. In November 2006, through a change order, D’Alessio requested significant changes to the Plumbing Contract, generating $17,464.85 in additional expenses. D’Alessio timely and fully paid for these costs, and Cellar Dwellers completed the work called for in the change order. D’Alessio also made a second timely payment pursuant to the Plumbing Contract, after Cellar Dwellers’ completion of the “rough in.” 3

*4 [¶ 7] On December 19, 2006, Cellar Dwellers finished “piping out” the boiler and tank, triggering payment of the second $10,000 Heating Contract installment. No payment was made until late January 2007, when D’Alessio presented Cellar Dwellers with a $5000 check and promised full payment in “a week or two.” Relying on this representation, Cellar Dwellers continued working and shortly thereafter received a second $5000 check. D’Alessio later instructed Cellar Dwellers not to cash the check, prompting Cellar Dwellers to stop working. Cellar Dwellers resumed work approximately two days later, assured by D’Alessio that the remaining $5000 would be forthcoming. Ultimately, D’Alessio paid $10,000 more, making a final $5000 payment on February 2, 2007. In total, Cellar Dwellers received $25,000 toward the Heating Contract, leaving a remaining balance of $2995 due upon completion of Cellar Dwellers’ work.

[¶ 8] On January 29, 2007, Cellar Dwellers properly installed the central vacuum system and billed D’Alessio $2478.35. D’Alessio has not made a payment for these services.

[¶ 9] Cellar Dwellers repeatedly told D’Alessio that work would cease unless he made payments. In late February 2007, before completing the basement plumbing and heating, Cellar Dwellers withdrew from the job site. At this point, the value of the services and materials not yet provided to D’Alessio totaled $3000. The plumbing and heating in the upstairs living area was completely finished and, as the District Court later found, had been done in a workmanlike manner. Although the work called for by the Plumbing and Heating Contracts had not been completed, Cellar Dwellers sent D’Alessio several invoices after stopping work. D’Alessio contacted Cellar Dwellers to ascertain the total cost to finish the basement heating and plumbing installation, but the parties were never able to reach an agreement to complete the project.

C. Litigation

[¶ 10] In early April 2007, Cellar Dwellers filed a mechanic’s lien against D’Ales-sio’s property. See 10 M.R.S. §§ 3251-3269 (2009). Thereafter, Cellar Dwellers filed a four-count complaint against D’Al-essio, claiming that it was entitled to enhanced damages pursuant to the prompt payment statute and alleging breach of contract, quasi-contract, unjust enrichment, and enforcement of the mechanic’s lien. In his answer, D’Alessio asserted several affirmative defenses and counterclaims for breach of contract, negligence, and violation of the Home Construction Contracts Act (HCCA), see 10 M.R.S. §§ 1486-1490(2009).

[¶ 11] A one-day trial was held in October 2008, after which the District Court entered a written judgment. The court found that the following “series of actions” by D’Alessio constituted a material breach of the parties’ contracts, justifying Cellar Dwellers’ departure from the job site before the plumbing and heating projects were completed:

[F]ailure to pay the second $10,000 heating contract installment upon “piping out the boiler and tank”; payment, when it did occur, in less than the full amount; payment with a non-negotiable check; use of the basement for storage despite Mr. Peacock’s objection and explanation; failure to pay for the central vacuum system within 20 days of invoice.

Contrary to D’Alessio’s arguments at trial, the court found that D’Alessio had no valid reason to withhold payment to Cellar Dwellers, and ruled against him on his counterclaims for breach of contract, negligence, and violation of the HCCA.

*5 [¶ 12] Regarding damages, the court awarded Cellar Dwellers contractual and equitable damages, as well as statutory remedies. Reasoning that D’Alessio owed Cellar Dwellers $9468.25, 4

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Untitled Case
D. Maine, 2026
Com. v. Saunder, S.
Superior Court of Pennsylvania, 2025
Fortney & Weygandt, Inc. v. Lewiston DMEP IX
2022 ME 5 (Supreme Judicial Court of Maine, 2022)
H&B Realty, LLC v. JJ Cars, LLC
2021 ME 14 (Supreme Judicial Court of Maine, 2021)
Maples v. Contorakes
Maine Superior, 2020
Fortney & Weygandt, Inc. v. Lewiston DMEP IX, LLC
2019 ME 175 (Supreme Judicial Court of Maine, 2019)
West v. Hussey
Maine Superior, 2019
Addison v. Daigle
Maine Superior, 2010

Cite This Page — Counsel Stack

Bluebook (online)
2010 ME 32, 993 A.2d 1, 2010 Me. LEXIS 32, 2010 WL 1307477, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cellar-dwellers-inc-v-dalessio-me-2010.