Addison v. Daigle
This text of Addison v. Daigle (Addison v. Daigle) is published on Counsel Stack Legal Research, covering Superior Court of Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
STATE OF MAINE SUPERIOR COURT PENOBSCOT, SS. CIVIL ACTION DOCKET NO CV-07-391 . p r;;,J - -, -.
MARY ADDISON,
Plaintiff, v. DECISION and JUDGMENT EUGENE DAIGLE,
Defendant.
Hearing was concluded and briefs filed by October 5, 2009. The plaintiff was
present and represented by counsel, Joseph Ferris, Esq., while the defendant was
present and represented by counsel, James Munch, Esq. The Court will address all
issues raised in the analysis that follows.
A. COUNT I
1. Existence of a Written Contract
This lawsuit arises from defendant's construction of a home for plaintiff in 2006.
Her prior residence had been destroyed by fire in March of 2006 and she explored
options to replace it. She found a set of plans for a new home that seemed suitable and
located a builder, Andy Samaras, owner of Hammer-All Home Improvement who
agreed to build the home according to the plans. He provided her with a proposal, Pl.'s
Ex. #3, that quoted a price of $173,430, and it contained certain terms and conditions
that had to be completed before specified payments were due. The homeowner was
required to provide site work, foundation, septic system, water-line to existing well,
cellar floor, and painting. The second floor was to be unfinished except for heat,
plumbing, and drywall. Included in the proposal was a list of allowances, as well as a
list of building materials and related costs. Unfortunately, Mr. Samaras chose to build another house instead of plaintiff's and Ms. Addison was faced with the prospect of
finding another builder, one who could complete the project by winter.
Ms. Addison worked at the University of Maine with the defendant, and spoke
with him frequently about the difficulties she had encountered in getting her house
built. She knew he worked as a computer systems administrator, but also was aware
that he bought and fixed properties and had construction knowledge. Mr. Daigle and
the plaintiff were friendly and he was concerned about her plight. Ms. Addison became
even more distressed after another potential builder backed out of the project and
eventually she and Mr. Daigle discussed whether he could provide assistance.
Although he was not a contractor, he was familiar with building procedures and
practices and knew an engineer, Mr. Manion, who could provide assistance. Defendant
indicated that he would consult with Mr. Manion and then decide whether he would
take on the project to assist the plaintiff. He eventually agreed to help.
Central to the Court's decision in this case is whether the terms of a construction
contract, Pl.'s Ex. #1, are binding on the parties. After agreeing to help, Mr. Daigle went
on-line to find a construction contract form and then proceeded to include the Samaras
contract terms in the new contract. Both agreements contained an agreement to build
the home according to the plans for $173,400 and included a similar schedule of
payments, and provided for an exclusion of foundation and site work from the contract.
The Samaras contract contained a list of allowances for certain expensive materials and
segments of construction such as drywall, plumbing, electrical, chimney, and the
homeowner was free to select materials within these allowances. The Daigle contract
had no list of allowances but specified that materials were to be specified by the
contractor and invoiced to the owner. Additionally, the Samaras contract provided that
the flooring would be the responsibility of the owner while flooring was included in the
2 Daigle contract. Both parties agree that the Daigle contract was based on the Samaras
contract.
As construction progressed, Ms. Addison needed to borrow funds from a bank to
complete the project. The bank required that she have a contract in order to obtain the
funds. She indicated this need to Mr. Daigle, which prompted him to draft the contract
described above. He obviously gave no independent thought to the cost of the project,
did not price materials, and performed no labor cost estimates, but just adopted Mr.
Samaris' conclusions in this regard. As the summer progressed without a loan
authorization, the plaintiff told the defendant that the bank needed a list of costs and
the parties jointly prepared construction cost worksheets. Def.'s Ex. #1,2,3, and 4 were
prepared for this purpose and Def. Ex. #2 was submitted to the bank. The costs on the
worksheet included costs such as foundation and site work that were not included in
the parties' contract, and the parties obviously manipulated the entries in various
categories in order for the entire project to come in at the target price of $189,500.
Plaintiff asserts that the parties' obligations with regard to the construction of her
home are defined in the written contract dated June 20, 2010. Plaintiff also argues that
the parole evidence rule excludes consideration of extrinsic evidence offered to change
the terms of the written contract. In reply, the defendant argues that extrinsic evidence
is admissible to prove that the parties did not intend to be bound by the written
contract, which was only prepared because the bank that originated the construction
loan required that the parties have a contract. The Court agrees that parol evidence is
not admissible to vary, add to, or contradict the terms of an integrated written contract.
Clark v. DiPietro, 525 A.2d 623, 625 (Me. 1987). If the agreement is partially integrated,
extrinsic evidence will be admissible if the additional terms are consistent with the
written terms. Rogers v. Jackson, 2002 ME 140, 3 does not appear to be decided in Maine, the Court is also willing to rule that extrinsic evidence is admissible on the issue of whether the parties intended to be bound by the terms of a written contract. See, Am. Jur. 2nd Evidence § 1120; Corbin on Contracts § 85.19; Zamore v. Whitten, 395 A.2d 435, 440 (Me. 1998). After reviewing the evidence admitted at hearing, the Court concludes that the parties intended to be bound by the June 20,2010 agreement. At the time of the agreement, the parties had been discussing the difficulties plaintiff had encountered in having her home built. The defendant agreed to be responsible for the construction of the home in order to help a friend. Since he wasn't a contractor, he went to the internet to download a form contract and then incorporated the Samaris terms into the form contract. Once he was assured of Manion's assistance, he expressed confidence that he could build a better home than Samaris and felt Samaris' price may have been high. Defendant knew plaintiff needed a contract in order to obtain a loan from the bank and assisted in this regard, but there is no indication that this was the sole reason for the contract to be drafted. There was absolutely no clear, unequivocal agreement between the parties that the written contract was for financing purposes only and not to be enforced. In the absence of an overt agreement that the written contract would not be enforceable, it is difficult to believe that the defendant, an
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
Addison v. Daigle, Counsel Stack Legal Research, https://law.counselstack.com/opinion/addison-v-daigle-mesuperct-2010.