Addison v. Daigle

CourtSuperior Court of Maine
DecidedJuly 30, 2010
DocketPENcv-07-391
StatusUnpublished

This text of Addison v. Daigle (Addison v. Daigle) is published on Counsel Stack Legal Research, covering Superior Court of Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Addison v. Daigle, (Me. Super. Ct. 2010).

Opinion

STATE OF MAINE SUPERIOR COURT PENOBSCOT, SS. CIVIL ACTION DOCKET NO CV-07-391 . p r;;,J - -, -.

MARY ADDISON,

Plaintiff, v. DECISION and JUDGMENT EUGENE DAIGLE,

Defendant.

Hearing was concluded and briefs filed by October 5, 2009. The plaintiff was

present and represented by counsel, Joseph Ferris, Esq., while the defendant was

present and represented by counsel, James Munch, Esq. The Court will address all

issues raised in the analysis that follows.

A. COUNT I

1. Existence of a Written Contract

This lawsuit arises from defendant's construction of a home for plaintiff in 2006.

Her prior residence had been destroyed by fire in March of 2006 and she explored

options to replace it. She found a set of plans for a new home that seemed suitable and

located a builder, Andy Samaras, owner of Hammer-All Home Improvement who

agreed to build the home according to the plans. He provided her with a proposal, Pl.'s

Ex. #3, that quoted a price of $173,430, and it contained certain terms and conditions

that had to be completed before specified payments were due. The homeowner was

required to provide site work, foundation, septic system, water-line to existing well,

cellar floor, and painting. The second floor was to be unfinished except for heat,

plumbing, and drywall. Included in the proposal was a list of allowances, as well as a

list of building materials and related costs. Unfortunately, Mr. Samaras chose to build another house instead of plaintiff's and Ms. Addison was faced with the prospect of

finding another builder, one who could complete the project by winter.

Ms. Addison worked at the University of Maine with the defendant, and spoke

with him frequently about the difficulties she had encountered in getting her house

built. She knew he worked as a computer systems administrator, but also was aware

that he bought and fixed properties and had construction knowledge. Mr. Daigle and

the plaintiff were friendly and he was concerned about her plight. Ms. Addison became

even more distressed after another potential builder backed out of the project and

eventually she and Mr. Daigle discussed whether he could provide assistance.

Although he was not a contractor, he was familiar with building procedures and

practices and knew an engineer, Mr. Manion, who could provide assistance. Defendant

indicated that he would consult with Mr. Manion and then decide whether he would

take on the project to assist the plaintiff. He eventually agreed to help.

Central to the Court's decision in this case is whether the terms of a construction

contract, Pl.'s Ex. #1, are binding on the parties. After agreeing to help, Mr. Daigle went

on-line to find a construction contract form and then proceeded to include the Samaras

contract terms in the new contract. Both agreements contained an agreement to build

the home according to the plans for $173,400 and included a similar schedule of

payments, and provided for an exclusion of foundation and site work from the contract.

The Samaras contract contained a list of allowances for certain expensive materials and

segments of construction such as drywall, plumbing, electrical, chimney, and the

homeowner was free to select materials within these allowances. The Daigle contract

had no list of allowances but specified that materials were to be specified by the

contractor and invoiced to the owner. Additionally, the Samaras contract provided that

the flooring would be the responsibility of the owner while flooring was included in the

2 Daigle contract. Both parties agree that the Daigle contract was based on the Samaras

contract.

As construction progressed, Ms. Addison needed to borrow funds from a bank to

complete the project. The bank required that she have a contract in order to obtain the

funds. She indicated this need to Mr. Daigle, which prompted him to draft the contract

described above. He obviously gave no independent thought to the cost of the project,

did not price materials, and performed no labor cost estimates, but just adopted Mr.

Samaris' conclusions in this regard. As the summer progressed without a loan

authorization, the plaintiff told the defendant that the bank needed a list of costs and

the parties jointly prepared construction cost worksheets. Def.'s Ex. #1,2,3, and 4 were

prepared for this purpose and Def. Ex. #2 was submitted to the bank. The costs on the

worksheet included costs such as foundation and site work that were not included in

the parties' contract, and the parties obviously manipulated the entries in various

categories in order for the entire project to come in at the target price of $189,500.

Plaintiff asserts that the parties' obligations with regard to the construction of her

home are defined in the written contract dated June 20, 2010. Plaintiff also argues that

the parole evidence rule excludes consideration of extrinsic evidence offered to change

the terms of the written contract. In reply, the defendant argues that extrinsic evidence

is admissible to prove that the parties did not intend to be bound by the written

contract, which was only prepared because the bank that originated the construction

loan required that the parties have a contract. The Court agrees that parol evidence is

not admissible to vary, add to, or contradict the terms of an integrated written contract.

Clark v. DiPietro, 525 A.2d 623, 625 (Me. 1987). If the agreement is partially integrated,

extrinsic evidence will be admissible if the additional terms are consistent with the

written terms. Rogers v. Jackson, 2002 ME 140,

3 does not appear to be decided in Maine, the Court is also willing to rule that extrinsic

evidence is admissible on the issue of whether the parties intended to be bound by the

terms of a written contract. See, Am. Jur. 2nd Evidence § 1120; Corbin on Contracts §

85.19; Zamore v. Whitten, 395 A.2d 435, 440 (Me. 1998). After reviewing the evidence

admitted at hearing, the Court concludes that the parties intended to be bound by the

June 20,2010 agreement.

At the time of the agreement, the parties had been discussing the difficulties

plaintiff had encountered in having her home built. The defendant agreed to be

responsible for the construction of the home in order to help a friend. Since he wasn't a

contractor, he went to the internet to download a form contract and then incorporated

the Samaris terms into the form contract. Once he was assured of Manion's assistance,

he expressed confidence that he could build a better home than Samaris and felt

Samaris' price may have been high. Defendant knew plaintiff needed a contract in order

to obtain a loan from the bank and assisted in this regard, but there is no indication that

this was the sole reason for the contract to be drafted. There was absolutely no clear,

unequivocal agreement between the parties that the written contract was for financing

purposes only and not to be enforced. In the absence of an overt agreement that the

written contract would not be enforceable, it is difficult to believe that the defendant, an

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Zamore v. Whitten
395 A.2d 435 (Supreme Judicial Court of Maine, 1978)
Cellar Dwellers, Inc. v. D'ALESSIO
2010 ME 32 (Supreme Judicial Court of Maine, 2010)
Rockland Poultry Co. v. Anderson
91 A.2d 478 (Supreme Judicial Court of Maine, 1952)
Rogers v. Jackson
2002 ME 140 (Supreme Judicial Court of Maine, 2002)
Clarke v. DiPietro
525 A.2d 623 (Supreme Judicial Court of Maine, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
Addison v. Daigle, Counsel Stack Legal Research, https://law.counselstack.com/opinion/addison-v-daigle-mesuperct-2010.