Kleinschmidt v. Morrow

642 A.2d 161, 1994 Me. LEXIS 154
CourtSupreme Judicial Court of Maine
DecidedMay 18, 1994
StatusPublished
Cited by16 cases

This text of 642 A.2d 161 (Kleinschmidt v. Morrow) is published on Counsel Stack Legal Research, covering Supreme Judicial Court of Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kleinschmidt v. Morrow, 642 A.2d 161, 1994 Me. LEXIS 154 (Me. 1994).

Opinion

GLASSMAN, Justice.

Maurice Morrow, d/b/a Maurice Morrow Construction, appeals and Hazel A. Kleinsehmidt cross-appeals from the entry of a judgment after a jury-waived trial in the Superior Court (Lincoln County, Perkins, J.) awarding compensatory damages to Kleinsehmidt on her complaint against Morrow. Morrow contends that the trial court erred in refusing to issue further findings of fact and conclusions of law and the evidence does not support the damages assessed against him. 1 By her cross-appeal, Kleinseh-midt contends that the trial court erred in refusing to award punitive damages to her on her claim for abuse of process and in refusing to grant her attorney fees pursuant to the Maine Unfair Trade Practices Act *163 (UTPA), 5 M.R.S.A. §§ 205-A to 214 (1989). For the reasons set forth herein we affirm the judgment.

I.

Based on the evidence, the trial court could have found the following facts: On April 6, 1989, the parties entered into a contract that provided Morrow would construct a new house adjacent to and on the same property as Kleinschmidt’s existing house in Jefferson at a cost of $68,200. The contract acknowledged the receipt by Morrow of a $20,000 deposit and recited that the balance was “to be paid when house is sold or other arrang-ments [sic] are made.” Although the contract did not state the completion date, Morrow told Kleinschmidt that it would take between two and three months to build a house.

In April 1989 Morrow began construction of the new home. By June 1989 Morrow had completed approximately one-half of the work and had depleted the $20,000 deposit. Despite the fact that the contract made no provision for progress payments, Morrow refused to perform further work on the new house until he received further payment. Because Morrow told her that it was important to get the windows and siding installed, Kleinschmidt paid an additional $2000 to Morrow for this work. When Morrow again requested further payment, Kleinschmidt refused and hired her own electrician to perform necessary electrical work. When the construction work ceased in late July or early August of 1989, the house was still not completed. On inquiry by Kleinschmidt to determine when Morrow was going to complete the house, Morrow stated that he would resume work on the house when Kleinschmidt obtained more money. Kleinschmidt contacted Morrow again in August 1989 to discuss completion of the roof, but Morrow stated, “I do not want anything more to do with the house, that’s it, I am all done working for you.”

In January 1990 Kleinschmidt had an opportunity to sell her old house, and after receiving a down payment on the purchase price, she contacted Morrow to request that he finish the new house. Morrow again refused. The sale of the old house did not materialize because the new house remained unfinished. Kleinschmidt contacted another contractor, Lawrence Terrio, to discuss completion of the new house. After examining the site, Terrio discovered numerous defects in Morrow’s workmanship. According to Terrio, because of defects in the placement and quality of trusses, rafters, and studs, it would be necessary to “gut” the house and redo the work. Terrio estimated that the cost of completing the house according to the original plans would be $47,500.

On April 11, 1990, Morrow filed a statement of lien in the Registry of Deeds, claiming a lien on both the new and the old house. Although he had received full payment for all labor and materials furnished by him, Morrow claimed a lien for an outstanding balance for work performed in the amount of $48,200 and misrepresented the date on which services were last performed. His stated purpose for filing the lien was to encumber Kleinsch-midt’s title so that he could get paid, to prevent Kleinschmidt from getting anyone else to work on the house, and to prevent the sale of the old house. Although Morrow received a letter from Kleinsehmidt’s counsel requesting that the lien be released, Morrow took no action to perfect or release the lien. In October 1991 and again in April 1992, Kleinsehmidt’s applications for financing to complete the new house were rejected because of the statement of lien filed by Morrow.

II.

Kleinschmidt filed the instant action in the District Court (Wiscasset) seeking compensatory damages for Morrow’s alleged breach of the construction contract and compensatory and punitive damages for Morrow’s alleged abuse of process. For Morrow’s alleged violation of the UTPA, she sought an injunctive order requiring Morrow to file a notice of release of the lien and payment of her attorney fees. After the matter was removed to the Superior Court, Morrow’s counterclaim seeking damages for Kleinschmidt’s alleged breach of the construction contract was dismissed with prejudice as a sanction for Morrow’s failure to comply with the court’s order *164 relating to discovery. Following a jury-waived trial, the court awarded to Kleinsch-midt $2300 in compensatory damages on her claim for Morrow’s breach of contract, $8000 in compensatory damages on her claim for his abuse of process and declared the lien filed by Morrow to be null and void. The court found that Kleinschmidt was not entitled to punitive damages for Morrow’s abuse of process and held that she was not entitled to recover her attorney fees pursuant to the UTPA because Kleinschmidt did not suffer a “loss” within the meaning of 6 M.R.S.A. § 213 (1989). Morrow’s motion for findings of fact and conclusions of law was denied. From the judgment entered accordingly, Morrow appeals and Kleinschmidt cross-appeals.

III.

At the outset, we reject Morrow’s contention that the trial court improperly denied Morrow’s motion for findings of fact and conclusions of law. The trial court issued a six-page decision that includes detailed factual findings and conclusions of law. When, as here, a trial court’s findings of fact and conclusions of law appear within the court’s decision, the court need not grant a request for findings of fact and conclusions of law. Bayley v. Bayley, 602 A.2d 1152, 1153 (Me.1992); see also M.R.Civ.P. 52. Moreover, we note that Morrow did not move for specific findings of fact and conclusions of law. See Murray v. Murray, 529 A.2d 1366, 1368, n. 1 (Me.1987) (“It is ... incumbent on litigants to move for specific findings of fact and conclusions of law in those cases in which the development of the facts and statement of the rationale is ... not sufficiently developed in, the court’s decision.” (Emphasis added)).

Morrow next contends because he did not perfect the lien in accordance with 10 M.R.S.A. § 3255(1) (Supp.1993) 2 the filing of a statement of lien could not result in damages to Kleinschmidt. 3 We disagree. The tort of abuse of process requires “use of the process in a manner not proper in the regular conduct of the proceedings_” Nadeau v. State, 395 A.2d 107, 117 (Me.1978) (emphasis added).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jennifer Roussel v. Sheldon Ashby
2015 ME 43 (Supreme Judicial Court of Maine, 2015)
Barriault v. Nevens
Maine Superior, 2009
Treadwell v. J.D. Construction Co.
2007 ME 150 (Supreme Judicial Court of Maine, 2007)
Downeast Ventures, Ltd. v. Washington County
450 F. Supp. 2d 106 (D. Maine, 2006)
Advanced Construction Corp. v. Pilecki
2006 ME 84 (Supreme Judicial Court of Maine, 2006)
Wharton v. Tri-State Drilling & Boring
2003 VT 19 (Supreme Court of Vermont, 2003)
Lee v. Surrette
Maine Superior, 2002
Brace v. Titcomb
Maine Superior, 2002
McTeague v. Department of Transportation
2000 ME 183 (Supreme Judicial Court of Maine, 2000)
Wachter v. Gratech Co., Ltd.
2000 ND 62 (North Dakota Supreme Court, 2000)
Tanguay v. Asen
1998 ME 277 (Supreme Judicial Court of Maine, 1998)
VanVoorhees v. Dodge
679 A.2d 1077 (Supreme Judicial Court of Maine, 1996)
Mariello v. Giguere
667 A.2d 588 (Supreme Judicial Court of Maine, 1995)
Dudley v. Wyler
647 A.2d 90 (Supreme Judicial Court of Maine, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
642 A.2d 161, 1994 Me. LEXIS 154, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kleinschmidt-v-morrow-me-1994.