Brace v. Titcomb

CourtSuperior Court of Maine
DecidedMay 17, 2002
DocketCUMre-00-038
StatusUnpublished

This text of Brace v. Titcomb (Brace v. Titcomb) is published on Counsel Stack Legal Research, covering Superior Court of Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brace v. Titcomb, (Me. Super. Ct. 2002).

Opinion

STATE OF MAINE ~) 5 SUPERIOR COURT CUMBERLAND, SS. oS CIVIL ACTION \y

oo Docket No. RE-00-038 , TEH-CUM- ©. i7 2 00R

DONALD L. GARBRECHT LAW LISRARY

‘eau , Oya Ll lai. oad dil

RICHARD W. BRACE, ET AL,1

RUUN 2°27 2002 Plaintiffs

vs. DECISION AND ORDER

G. FREDERICK TITCOMB, ET AL,

Defendants

The defendant G. Frederick Titcomb, Inc. ("Titcomb-Corp") is a closely held corporation that provides general contracting services for the construction, renovation and remodeling of buildings. The defendant G. Frederick Titcomb ("Frederick") is its sole shareholder, officer and employee.

In 1989, the plaintiffs Richard and Cheryl Brace purchased lakefront nroperty on Basswood Bay Road, Harrison, Maine. The property included a

summer home with exterior dimensions of approximately 26' by 36’.

1This case was originally styled as Hancock Lumber Company, Inc., v. G. Frederick Titcomb. Pursuant to the stipulations of the parties, all of the claims of the original plaintiff Hancock Lumber Company, Inc., have been dismissed without prejudice. As a result, both Hancock Lumber and Norway Savings Bank are no longer parties in this action.

The trial proceeded on the cross claims of the defendants Brace and Titcomb against each other. Simply for ease of identification throughout the trial and in this Judgment, Richard W. Brace and Cheryl M. Brace are designated and referred to as the plaintiffs and G. Frederick Titcomb and G. Frederick Titcomb, Inc., are designated « d referred to as the defendants. In July 1999, Richard Brace first contacted Frederick about doing renovation and expansion work on the Braces's summer home. They had several discussions during which Frederick said that he would be personally on the job site and that his company would stand behind its work. In September 1999, the parties entered into a written contract for the renovation and substantial expansion of the home. The agreement was

drafted by Frederick on the stationery of Titcomb-Corp and identified Cheryl

Ezace as the "customer"? and Titcomb-Corp as the "contractor." After adjusting for credits and unused allowances, the contractor agreed to provide the necessary labor and materials for a total fixed price of $144,250. In addition, the contractor provided extra items that were not part of the underlying contract for an additional $5,300: a half bathroom (plumbing not included)($1,600); a roof extension for the entry deck ($350); a Salt Box generator and storage building ($3,000); and two triangle louvers ($350). “ke Braces obtained a construction loan from Norway Savings Bank and agreed to pay the contractor pursuant to a progress or draw payment schedule set forth in the contract.

Between September 7, 1999, and January 11, 2000, the contractor submitted four draw requests totalling $125,693. Mr. Brace became

increasingly concerned that each draw request did not fully conform to the

2At trial, the parties acknowledged that, in fact, the “customer” was Cheryl and Richard Brace. contract requirements and included work that had not been done.* He was also concerned about construction defects and the quality of the contractor's work. Frederick did the electrical work for the house even though he was not licensed to do so. As a result, an electrician hired by the Braces to run _ electrical service to the house refused to tie into the work done by Frederick.4 There were other contract nonconformities and defects with respect to the J-beam floor joists and perimeter joists, sub-flooring, the bead-board cathedral ceiling in the great room (kitchen/living room), half- walls in the kitchen, the exterior porches or decks, elevations of the new foundation flooring, the seal or bond at the joint between the new and existing foundations, the use of steel fascias instead of aluminum as required ‘ay the contract, glass sliding door and windows in the basement, drainage, chimney refacing, lack of headers for load bearing walls, and the wrong color bay window.®

In mid-January 2000, the Braces were informed that a major material supplier, Hancock Lumber, had not been paid by the contractor and intended to place a mechanics’ lien on their property. On February 9, 2000,

the supplier's attorney notified the Braces that the lien had been recorded

3The second draw request included items totalling $2,000 that had been paid as part of the first request. The third included items not yet completed: i.e., installation of porch, entry decks and framing; rough wiring; and excavation. The fourth requested more than the amount allowed by the contract and included electrical wiring personally done by Frederick, who was not licensed to do such work.

4Frederick Titcomb was criminally charged and convicted in connection with the electrical work done by him, and the Maine State Electrical Inspector ordered that his work be corrected by a licensed electrician.

5The correct replacement bay window was delivered to the site, but not installed, at the time the contract was terminated by the Braces in February 2000.

3 on the land records.® As a result, Norway Savings Bank froze further 2isbursement of the construction loan proceeds. On February 16, 2000, the Braces notified the contractor by letter that they were terminating the contract. As of that date, the Braces's total payments to the contractor were $78,748 and the contractor's total expenditures for the project were $90,000.

The Braces then hired a new contractor, D.C. Building & Remodeling

("D.C. B&R"), to repair the defects and finish the work contemplated by the -omtract.’ The new contractor completed the work on a "time and materials" basis by December 18, 2000,®° and was paid $130,686.30 by the Braces.2 Of this sum, $17,320.59 is not attributable to repairing or finishing the original contract work and should not be included.!° Accordingly, the court finds that, in addition to the sums already paid to Titcomb-Corp, it cost the Braces $113,365.71 to repair the defective work and complete the

project.

6Hancock Lumber subsequently sued the Braces on its lien claim and was the original plaintiff in this action. As previously noted, Hancock is no longer a party in this case.

7The principals of D.C. B&R were Mike Dean and John Courteau.

8After December 18, 2000, D.C. R&B did additional work not related to the subject matter of this case.

9Although not conceding liability or the validity of their respective legal and factual arguments, the parties have agreed that, in its analysis of the claims in this ease, the court may consider the summary figures set forth in Attorney Vickerson's istter to the court, dated March 18, 2002, without having to undertake additional analysis concerning the composition of those figures.

10Charges for labor ($1,760), fireplace ($3,960.59), tree removal ($1,600), and landscaping ($10,000) are excluded. The Braces assert claims!! against the defendants for breach of contract (Count I), breach of warranty (Count II), violation of the Home Construction Contract Act (Count III), violation of the Unfair Trade Practices Act (Count IV), and slander of title (Count V).!2_ Correspondingly, the defendants assert claims against the Braces for violation of the Prompt Payment Act (Count J), unjust enrichment (Count I), mechanics’ lien (Count III), and contribution (Count IV).*?

DISCUSSION

A Breach of Contract

Based upon the foregoing, the court finds that the contractor breached the contract and that the Braces paid a total of $192,113.71 for a result that the contractor agreed to provide for a fixed contract price of $144,250, plus exira items totalling $5,300. Accordingly, the Braces have been damaged in the amount of $42,563.71. See VanVoorhees v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Placzek
380 A.2d 1010 (Supreme Judicial Court of Maine, 1977)
VanVoorhees v. Dodge
679 A.2d 1077 (Supreme Judicial Court of Maine, 1996)
Kleinschmidt v. Morrow
642 A.2d 161 (Supreme Judicial Court of Maine, 1994)
Beaulieu v. Dorsey
562 A.2d 678 (Supreme Judicial Court of Maine, 1989)
Suminski v. Maine Appliance Warehouse, Inc.
602 A.2d 1173 (Supreme Judicial Court of Maine, 1992)
Johnson v. Exclusive Properties Unlimited
1998 ME 244 (Supreme Judicial Court of Maine, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
Brace v. Titcomb, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brace-v-titcomb-mesuperct-2002.