Lee v. Surrette
This text of Lee v. Surrette (Lee v. Surrette) is published on Counsel Stack Legal Research, covering Superior Court of Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
SIATE OF MAINE
CUMBER| AND, SS STATE OF MAINE CUMBERLAND: & SUPERIOR COURT CUMBERLAND, SS. —* CIVIL ACTION
. Docket No. RE-01-05 ioe SEP 20 P23 Fee lem 44 Foon
FREDDIE E. LEE,
Plaintiff VS. DECISION AND ORDER DONALD L. GARBRECHT DONALD SURRETTE LAW LIBRARY dba Bridgton Apartments, Defendant OCT 4 2002
The plaintiff owns and operates an excavation business. The defendant -- owns and operates an apartment complex in Bridgton, Maine known as Bridgton Apartments.
On April 23, 2001 the parties entered into an oral agreement pursuant to which the plaintiff was to do excavation work around Building Number One of the complex to divert rain and runoff water, and correct defects in and expand the parking lot serving that building.! In return, the defendant agreed to pay the plaintiff on a time-basis at the rate'‘of $35 per hour.?
The plaintiff began the job on April 24, 2001, using a bulldozer and a
backhoe. The plaintiff submitted bills to the defendant totalling $831.25:
1The plaintiff also did work around Building Number Three. However, that work and the plaintiff's related billing are not the subject of this litigation.
*There was some disagreement between the parties as to whether their contract included an exception of some sort in the event ledge was discovered during the course ot the work. The court finds that there was no such exception in the agreement and, in any event, is satisfied from the evidence that no ledge was encountered at the job site.
1 one for $813.75 reflecting 23.25 hours of work done through April 27th, and another in the amount of $17.50 for one-half hour's work on April 30th.? Defendant's Exhs. 3 & 4. In the performance of the work, the plaintiff left permanent track marks from his heavy equipment embedded in the asphalt driveway, cut a ditch 8" deep across the entrance to the parking lot which drained surface water in the wrong direction, and placed a large boulder in the middle of the parking lot which reduced the number of parking spaces from five to two.
By letter dated April 30, 2001, the defendant advised the plaintiff that he was not satisfied with the quality of the plaintiffs "workmanship" and was withholding payment of his bills until the problems in the parking area were fixed. Defendant's Exh. 5. The defendant also indicated that he was hiring another contractor to "correct" the plaintiffs work. Id. In response, the plaintiff stopped working and the oral contract was effectively terminated by the parties as of the date of the defendant's letter. When the plaintiff stopped working, the parking lot was left in a muddy and generally unusable condition.
The defendant hired JK Maintenance ("JK") to correct and complete the plaintiffs work. JK charged $1,600 to excavate and haul material from the premises, move the boulder in the parking lot, dig out the surrounding
bank area and use existing rocks to make a retaining wall, install a swail to
3The latter invoice also reflects charges totalling $125 for transporting equipment to and from the job site. However, these charges are not allowed by the court since the parties' oral agreement only contemplated an hourly billing for excavation services rendered. divert surface water, relevel the driveway, and bring in 12 yards of gravel compacting material. Defendant's Exhs. 6.4 Of this sum, $400 is
attributable to correcting the plaintiffs work.®
The plaintiff asserts a mechanics lien claim for the amount of his unpaid invoices. Correspondingly, the defendant counterclaims against the plaintiff for breach of contract (Count I) and negligence (Count IV).
DISCUSSION
The court finds that there was a contract between the parties, that the plaintiffs performance under the agreement was defective, and that, as a result of the plaintiffs negligence, the parking lot was rendered substantially unusable and surface water was improperly drained. A contractor has a duty to perform in a workmanlike manner, and can be liable fot negligence in the performance of his contractual obligations. Paine v. Spottiswoode, 612 A.2d 235, 238-39 (Me. 1992). Based upon the foregoing, the court finds that the defendant has been damaged in the amount of $400, being the cost incurred to have JK repair the defective work. See Van voorhees v. Dodge, 679 A.2d 1077, 1081 (Me. 1996); see also Kleinschmidt v. Morrow, 642 A.2d 161,
165 (Me. 1994). "[The] measure of recovery for incomplete or defective
4The defendant also paid JK $873.80 for additional work. These charges are not related to the subject matter of this litigation and are not allowed as damages in this case.
Further, the defendant paid JK and Technical Services, Inc., a total of $389.38 to determine whether the plaintiff had caused any damage to the septic system of the apartment complex. No damage was found and these charges are also not allowed.
5Jack Kostka, the owner of JK, testified credibly that, if his company had been hired to do the original work from the outset of the project, it would have only charged the defendant $1,200. work [is] 'the amount reasonably required to remedy the defect' as specifically measured by the actual cost of repair." Anuszewski v. Jurevic, 566 A.2d 742, 744 (Me. 1989). As a result, after allowing for the costs incurred by the defendant for correcting the plaintiffs work, the amount owed by the defendant to the plaintiff, and for which the plaintiff is entitled to a lien, is $431.25. 10 M.R.S.A. § 3251; Pond Cove Millwork Co. v. Steeves, 598 A.2d 1181, 1182 (Me. 1991) (the amount owed to a contractor "may be subject to deductions or setoffs ... for expenses incurred or damages sustained" by the owner to remedy the contractor's defective performance). DECISION
Based upon the foregoing, and pursuant to M.R. Civ. P. 79(a), the Clerk
is directed to enter this Decision and Order on the Civil Docket by a
notation incorporating it by reference and the entry is
A. On Defendant's Counterclaims, Judgment for Defendant in the amount of $400, which is allowed as a setoff against Plaintiff's claim;
B. On Plaintiffs Complaint, after allowance for the damages awarded to
Defendant on his Counterclaims, Judgment for Plaintiff in the net amount of $431.25; and
C. Neither party is allowed costs in this action.
Dated: September 19, 2002 NO
Justice, Superior Court
Date Filed __05-24-01 Cumberland
Docket No. __ RE-01-52
County
Action __Real Estate Mechanics Liens
Freddie F.Lee d/b/a The Earthmover
Donald Surrette d/b/a Bridgton Apartments
Plaintiffs Attorney
Freddie F. Lee RR # 1 Box 498 Bridgton, Maine 04009
Defendant’s Attorney
12 SANDY LANE
SALISBURY, MA 01952 DAVID PIERSON, ESQ 777-4600 PO BOX 7120 LEWISTON, ME 04243
Date of Entry 2001 May 25 Received 05-24-01 Summary Sheet filed. Complaint with Exhibit's A ~ C filed. June 12 | Received 6-12-01: Defendants Answer to Complaint filed. June 13 Received 06-13-01: Affidavit of Donald Surrette filed. June 15 Received 06-15-01: Summons filed showing officer's return of service on June 4, 2001 upon Defendant, Donald Surrette. Jun. 27 Received 06-27-01: Scheduling Order filed. (Humphrey, J.). Scheduling Order filed. Discovery deadline is February 27, 2002.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
Lee v. Surrette, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lee-v-surrette-mesuperct-2002.