US f/u/b of Modern Mosaic, Ltd v. Turner Construction Company

946 F.3d 201
Court of Appeals for the Fourth Circuit·Decided December 26, 2019·No. 18-1703·Published·Cited by 49 cases

Opinion

PUBLISHED

UNITED STATES COURT OF APPEALS FOR THE FOURTH CIRCUIT

No. 18-1703

THE UNITED STATES OF AMERICA FOR THE USE AND BENEFIT OF MODERN MOSAIC, LTD., a foreign business corporation,

Plaintiff – Appellant,

v.

TURNER CONSTRUCTION COMPANY, a New York corporation; TRAVELERS CASUALTY AND SURETY COMPANY OF AMERICA; FEDERAL INSURANCE COMPANY; FIDELITY & DEPOSIT COMPANY OF MARYLAND; ZURICH AMERICAN INSURANCE COMPANY; LIBERTY MUTUAL INSURANCE COMPANY; THE CONTINENTAL INSURANCE COMPANY,

Defendants – Appellees.

Appeal from the United States District Court for the Northern District of West Virginia, at Clarksburg. Frederick P. Stamp, Jr., Senior District Judge. (1:16-cv-00012-FPS-MJA)

Argued: October 31, 2019 Decided: December 26, 2019

Before WYNN, QUATTLEBAUM, and RUSHING, Circuit Judges.

Affirmed by published opinion. Judge Quattlebaum wrote the opinion, in which Judge Wynn and Judge Rushing joined.

ARGUED: Edward J. Sheats, SHEATS & BAILEY, PLLC, Liverpool, New York, for Appellant. Michael David Griffith, Jr., THOMAS COMBS & SPANN, PLLC, Charleston, West Virginia; Douglas Leo Patin, BRADLEY ARANT BOULT CUMMINGS,

Washington, D.C., for Appellees. ON BRIEF: Jeffrey D. Van Volkenburg, Allison S. McClure, MCNEER HIGHLAND MCMUNN & VARNER, Clarksburg, West Virginia, for Appellant. Michael S. Koplan, BRADLEY ARANT BOULT CUMMINGS, Washington, D.C., for Appellees.

QUATTLEBAUM, Circuit Judge:

One of our country’s bedrock principles is the freedom of individuals and entities to enter into contracts and rely that their terms will be enforced. 1 Consistent with that principle, the Federal Bureau of Investigation (the “FBI”) entered into a contract (the “Prime Contract”) with Turner Construction Company (“Turner”), a large general contractor, to build a major FBI facility in West Virginia. Turner then retained various subcontractors to handle particular parts of the project. One of those subcontractors was Modern Mosaic Ltd. (“Modern”), a firm specializing in precast concrete. Turner and Modern entered into a subcontract (the “Subcontract”) outlining Modern’s role in the construction of the FBI facility.

During and after Modern’s work on this project, disputes between it and Turner arose. After attempts to resolve the disputes failed, Modern sued Turner in the United States District Court for the Northern District of West Virginia.

Modern asserts four main claims: (1) it incurred increased costs because Turner improperly failed to “field verify” the existing garage; (2) it was improperly required to incur the cost of a full-time engineer or licensed surveyor on site; (3) it incurred increased

1 That principle, of course, predates American law. Ancient Greek philosopher Plato said “[i]f a man fails to fulfill an agreed contract—unless he had contracted to do something forbidden by law or decree, or gave his consent under some iniquitous pressure, or was involuntarily prevented from fulfilling his contract because of some unlooked-for accident—an action for such an unfulfilled agreement should be brought in the tribal courts . . . .” Plato, The Laws, BOOK 11, § 23, CONTRACTS. In fact, even earlier cultures relied on contracts. Genesis 21:23-27 reports that the Hebrew patriarch Abraham and King Abimelech of Gerar entered into a contract to resolve a dispute about the ownership of a well at Beersheba, now a modern city in Israel’s Negev region.

costs because of the deficient soil remediation work of another subcontractor; and (4) Turner should be estopped from denying Modern’s claims because of its improper conduct regarding a mediation between the FBI and Turner.

Properly applying West Virginia law, 2 the district court rejected all of Modern’s claims based on the plain language of the Subcontract. First, it granted Turner summary judgment on the field verification claim. Then, after a bench trial, it ruled in favor of Turner on the remaining claims. We agree with the district court. These two sophisticated businesses entered into a detailed contract spelling out their rights and responsibilities in the construction of the FBI facility. The provisions of that contract directly address the very issues raised in this appeal. They also compel the result reached by the district court. Thus, we affirm.

I. Field Verification

The bulk of Modern’s contractual responsibilities consisted of fabricating and installing precast concrete panels on an existing parking garage at the FBI facility. Modern prepared the panels in accordance with the dimensions called for in the engineering drawings. During its work, however, Modern discovered that the parking garage was not built to the specified dimensions. As a result, the panels did not fit to the garage. To correct

2 The application of the Miller Act—the basis for federal question jurisdiction in this case—is not disputed. Even so, the predominant acts relevant to the Subcontract and its performance occurred in West Virginia. As such, that law governs contract interpretation. See United States ex rel. Shields, Inc. v. Citizens & S. Nat. Bank of Atlanta, Ga., 367 F.2d 473, 477 (4th Cir. 1966).

this problem, Modern performed remedial work on the panels costing an additional $975,072.31.

Modern argues that Turner was contractually required to field verify that the parking garage was built to the dimensions of the engineering drawings. If done properly, Modern claims, this would have identified the discrepancy between the as-built dimensions and the contractual dimensions before Modern prepared the panels. According to Modern, proper verification would also have prevented the remedial costs it incurred. The district court rejected this claim finding the contractual documents required Modern, not Turner, to conduct field verification.

A.

Modern first challenges the district court’s grant of summary judgment to Turner based on its conclusion that the contracts unambiguously required Modern to field verify the structure. Modern claims that the contracts are ambiguous regarding the responsibility for field verification and that extrinsic evidence supports its interpretation.

This Court reviews a district court’s grant of summary judgment de novo. Variety Stores, Inc. v. Wal-Mart Stores, Inc., 888 F.3d 651, 659 (4th Cir. 2018). Summary judgment is appropriate “if the movant shows that there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.” Id. (quoting Fed. R. Civ. P. 56(a)). In making this determination, “courts must view the evidence in the light most favorable to the nonmoving party and refrain from weigh[ing] the evidence or mak[ing] credibility determinations.” Id. (internal quotation marks omitted) (quoting Lee v. Town of Seaboard, 863 F.3d 323, 327 (4th Cir. 2017)).

In challenging the district court’s summary judgment decision regarding field verification, Modern points to the Prime Contract. Section 010100 of the Prime Contract required Turner to verify and accept the work of previous contractors and compare the contract documents and the as-built conditions for discrepancies. Further, section 010400 required Turner to verify all existing structures and dimensions as shown on the documents. Relying on these provisions, Modern argues Turner was responsible for field verification.

However, Modern ignores the way these two provisions relate to the rest of the contracts. As the district court properly noted, the Prime Contract contains a “flow down” clause. That provision provides that Modern agreed to be bound by “each and all of the terms and provisions” of the Prime Contract and to assume all of the duties, obligations and responsibilities that Turner assumed toward the FBI. (J.A. 22). Based on this language, Modern was responsible for Turner’s obligations under sections 010100 and 010400 of the Prime Contract.

Free access — add to your briefcase to read the full text and ask questions with AI

US f/u/b of Modern Mosaic, Ltd v. Turner Construction Company, 946 F.3d 201 (4th Cir. 2019).

946 F.3d 201 (US f/u/b of Modern Mosaic, Ltd v. Turner Construction Company) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related