US f/u/b of Modern Mosaic, Ltd v. Turner Construction Company

946 F.3d 201
CourtCourt of Appeals for the Fourth Circuit
DecidedDecember 26, 2019
Docket18-1703
StatusPublished
Cited by49 cases

This text of 946 F.3d 201 (US f/u/b of Modern Mosaic, Ltd v. Turner Construction Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
US f/u/b of Modern Mosaic, Ltd v. Turner Construction Company, 946 F.3d 201 (4th Cir. 2019).

Opinion

PUBLISHED

UNITED STATES COURT OF APPEALS FOR THE FOURTH CIRCUIT

No. 18-1703

THE UNITED STATES OF AMERICA FOR THE USE AND BENEFIT OF MODERN MOSAIC, LTD., a foreign business corporation,

Plaintiff – Appellant,

v.

TURNER CONSTRUCTION COMPANY, a New York corporation; TRAVELERS CASUALTY AND SURETY COMPANY OF AMERICA; FEDERAL INSURANCE COMPANY; FIDELITY & DEPOSIT COMPANY OF MARYLAND; ZURICH AMERICAN INSURANCE COMPANY; LIBERTY MUTUAL INSURANCE COMPANY; THE CONTINENTAL INSURANCE COMPANY,

Defendants – Appellees.

Appeal from the United States District Court for the Northern District of West Virginia, at Clarksburg. Frederick P. Stamp, Jr., Senior District Judge. (1:16-cv-00012-FPS-MJA)

Argued: October 31, 2019 Decided: December 26, 2019

Before WYNN, QUATTLEBAUM, and RUSHING, Circuit Judges.

Affirmed by published opinion. Judge Quattlebaum wrote the opinion, in which Judge Wynn and Judge Rushing joined.

ARGUED: Edward J. Sheats, SHEATS & BAILEY, PLLC, Liverpool, New York, for Appellant. Michael David Griffith, Jr., THOMAS COMBS & SPANN, PLLC, Charleston, West Virginia; Douglas Leo Patin, BRADLEY ARANT BOULT CUMMINGS, Washington, D.C., for Appellees. ON BRIEF: Jeffrey D. Van Volkenburg, Allison S. McClure, MCNEER HIGHLAND MCMUNN & VARNER, Clarksburg, West Virginia, for Appellant. Michael S. Koplan, BRADLEY ARANT BOULT CUMMINGS, Washington, D.C., for Appellees.

2 QUATTLEBAUM, Circuit Judge:

One of our country’s bedrock principles is the freedom of individuals and entities

to enter into contracts and rely that their terms will be enforced. 1 Consistent with that

principle, the Federal Bureau of Investigation (the “FBI”) entered into a contract (the

“Prime Contract”) with Turner Construction Company (“Turner”), a large general

contractor, to build a major FBI facility in West Virginia. Turner then retained various

subcontractors to handle particular parts of the project. One of those subcontractors was

Modern Mosaic Ltd. (“Modern”), a firm specializing in precast concrete. Turner and

Modern entered into a subcontract (the “Subcontract”) outlining Modern’s role in the

construction of the FBI facility.

During and after Modern’s work on this project, disputes between it and Turner

arose. After attempts to resolve the disputes failed, Modern sued Turner in the United

States District Court for the Northern District of West Virginia.

Modern asserts four main claims: (1) it incurred increased costs because Turner

improperly failed to “field verify” the existing garage; (2) it was improperly required to

incur the cost of a full-time engineer or licensed surveyor on site; (3) it incurred increased

1 That principle, of course, predates American law. Ancient Greek philosopher Plato said “[i]f a man fails to fulfill an agreed contract—unless he had contracted to do something forbidden by law or decree, or gave his consent under some iniquitous pressure, or was involuntarily prevented from fulfilling his contract because of some unlooked-for accident—an action for such an unfulfilled agreement should be brought in the tribal courts . . . .” Plato, The Laws, BOOK 11, § 23, CONTRACTS. In fact, even earlier cultures relied on contracts. Genesis 21:23-27 reports that the Hebrew patriarch Abraham and King Abimelech of Gerar entered into a contract to resolve a dispute about the ownership of a well at Beersheba, now a modern city in Israel’s Negev region. 3 costs because of the deficient soil remediation work of another subcontractor; and (4)

Turner should be estopped from denying Modern’s claims because of its improper conduct

regarding a mediation between the FBI and Turner.

Properly applying West Virginia law, 2 the district court rejected all of Modern’s

claims based on the plain language of the Subcontract. First, it granted Turner summary

judgment on the field verification claim. Then, after a bench trial, it ruled in favor of Turner

on the remaining claims. We agree with the district court. These two sophisticated

businesses entered into a detailed contract spelling out their rights and responsibilities in

the construction of the FBI facility. The provisions of that contract directly address the very

issues raised in this appeal. They also compel the result reached by the district court. Thus,

we affirm.

I. Field Verification

The bulk of Modern’s contractual responsibilities consisted of fabricating and

installing precast concrete panels on an existing parking garage at the FBI facility. Modern

prepared the panels in accordance with the dimensions called for in the engineering

drawings. During its work, however, Modern discovered that the parking garage was not

built to the specified dimensions. As a result, the panels did not fit to the garage. To correct

2 The application of the Miller Act—the basis for federal question jurisdiction in this case—is not disputed. Even so, the predominant acts relevant to the Subcontract and its performance occurred in West Virginia. As such, that law governs contract interpretation. See United States ex rel. Shields, Inc. v. Citizens & S. Nat. Bank of Atlanta, Ga., 367 F.2d 473, 477 (4th Cir. 1966). 4 this problem, Modern performed remedial work on the panels costing an additional

$975,072.31.

Modern argues that Turner was contractually required to field verify that the parking

garage was built to the dimensions of the engineering drawings. If done properly, Modern

claims, this would have identified the discrepancy between the as-built dimensions and the

contractual dimensions before Modern prepared the panels. According to Modern, proper

verification would also have prevented the remedial costs it incurred. The district court

rejected this claim finding the contractual documents required Modern, not Turner, to

conduct field verification.

A.

Modern first challenges the district court’s grant of summary judgment to Turner

based on its conclusion that the contracts unambiguously required Modern to field verify

the structure. Modern claims that the contracts are ambiguous regarding the responsibility

for field verification and that extrinsic evidence supports its interpretation.

This Court reviews a district court’s grant of summary judgment de novo. Variety

Stores, Inc. v. Wal-Mart Stores, Inc., 888 F.3d 651, 659 (4th Cir. 2018). Summary

judgment is appropriate “if the movant shows that there is no genuine dispute as to any

material fact and the movant is entitled to judgment as a matter of law.” Id. (quoting Fed.

R. Civ. P. 56(a)). In making this determination, “courts must view the evidence in the light

most favorable to the nonmoving party and refrain from weigh[ing] the evidence or

mak[ing] credibility determinations.” Id. (internal quotation marks omitted) (quoting Lee

v. Town of Seaboard, 863 F.3d 323, 327 (4th Cir. 2017)).

5 In challenging the district court’s summary judgment decision regarding field

verification, Modern points to the Prime Contract. Section 010100 of the Prime Contract

required Turner to verify and accept the work of previous contractors and compare the

contract documents and the as-built conditions for discrepancies. Further, section 010400

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
946 F.3d 201, Counsel Stack Legal Research, https://law.counselstack.com/opinion/us-fub-of-modern-mosaic-ltd-v-turner-construction-company-ca4-2019.