Universal Contracting Corp. v. Aug, Unpublished Decision (12-30-2004)

2004 Ohio 7133
CourtOhio Court of Appeals
DecidedDecember 30, 2004
DocketAppeal No. C-030719.
StatusUnpublished
Cited by5 cases

This text of 2004 Ohio 7133 (Universal Contracting Corp. v. Aug, Unpublished Decision (12-30-2004)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Universal Contracting Corp. v. Aug, Unpublished Decision (12-30-2004), 2004 Ohio 7133 (Ohio Ct. App. 2004).

Opinion

OPINION
{¶ 1} Plaintiff-appellant Universal Contracting Corporation ("Universal") appeals from the trial court's entry of judgment notwithstanding the verdict ("JNOV") in favor of defendant-appellee Margo Aug. A jury had awarded Universal $467,154 in damages on its claim that Aug had negligently misrepresented that Preserving Affordable Housing, Inc. ("PAH") had sufficient funds to pay Universal, its general contractor, to complete the $13 million renovation of the Garden Hill Apartments at Winton Terrace, in Cincinnati, Ohio. Aug was PAH's executive officer. The issue in this appeal is whether Aug as a corporate officer could be held separately liable for negligent misrepresentation pursuant to Restatement of the Law 2d, Torts (1965), Section 522 where the parties' contract created a duty to provide ability-to-pay information to Universal. We conclude that the trial court properly entered judgment for Aug on her JNOV motion, where Universal, a sophisticated business entity, after negotiating at arms' length, had entered into an agreement with PAH that imposed a specific duty on PAH to disclose the status of its funding to Universal, and where PAH had breached that duty, and Universal had sued on that breach and recovered economic-loss damages.

FACTS AND PROCEDURE
{¶ 2} PAH was a nonprofit organization in the business of purchasing property in Cincinnati to rehabilitate for use as low-income residential housing. In December 1996, PAH entered into the Winton Terrace renovation contract with Universal. PAH and Universal were the only parties to the contract. Aug signed the contract for PAH in her capacity as its executive officer. Article 3 of the agreement specified PAH's responsibilities. In section 3.11, the contract identified PAH's duty as owner to "furnish, prior to commencing work and at such future times as may be requested, reasonable evidence satisfactory to [Universal] that sufficient funds are available and committed for the entire cost of the Project." The agreement also identified Universal's rights if PAH breached this contracted duty: "Unless such reasonable evidence is furnished, the Construction Manager is not required to commence or continue any Work, or may, if such evidence is not presented within a reasonable time, stop the Project upon 15 days notice to the Owner. The failure of the Construction Manager to insist upon the providing of this evidence at any one time shall not be a waiver of the Owner's obligation to make payments pursuant to this Agreement nor shall it be a waiver of the Construction Manager's right to request or insist that evidence be provided at a later date."

{¶ 3} Almost immediately after work had begun, Universal and PAH identified defects in the architectural plans that required an expansion of the renovation project and an increase in the expenses involved. In August 1998, Universal's president wrote a letter to Aug at PAH outlining his concerns that PAH might lack the funds to complete the enlarged project. Because of federally imposed tax-credit funding restrictions, PAH could not then provide sufficient funding assurances to Universal. Universal threatened to exercise its contractual right to stop work if PAH could not provide additional assurances of funding. At a meeting in November 1998, Aug provided oral assurance that PAH had additional Housing and Urban Development ("HUD") funds and could adequately fund the project. Based upon that representation, Universal rescinded its work-stoppage notice and urged its subcontractors to return to work. But Universal continued to seek written confirmation that funding was available.

{¶ 4} PAH knew that the HUD funds were not forthcoming. PAH endeavored to obtain substitute HUD funding but was not successful. Universal continued working for five more months until April 1999. When PAH was unable to make several payments, Universal stopped work.

{¶ 5} Pursuant to the terms of the contract, in April 1999, Universal filed a claim with the American Arbitration Association alleging that PAH had breached its contractual duty to provide information that sufficient funds were available and seeking money damages. Universal raised no claims of negligent misrepresentation, and Aug was not made a party to the arbitration.

{¶ 6} On July 5, 2000, the arbitration panel awarded Universal and its subcontractors a $4,379,721.10 judgment against PAH. In its detailed arbitration award, the panel found "in favor of Universal against PAH for PAH's breach of contract for its own conduct and that of its representatives, including the conduct of [the project architects]." In the eight-page decision, the panel awarded Universal a total of $2,044,153 for the unpaid balance on work in progress, labor-escalation costs, extended general conditions, extended supervision, lost productivity, unabsorbed office overhead, and demobilization costs. The remaining amounts were awarded to subcontractors Geiler ($902,628), BJ Jacobs ($54,132), Zero-Breeze ($119,563), S/C Shaw ($5,157), Mayers Electric ($274,744), Ooten Interior Systems ($99,031), OK Interiors ($120,778), O'Rourke Construction ($17,380), and Wise Construction ($700,459). On September 22, 2000, in the consolidated cases numbered A-9905309 and A-0004161, the Hamilton County Common Pleas Court confirmed the arbitration award and entered a judgment against PAH subject to 10% interest per annum until payment was made in full.

{¶ 7} According to the affidavit filed in this case by Aug, PAH was unable to fully satisfy the judgment on the breach-of-contract claim. On May 31, 2001, Universal filed this action, alleging that Aug had negligently misrepresented PAH's ability to fund the project and that Universal had relied upon that representation to its detriment by returning to work. Universal sought $4,516,700 in compensatory damages from Aug. Following the denial of Aug's pretrial motions, a jury awarded Universal $467,154 in damages. Aug moved for judgment notwithstanding the verdict pursuant to Civ.R. 50(B). In its well-reasoned 11-page decision, the trial court granted the motion, ruling that while a corporate officer could generally be held liable for torts committed in the course of business, Universal could not proceed in a separate action against Aug for negligent misrepresentation when "[t]he contractual duty of PAH in the arbitration process and the claimed tortuous [sic] conduct of Aug * * * involve[d] the identical duty to provide [correct funding information]."

{¶ 8} When Universal filed this appeal, it was consolidated, for purposes of argument only, with the appeal of a declaratory-judgment action concerning whether Aug would be covered under PAH's directors-and-officers liability policy if Universal obtained a judgment against her.

STANDARD OF REVIEW
{¶ 9} This court's review of the trial court's resolution of Aug's Civ.R. 50(B) JNOV motion involves a question of law and "not questions of fact, although evidence must be reviewed and considered." Meyers v. HotBagels Factory (1999), 131 Ohio App.3d 82, 92, 721 N.E.2d 1068; see, also, Ruta v. Breckenridge-Remy (1982), 69 Ohio St.2d 66, 430 N.E.2d 935

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Geiler Co. v. Hamilton Cty. Pub. Library Bd. of Trustees
2024 Ohio 5793 (Ohio Court of Appeals, 2024)
Cauthen v. Weil
S.D. Ohio, 2023
425 Beecher, L.L.C. v. Unizan Bank, National Ass'n
927 N.E.2d 46 (Ohio Court of Appeals, 2010)
Gmac Mortgage v. Titch, Unpublished Decision (3-2-2005)
2005 Ohio 868 (Ohio Court of Appeals, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
2004 Ohio 7133, Counsel Stack Legal Research, https://law.counselstack.com/opinion/universal-contracting-corp-v-aug-unpublished-decision-12-30-2004-ohioctapp-2004.