[Cite as Geiler Co. v. Hamilton Cty. Pub. Library Bd. of Trustees, 2024-Ohio-5793.]
IN THE COURT OF APPEALS FIRST APPELLATE DISTRICT OF OHIO HAMILTON COUNTY, OHIO
THE GEILER COMPANY, : APPEAL NO. C-240162 TRIAL NO. A-2102261 Plaintiff-Appellant, :
vs. :
BOARD OF TRUSTEES OF THE : PUBLIC LIBRARY OF CINCINNATI OPINION AND HAMILTON COUNTY, :
Defendant-Appellee. :
Civil Appeal From: Hamilton County Court of Common Pleas
Judgment Appealed From Is: Affirmed
Date of Judgment Entry on Appeal: December 11, 2024
Wood & Lamping LLP and C.J. Schmidt, for Plaintiff-Appellant,
Melissa A. Powers, Hamilton County Prosecuting Attorney, and Michael J. Friedmann, Assistant Prosecuting Attorney, for Defendant-Appellee. OHIO FIRST DISTRICT COURT OF APPEALS
ZAYAS, Judge.
{¶1} In this breach-of-contract action, plaintiff-appellant The Geiler
Company (“Geiler”) appeals from the judgment of the Hamilton County Court of
Common Pleas, declining to rule in its favor on its claims against defendant-appellee
Board of Trustees of the Public Library of Cincinnati and Hamilton County (“the
library”) for breach of contract and negligent misrepresentation. Geiler raises two
assignments of error challenging the trial court’s decision as to each claim. For the
reasons that follow, we overrule both assignments of error and affirm the judgment of
the trial court.
I. The TC-05 Contract
{¶2} On April 8, 2019, the library (as the “owner”) entered into a contract
with Geiler (as the “contractor”) for “TC-05—HVAC Upgrades” (“the contract”). The
contract listed the engineer on the project as Motz Consulting Engineers, Inc.,
(“Motz”). The contract provided that Geiler “shall fully execute the Work described in
the contract documents, except as specifically indicated in the Contract Documents to
be the responsibility of others.” Among an abundance of other things, Geiler was
responsible for installation of prepurchased Air Handling Units (“AHUs”). Each AHU
was to be “fabricated so that it can be delivered in proper shipping sections and will be
complete [sic] knocked down at the site to permit entry through openings in the
buildings.” Geiler, as the HVAC contractor, was “responsible to coordinate shipping
sections and knock down and reconstruction with the manufacturer.”
{¶3} Addendum 1 to the contract provides, “This addendum supplements
and amends the project manual and drawings, shall be taken into account in preparing
proposals, and shall become a part of the contract documents.” Addendum 1 includes
“clarifications” based on questions asked at the prebid meeting. Of relevance, the OHIO FIRST DISTRICT COURT OF APPEALS
addendum provides an answer to the question, “Are the units sized according to the
job?” The answer states, “yes the unit reps have walked the spaces, understand the
limitations and have worked with the engineer to size the units to accommodate the
tight working conditions.”
{¶4} Addendum 1 further includes the agenda for the prebid meeting. The
agenda includes a “Scope of Work overview” list. Of relevance, the list states,
“Equipment has been prepurchased and will be shipped to Cincinnati. Contractor
shall coordinate all shipping with manufacturer’s [sic] (EAP-AHUs, and boilers—
Blackmore and Glunt). Contractor shall receive, rig, install, start up, commission
equipment as though it is their own.” The list also states, “Contractors shall make
themselves aware of the pathways necessary to rig the equipment into place (boilers
may require removal of doors and portion of walls; AHU’s will need to be completely
knocked down, rigged into place, and re constructed [sic]).”
II. Events After the Contract
{¶5} In August 2019, EAP—the AHU manufacturer—sent an email to
individuals from Motz, Geiler, and the library, indicating the AHUs would be
“delivered assembled but, without the sealant.” The email said, “This will make the
disassembly easy. Geiler will be able to break them down as small as they need to get
them to the final location.”
{¶6} Doug Weberding, the project manager from Geiler, was included in the
email. Weberding forwarded the email to Jeff Gerrein from the library and said, “This
is not ours to disassemble. We were told they would be in sections and fit through the
doors. We don’t have labor to disassemble these units.”
{¶7} Gerrein forwarded the email to two individuals from Motz—Michael
Murdock and Cody Fralick—with a note that said, “fyi.” Murdock forwarded the email
3 OHIO FIRST DISTRICT COURT OF APPEALS
to Fralick and two others from Motz—Dave Wahoff and Jeff Haynay—with a message
that said, “Guys—what did we say in the spec? I assumed they would come in
individual pieces? Modular?”
{¶8} Haynay responded to the email, adding Gerrein and Weberding to the
email, and said, “All please see attached spec section and pre-bid meeting minutes. It
is clearly called out in both that the AHU’s [sic] would need to be knocked down at the
site and that the shipping sections and reconstruction of the units would need to be
coordinated with the manufacturer.”
{¶9} In October 2019, the AHUs arrived. That same month, Ron Powell from
Motz forwarded the above-mentioned emails to Weberding and said, “After reading
the project documents it is clear the rigging and assembly of the air handler [sic] were
discussed several times and is the responsible [sic] of the mechanical contractor.
Please see excerpts below.” The email then referenced the above-mentioned
provisions of the contract indicating that the AHUs would need to be completely
knocked down.
{¶10} Eventually, on March 27, 2020, Weberding sent a letter to the library
regarding “Air Handler Disassembly and Reassembly Costs.” The letter said:
This is to let you know that as [sic] Friday 3/27/20 The Geiler
Company has finished the last AHU installation for the Hamilton
County Project. It is still our position that the disassembly and
reassembly of the Air Handling Units is a clearly recompensable change
order based on the documents provided during the bid period. The final
approved submittals on the owner provided AHU’s [sic] was not
received by Geiler until June 2019, well after we received the contract.
Attached is the estimated change order cost to date for the
4 OHIO FIRST DISTRICT COURT OF APPEALS
disassembly, reassembly and Electric. It is based on 320 pipefitter
hours per unit to perform the work.
Total cost is $270,238.16. We would assume that you want to
meet with management of Geiler at the first opportunity. Please
indicate your availability.
{¶11} The library ultimately declined to provide the requested additional
compensation.
III. Procedural History
{¶12} In July 2021, Geiler initiated the instant action against the library,
asserting claims for breach of contract and negligent misrepresentation. The breach-
of-contract claim asserted that the library materially breached the contract by failing
to ensure that the AHUs arrived in a manner “suitable for ingress into the Project
property.” The negligent-misrepresentation claim asserted that Geiler justifiably
relied on the library’s misrepresentation that the AHUs would “arrive in a manner that
allowed for easy ingress into the Project property.”
{¶13} The cause eventually proceeded to a three-day bench trial in December
2023, during which the trial court granted a directed verdict on Geiler’s claim for
negligent misrepresentation at the close of Geiler’s case-in-chief. In February 2024,
the trial court entered judgment in favor of the library on Geiler’s claim for breach of
contract. Geiler now appeals.
IV. Law and Analysis
A. First Assignment of Error
{¶14} In its first assignment of error, Geiler challenges the trial court’s denial
of its claim for breach of contract.
{¶15} The trial court denied Geiler’s breach-of-contract claim after finding
5 OHIO FIRST DISTRICT COURT OF APPEALS
that Geiler was contractually required to knockdown the AHUs into the size needed to
get through the pathways, and was contractually required to obtain a change order and
provide the library notice of its claim if it believed that the knockdown work was
outside the scope of the original contract.
{¶16} Geiler challenges these findings, arguing that the contract provided that
the AHUs would arrive disassembled and that it provided proper notice of its claim
under the contract.
{¶17} Because we find the notice issue dispositive of this assignment of error,
we address that issue first.
{¶18} Section 9.1 of the contract provides, “The Contract Sum is stated in the
Agreement and, including authorized adjustments, is the total amount payable by the
Owner to the Contractor for performance of Work under the Contact Documents.”
{¶19} In its breach-of-contact claim, Geiler sought a monetary award of the
increase in costs “in excess of that which was contemplated per the terms of the
contract.” In other words, Geiler was seeking additional costs related to the work it
performed. Thus, consistent with the March 27, 2020 letter, Geiler was seeking an
increase in the Contract Sum.
{¶20} After trial, the trial court found that the Contract Sum remained fixed
as Geiler failed to provide the requisite notice of its claim 1 under Sections 15.1.2 and
15.1.4 of the contract where Geiler did not provide the notice of its claim to the library
until March 27, 2020, after Geiler had completed the work.
1 Section 15.1.1 of the contract provides:
A claim is a demand or assertion by one of the parties seeking, as a matter of right, payment of money, or other relief with respect to the terms of the Contract. The term ‘claim’ also includes other disputes and matters in question between the Owner and the Contractor arising out of or relating to the Contract. The responsibility to substantiate Claims shall rest with the party making the claim.
6 OHIO FIRST DISTRICT COURT OF APPEALS
{¶21} Section 15.1.2 of the contract provides:
Claims by either the Owner or Contractor must be initiated by
written notice to the other party and to the Initial Decision Maker2 with
a copy sent to the Architect, if the Architect is not serving as the Initial
Decision Maker. Claims by either party must be initiated within 21 days
after occurrence of the event giving rise to such Claim or within 21 days
after the claimant first recognizes the condition giving rise to the Claim,
whichever is later.
{¶22} Section 15.1.4 of the General Conditions of the contract provides, “If the
contractor wishes to make a Claim for an increase in the Contract Sum, written notice
as provided herein shall be given before proceeding to execute the Work.”
{¶23} Geiler argues that the trial court erred in finding that it failed to provide
the requisite notice of its claim under the contract where it “properly and timely
asserted a claim” in the August 2019 email from Weberding to Gerrein.
{¶24} “Although the interpretation of a written contract poses a question of
law that we review de novo, where the appellant challenges the trial court’s factual
findings, we apply a manifest-weight-of-the-evidence standard.” Washington v. Am.
Gen. Life Ins. Co., 2022-Ohio-339, ¶ 13 (1st Dist.), citing Qiming He v. Half Price
Heating & Air, 2021-Ohio-1599, ¶ 6 (1st Dist.). “Under this standard of review, we
‘weigh the evidence and all reasonable inferences, consider the credibility of the
witnesses, and determine whether in resolving conflicts in the evidence, the trial court
clearly lost its way and created such a manifest miscarriage of justice that its judgment
must be reversed and a new trial ordered.’” Id., citing Qiming at ¶ 7. “‘In weighing the
2 Under the terms of the contract, Motz was to serve as the initial decision maker.
7 OHIO FIRST DISTRICT COURT OF APPEALS
evidence, we “must always be mindful of the presumption in favor of the finder of
fact.”’” Id., quoting Qiming at ¶ 7.
{¶25} The trial court found that Weberding’s email was not “a notice of claim”
as it failed to, at least, put the library on notice that Geiler was going to make a claim
and provide an estimate of the cost.
{¶26} As previously mentioned, the email from Weberding was sent in
response to an email from the manufacturer about the arrival condition of the AHUs,
and said, “[The AHUs are] not ours to disassemble. We were told they would be in
sections and fit through the doors. We don’t have labor to disassemble these units.”
The email did not contain any express assertion of any right to additional payment
under the contract or demand any other form of relief.
{¶27} At trial, Weberding agreed in his testimony that the email was sent prior
to the AHUs arriving. Significantly, he denied submitting a formal claim once the
AHUs arrived in October 2019. Instead, he agreed that Geiler’s formal claim was the
March 2020 letter, which was sent once “all the units were done.”
{¶28} Additionally, William Geiler—the vice president of Geiler—testified that
the March 2020 letter was the “initial notification” of what Geiler felt the additional
assembly costs would be.
{¶29} Further, David Wahoff—the engineer for Motz—denied in his testimony
that the email asked for an additional contract sum or made a claim for additional
{¶30} Based on this evidence, we cannot conclude that the trial court clearly
lost its way and created a manifest miscarriage of justice when it found that the email
did not serve as notice of Geiler’s claim for an increase in the Contract Sum. See
generally Eastley v. Volkman, 2012-Ohio-2179, ¶ 21, quoting Seasons Coal Co., Inc.
8 OHIO FIRST DISTRICT COURT OF APPEALS
v. Cleveland, 10 Ohio St.3d 77 (1984) (“‘If the evidence is susceptible of more than one
construction, the reviewing court is bound to give it that interpretation which is
consistent with the verdict and judgment, most favorable to sustaining the verdict and
judgment.’”).
{¶31} Beyond that, the March 2020 notice that Geiler sent to the library was
not provided prior to Geiler executing the work, nor was it sent within 21 days after
Geiler was on notice of the disassembly issue or within 21 days after the AHUs arrived
from the manufacturer. Consequently, because the March 2020 notice does not
comply with the contractual requirements for asserting a claim for an increase in the
Contract Sum, we cannot find error in the trial court’s determination that Geiler failed
to provide the requisite notice of its claim under Sections 15.1.2 and 15.1.4 of the
contract in order to prevail on its claim for breach of contract. Accordingly, we
overrule the first assignment of error and affirm the judgment of the trial court as to
Geiler’s claim for breach of contract.
B. Second Assignment of Error
{¶32} In its second assignment of error, Geiler argues that the trial court erred
in granting the library’s motion for a directed verdict on its claim for negligent
misrepresentation.
{¶33} As an initial matter, in a bench trial, “a motion for judgment at the
conclusion of the plaintiff’s evidence is one for dismissal under Civ.R. 41(B)(2), not a
motion for a directed verdict under Civ.R. 50.” Beal v. Bauer, 2014-Ohio-614, ¶ 8 (1st
Dist.), citing St. Clair v. Person, 2002-Ohio-1129 (1st Dist.).
{¶34} The library moved for a “directed verdict” at the close of Geiler’s case,
rather than a dismissal, and the trial court said that it was granting the motion. While
this is technically improper in a bench trial, “courts reason that no prejudice results
9 OHIO FIRST DISTRICT COURT OF APPEALS
from the erroneous application of the directed verdict standard because the standard
is ‘“much more rigorous than the involuntary dismissal standard,”’ and thus,
‘“satisfaction of the Civ.R. 50(A) standard implies satisfaction of the Civ.R. 41(B)(2)
standard.”’” (Citation omitted.) Jarupan v. Hanna, 2007-Ohio-5081, ¶ 10 (10th
Dist.). Consequently, the trial court’s granting of the library’s motion for a directed
verdict was harmless error, so long as dismissal was appropriate under Civ.R. 41(B)(2).
{¶35} In relevant part, Civ.R. 41(B)(2) provides:
After the plaintiff, in an action tried by the court without a jury,
has completed the presentation of the plaintiff's evidence, the
defendant, without waiving the right to offer evidence in the event the
motion is not granted, may move for a dismissal on the ground that
upon the facts and the law the plaintiff has shown no right to relief. The
court as trier of the facts may then determine them and render judgment
against the plaintiff or may decline to render any judgment until the
close of all the evidence.
{¶36} “Civ.R. 41(B)(2) allows a trial court to determine the facts by weighing
the evidence and resolving any conflicts therein.” (Citations omitted.) Jarupan at ¶
9. “If, after evaluating the evidence, a trial court finds that the plaintiff has failed to
meet [his or] her burden of proof, then the trial court may enter judgment in the
defendant’s favor.” Id.
{¶37} This court must uphold a dismissal under Civ.R. 41(B)(2) “unless we
find it to be erroneous at a matter of law or against the manifest weight of the
evidence.” Beal, 2014-Ohio-614, at ¶ 9 (1st Dist.), citing Goering v. Chriscon Builders,
Ltd., 2011-Ohio-5480, ¶ 16 (1st Dist.).
{¶38} The tort of negligent misrepresentation:
10 OHIO FIRST DISTRICT COURT OF APPEALS
provides that “one who, in the course of his business, profession or
employment, or in any other transaction in which he has a pecuniary
interest, supplies false information for the guidance of others in their
business transactions, is subject to liability for economic loss caused to
them by their justifiable reliance upon the information, if he fails to
exercise reasonable care or competence in obtaining or communicating
the information.”
(Emphasis in original.) Universal Contr. Corp. v. Aug, 2004-Ohio-7133, ¶ 11 (1st
Dist.), quoting Delman v. Cleveland Hts., 41 Ohio St.3d 1, 4 (1989). “In negligent-
misrepresentation claims, the scope of the special duty and the scope of the
permissible recovery will vary on a case-by-case basis.” Id. at ¶ 16.
{¶39} Geiler’s negligent-misrepresentation claim is premised on the assertion
that the library is liable for making false representations during the bidding process.
It derives from a statement that was made in Addendum 1 to a separate contract, TC-
02, which is the contract between EAP and the library for purchase of the AHUs.
Notably, the TC-02 contract is not a part of the TC-05 contract, nor is Geiler a party to
the TC-02 contract.
{¶40} In the TC-02 addendum, there is a “mechanical equipment
clarifications section.” It provides a response to the question, “Does the unit have to
arrive assembled or can it come crates [sic] labeled for assembly?” The answer, in
part, provides, “It is the responsibility of the manufacturer to provide the equipment
components in size, orientation and configuration that will allow transport to the final
installation point.” Geiler claims that it relied upon this statement (the “TC-02
statement”) when it prepared its bid for the TC-05 contract.
{¶41} The library moved for a judgment as a matter of law on this claim,
11 OHIO FIRST DISTRICT COURT OF APPEALS
arguing that “the [TC-05] contract controlled the case,” because, by signing the
contract, Geiler warranted that it had read all the bidding documents and reported any
errors or inconsistencies that needed clarification prior to signing. In response, Geiler
argued that its reliance on the TC-02 statement was reasonable. The trial court
ultimately dismissed the claim after finding that “the case really is about the [TC-05]
contract.”
{¶42} Geiler now argues that the trial court erred as a matter of law in finding
that the library’s “misrepresentations were assumed into the TC-05 contract” as the
TC-02 statement was made prior to the formation of the contract and the bid package
obligated all bidders to “familiarize themselves with all the bidding documents
including the bidding documents for other portions of the Project.”
{¶43} However, the TC-05 contract expressly states, at the start of the
contract, that it “represents the entire and integrated agreement between the parties
hereto and supersedes prior negotiations, representations or agreements, either
written or oral.” (Emphasis added.)
{¶44} The Ohio Supreme Court has held that a contractor should not be
permitted to circumvent its contract terms by virtue of labeling the action a tort. See
Universal, 2004-Ohio-7133, at ¶ 19 (1st Dist.), citing Foster Wheeler Enviresponse v.
Franklin Cty. Convention Facilities Auth., 78 Ohio St.3d 353, 367 (1997).
{¶45} Consistent with this principle, Geiler should not be permitted to
circumvent its own contract terms by bringing a negligent-misrepresentation claim
based on documents that were submitted to bidders for a separate contract prior to
the date on which it entered its own contract with the library on the same subject
matter.
{¶46} Nevertheless, even assuming Geiler could assert a claim for negligent
12 OHIO FIRST DISTRICT COURT OF APPEALS
misrepresentation in this situation, we hold that Geiler could not, as a matter of law,
have justifiably relied on the alleged misrepresentation made during the bidding
process where the contract expressly put Geiler on notice to not rely on prior
representations as the contract superseded any prior negotiations, representations or
agreements made. See generally Foster Wheeler at 366, citing R.J. Wildner
Contracting Co., Inc. v. Ohio Turnpike Comm., 913 F.Supp. 1031, 1040 (N.D.Ohio
1996).
{¶47} Therefore, we hold that the trial court did not err in dismissing Geiler’s
claim for negligent misrepresentation as a matter of law. Accordingly, we overrule the
second assignment of error and affirm the judgment of the trial court as to Geiler’s
claim for negligent misrepresentation.
V. Conclusion
{¶48} Based on the foregoing, we overrule the assignments of error and affirm
the judgment of the trial court.
Judgment affirmed.
BOCK, P.J., and BERGERON, J., concur.
Please note:
The court has recorded its entry on the date of the release of this opinion.