Geiler Co. v. Hamilton Cty. Pub. Library Bd. of Trustees

2024 Ohio 5793
CourtOhio Court of Appeals
DecidedDecember 11, 2024
DocketC-240162
StatusPublished
Cited by1 cases

This text of 2024 Ohio 5793 (Geiler Co. v. Hamilton Cty. Pub. Library Bd. of Trustees) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Geiler Co. v. Hamilton Cty. Pub. Library Bd. of Trustees, 2024 Ohio 5793 (Ohio Ct. App. 2024).

Opinion

[Cite as Geiler Co. v. Hamilton Cty. Pub. Library Bd. of Trustees, 2024-Ohio-5793.]

IN THE COURT OF APPEALS FIRST APPELLATE DISTRICT OF OHIO HAMILTON COUNTY, OHIO

THE GEILER COMPANY, : APPEAL NO. C-240162 TRIAL NO. A-2102261 Plaintiff-Appellant, :

vs. :

BOARD OF TRUSTEES OF THE : PUBLIC LIBRARY OF CINCINNATI OPINION AND HAMILTON COUNTY, :

Defendant-Appellee. :

Civil Appeal From: Hamilton County Court of Common Pleas

Judgment Appealed From Is: Affirmed

Date of Judgment Entry on Appeal: December 11, 2024

Wood & Lamping LLP and C.J. Schmidt, for Plaintiff-Appellant,

Melissa A. Powers, Hamilton County Prosecuting Attorney, and Michael J. Friedmann, Assistant Prosecuting Attorney, for Defendant-Appellee. OHIO FIRST DISTRICT COURT OF APPEALS

ZAYAS, Judge.

{¶1} In this breach-of-contract action, plaintiff-appellant The Geiler

Company (“Geiler”) appeals from the judgment of the Hamilton County Court of

Common Pleas, declining to rule in its favor on its claims against defendant-appellee

Board of Trustees of the Public Library of Cincinnati and Hamilton County (“the

library”) for breach of contract and negligent misrepresentation. Geiler raises two

assignments of error challenging the trial court’s decision as to each claim. For the

reasons that follow, we overrule both assignments of error and affirm the judgment of

the trial court.

I. The TC-05 Contract

{¶2} On April 8, 2019, the library (as the “owner”) entered into a contract

with Geiler (as the “contractor”) for “TC-05—HVAC Upgrades” (“the contract”). The

contract listed the engineer on the project as Motz Consulting Engineers, Inc.,

(“Motz”). The contract provided that Geiler “shall fully execute the Work described in

the contract documents, except as specifically indicated in the Contract Documents to

be the responsibility of others.” Among an abundance of other things, Geiler was

responsible for installation of prepurchased Air Handling Units (“AHUs”). Each AHU

was to be “fabricated so that it can be delivered in proper shipping sections and will be

complete [sic] knocked down at the site to permit entry through openings in the

buildings.” Geiler, as the HVAC contractor, was “responsible to coordinate shipping

sections and knock down and reconstruction with the manufacturer.”

{¶3} Addendum 1 to the contract provides, “This addendum supplements

and amends the project manual and drawings, shall be taken into account in preparing

proposals, and shall become a part of the contract documents.” Addendum 1 includes

“clarifications” based on questions asked at the prebid meeting. Of relevance, the OHIO FIRST DISTRICT COURT OF APPEALS

addendum provides an answer to the question, “Are the units sized according to the

job?” The answer states, “yes the unit reps have walked the spaces, understand the

limitations and have worked with the engineer to size the units to accommodate the

tight working conditions.”

{¶4} Addendum 1 further includes the agenda for the prebid meeting. The

agenda includes a “Scope of Work overview” list. Of relevance, the list states,

“Equipment has been prepurchased and will be shipped to Cincinnati. Contractor

shall coordinate all shipping with manufacturer’s [sic] (EAP-AHUs, and boilers—

Blackmore and Glunt). Contractor shall receive, rig, install, start up, commission

equipment as though it is their own.” The list also states, “Contractors shall make

themselves aware of the pathways necessary to rig the equipment into place (boilers

may require removal of doors and portion of walls; AHU’s will need to be completely

knocked down, rigged into place, and re constructed [sic]).”

II. Events After the Contract

{¶5} In August 2019, EAP—the AHU manufacturer—sent an email to

individuals from Motz, Geiler, and the library, indicating the AHUs would be

“delivered assembled but, without the sealant.” The email said, “This will make the

disassembly easy. Geiler will be able to break them down as small as they need to get

them to the final location.”

{¶6} Doug Weberding, the project manager from Geiler, was included in the

email. Weberding forwarded the email to Jeff Gerrein from the library and said, “This

is not ours to disassemble. We were told they would be in sections and fit through the

doors. We don’t have labor to disassemble these units.”

{¶7} Gerrein forwarded the email to two individuals from Motz—Michael

Murdock and Cody Fralick—with a note that said, “fyi.” Murdock forwarded the email

3 OHIO FIRST DISTRICT COURT OF APPEALS

to Fralick and two others from Motz—Dave Wahoff and Jeff Haynay—with a message

that said, “Guys—what did we say in the spec? I assumed they would come in

individual pieces? Modular?”

{¶8} Haynay responded to the email, adding Gerrein and Weberding to the

email, and said, “All please see attached spec section and pre-bid meeting minutes. It

is clearly called out in both that the AHU’s [sic] would need to be knocked down at the

site and that the shipping sections and reconstruction of the units would need to be

coordinated with the manufacturer.”

{¶9} In October 2019, the AHUs arrived. That same month, Ron Powell from

Motz forwarded the above-mentioned emails to Weberding and said, “After reading

the project documents it is clear the rigging and assembly of the air handler [sic] were

discussed several times and is the responsible [sic] of the mechanical contractor.

Please see excerpts below.” The email then referenced the above-mentioned

provisions of the contract indicating that the AHUs would need to be completely

knocked down.

{¶10} Eventually, on March 27, 2020, Weberding sent a letter to the library

regarding “Air Handler Disassembly and Reassembly Costs.” The letter said:

This is to let you know that as [sic] Friday 3/27/20 The Geiler

Company has finished the last AHU installation for the Hamilton

County Project. It is still our position that the disassembly and

reassembly of the Air Handling Units is a clearly recompensable change

order based on the documents provided during the bid period. The final

approved submittals on the owner provided AHU’s [sic] was not

received by Geiler until June 2019, well after we received the contract.

Attached is the estimated change order cost to date for the

4 OHIO FIRST DISTRICT COURT OF APPEALS

disassembly, reassembly and Electric. It is based on 320 pipefitter

hours per unit to perform the work.

Total cost is $270,238.16. We would assume that you want to

meet with management of Geiler at the first opportunity. Please

indicate your availability.

{¶11} The library ultimately declined to provide the requested additional

compensation.

III. Procedural History

{¶12} In July 2021, Geiler initiated the instant action against the library,

asserting claims for breach of contract and negligent misrepresentation. The breach-

of-contract claim asserted that the library materially breached the contract by failing

to ensure that the AHUs arrived in a manner “suitable for ingress into the Project

property.” The negligent-misrepresentation claim asserted that Geiler justifiably

relied on the library’s misrepresentation that the AHUs would “arrive in a manner that

allowed for easy ingress into the Project property.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Loyalty 360, Inc. v. Empirical Edge, Inc.
2025 Ohio 2134 (Ohio Court of Appeals, 2025)

Cite This Page — Counsel Stack

Bluebook (online)
2024 Ohio 5793, Counsel Stack Legal Research, https://law.counselstack.com/opinion/geiler-co-v-hamilton-cty-pub-library-bd-of-trustees-ohioctapp-2024.