Geiler Co. v. Hamilton Cty. Pub. Library Bd. of Trustees

2024 Ohio 5793
Ohio Court of Appeals·Decided December 11, 2024·No. C-240162·Published·Cited by 1 cases

Opinion

IN THE COURT OF APPEALS

FIRST APPELLATE DISTRICT OF OHIO HAMILTON COUNTY, OHIO

THE GEILER COMPANY, : APPEAL NO. C-240162 TRIAL NO. A-2102261 Plaintiff-Appellant, :

vs. :

BOARD OF TRUSTEES OF THE : PUBLIC LIBRARY OF CINCINNATI OPINION AND HAMILTON COUNTY, :

Defendant-Appellee. :

Civil Appeal From: Hamilton County Court of Common Pleas Judgment Appealed From Is: Affirmed Date of Judgment Entry on Appeal: December 11, 2024

Wood & Lamping LLP and C.J. Schmidt, for Plaintiff-Appellant,

Melissa A. Powers, Hamilton County Prosecuting Attorney, and Michael J. Friedmann, Assistant Prosecuting Attorney, for Defendant-Appellee.

ZAYAS, Judge.

{¶1} In this breach-of-contract action, plaintiff-appellant The Geiler Company (“Geiler”) appeals from the judgment of the Hamilton County Court of Common Pleas, declining to rule in its favor on its claims against defendant-appellee Board of Trustees of the Public Library of Cincinnati and Hamilton County (“the library”) for breach of contract and negligent misrepresentation. Geiler raises two assignments of error challenging the trial court’s decision as to each claim. For the reasons that follow, we overrule both assignments of error and affirm the judgment of the trial court.

I. The TC-05 Contract

{¶2} On April 8, 2019, the library (as the “owner”) entered into a contract with Geiler (as the “contractor”) for “TC-05—HVAC Upgrades” (“the contract”). The contract listed the engineer on the project as Motz Consulting Engineers, Inc., (“Motz”). The contract provided that Geiler “shall fully execute the Work described in the contract documents, except as specifically indicated in the Contract Documents to be the responsibility of others.” Among an abundance of other things, Geiler was responsible for installation of prepurchased Air Handling Units (“AHUs”). Each AHU was to be “fabricated so that it can be delivered in proper shipping sections and will be complete [sic] knocked down at the site to permit entry through openings in the buildings.” Geiler, as the HVAC contractor, was “responsible to coordinate shipping sections and knock down and reconstruction with the manufacturer.”

{¶3} Addendum 1 to the contract provides, “This addendum supplements and amends the project manual and drawings, shall be taken into account in preparing proposals, and shall become a part of the contract documents.” Addendum 1 includes “clarifications” based on questions asked at the prebid meeting. Of relevance, the

addendum provides an answer to the question, “Are the units sized according to the job?” The answer states, “yes the unit reps have walked the spaces, understand the limitations and have worked with the engineer to size the units to accommodate the tight working conditions.”

{¶4} Addendum 1 further includes the agenda for the prebid meeting. The agenda includes a “Scope of Work overview” list. Of relevance, the list states, “Equipment has been prepurchased and will be shipped to Cincinnati. Contractor shall coordinate all shipping with manufacturer’s [sic] (EAP-AHUs, and boilers— Blackmore and Glunt). Contractor shall receive, rig, install, start up, commission equipment as though it is their own.” The list also states, “Contractors shall make themselves aware of the pathways necessary to rig the equipment into place (boilers may require removal of doors and portion of walls; AHU’s will need to be completely knocked down, rigged into place, and re constructed [sic]).”

II. Events After the Contract

{¶5} In August 2019, EAP—the AHU manufacturer—sent an email to individuals from Motz, Geiler, and the library, indicating the AHUs would be “delivered assembled but, without the sealant.” The email said, “This will make the disassembly easy. Geiler will be able to break them down as small as they need to get them to the final location.”

{¶6} Doug Weberding, the project manager from Geiler, was included in the email. Weberding forwarded the email to Jeff Gerrein from the library and said, “This is not ours to disassemble. We were told they would be in sections and fit through the doors. We don’t have labor to disassemble these units.”

{¶7} Gerrein forwarded the email to two individuals from Motz—Michael Murdock and Cody Fralick—with a note that said, “fyi.” Murdock forwarded the email

to Fralick and two others from Motz—Dave Wahoff and Jeff Haynay—with a message that said, “Guys—what did we say in the spec? I assumed they would come in individual pieces? Modular?”

{¶8} Haynay responded to the email, adding Gerrein and Weberding to the email, and said, “All please see attached spec section and pre-bid meeting minutes. It is clearly called out in both that the AHU’s [sic] would need to be knocked down at the site and that the shipping sections and reconstruction of the units would need to be coordinated with the manufacturer.”

{¶9} In October 2019, the AHUs arrived. That same month, Ron Powell from Motz forwarded the above-mentioned emails to Weberding and said, “After reading the project documents it is clear the rigging and assembly of the air handler [sic] were discussed several times and is the responsible [sic] of the mechanical contractor. Please see excerpts below.” The email then referenced the above-mentioned provisions of the contract indicating that the AHUs would need to be completely knocked down.

{¶10} Eventually, on March 27, 2020, Weberding sent a letter to the library regarding “Air Handler Disassembly and Reassembly Costs.” The letter said:

This is to let you know that as [sic] Friday 3/27/20 The Geiler Company has finished the last AHU installation for the Hamilton County Project. It is still our position that the disassembly and reassembly of the Air Handling Units is a clearly recompensable change order based on the documents provided during the bid period. The final approved submittals on the owner provided AHU’s [sic] was not received by Geiler until June 2019, well after we received the contract.

Attached is the estimated change order cost to date for the

disassembly, reassembly and Electric. It is based on 320 pipefitter hours per unit to perform the work.

Total cost is $270,238.16. We would assume that you want to meet with management of Geiler at the first opportunity. Please indicate your availability.

{¶11} The library ultimately declined to provide the requested additional compensation.

III. Procedural History

{¶12} In July 2021, Geiler initiated the instant action against the library, asserting claims for breach of contract and negligent misrepresentation. The breach- of-contract claim asserted that the library materially breached the contract by failing to ensure that the AHUs arrived in a manner “suitable for ingress into the Project property.” The negligent-misrepresentation claim asserted that Geiler justifiably relied on the library’s misrepresentation that the AHUs would “arrive in a manner that allowed for easy ingress into the Project property.”

{¶13} The cause eventually proceeded to a three-day bench trial in December 2023, during which the trial court granted a directed verdict on Geiler’s claim for negligent misrepresentation at the close of Geiler’s case-in-chief. In February 2024, the trial court entered judgment in favor of the library on Geiler’s claim for breach of contract. Geiler now appeals.

IV. Law and Analysis A. First Assignment of Error

{¶14} In its first assignment of error, Geiler challenges the trial court’s denial of its claim for breach of contract.

{¶15} The trial court denied Geiler’s breach-of-contract claim after finding

that Geiler was contractually required to knockdown the AHUs into the size needed to get through the pathways, and was contractually required to obtain a change order and provide the library notice of its claim if it believed that the knockdown work was outside the scope of the original contract.

{¶16} Geiler challenges these findings, arguing that the contract provided that the AHUs would arrive disassembled and that it provided proper notice of its claim under the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Geiler Co. v. Hamilton Cty. Pub. Library Bd. of Trustees, 2024 Ohio 5793 (Ohio Ct. App. 2024).

2024 Ohio 5793 (Geiler Co. v. Hamilton Cty. Pub. Library Bd. of Trustees) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Loyalty 360, Inc. v. Empirical Edge, Inc.
2025 Ohio 2134 (Ohio Court of Appeals, 2025)